IDOT contract 61L95 bid tabulation
Aurora, section 25-00371-00-RS. Let by Illinois DOT on January 16, 2026, Kane, District 01. 3 bids received; low bid $3,133,675 by Geneva Construction Company.
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 50
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Geneva Construction Company | $3,133,675 | Low |
| 2 | Builders Paving, LLC | $3,162,148 | +1.0% |
| 3 | Plote Construction, Inc. | $3,391,016 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geneva Construction Company | 2. Builders Paving, LLC | 3. Plote Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | Driveway remov & repl (X4400080) | SY | 80 | $135.00 | $130.00 | $113.00 |
| 2 | CC&G RMVL repl < = 10 (X4400501) | LF | 600 | $62.00 | $67.50 | $75.00 |
| 3 | CC&G RMVL repl > 10FT (X4400503) | LF | 1,400 | $58.00 | $67.50 | $65.70 |
| 4 | Sanitary manhole adj (X6026050) | EACH | 6 | $1,400.00 | $1,000.00 | $1,000.00 |
| 5 | FR & lids adjust SPL (X6030310) | EACH | 127 | $0.01 | $1,150.00 | $500.00 |
| 6 | Temp info signing (X7200061) | SF | 320 | $16.00 | $18.00 | $18.00 |
| 7 | Det loop repl (X8860105) | LF | 1,400 | $20.12 | $20.15 | $20.12 |
| 8 | Topsoil F & P 4 (21101615) | SY | 1,920 | $1.00 | $4.12 | $0.10 |
| 9 | Sodding salt tolerant (25200110) | SY | 1,920 | $23.00 | $21.00 | $23.00 |
| 10 | Supple watering (25200200) | UNIT | 103.70 | $0.10 | $0.01 | $0.10 |
| 11 | Sub gran mat B (31101000) | TON | 415 | $21.32 | $20.00 | $1.00 |
| 12 | Bit matls tack CT (40600290) | LB | 61,581 | $0.01 | $0.01 | $0.01 |
| 13 | Long joint sealant (40600370) | LF | 35,380 | $3.50 | $3.55 | $3.55 |
| 14 | Mix CR JTS flangewys (40600400) | TON | 36.50 | $200.00 | $550.00 | $800.00 |
| 15 | HMA surf rem butt JT (40600982) | SY | 792 | $20.00 | $35.00 | $9.00 |
| 16 | P HMA BC IL-4.75 N50 (40603200) | TON | 5,018 | $114.00 | $103.00 | $127.00 |
| 17 | HMA SC IL-9.5 D N50 (40604060) | TON | 3,750 | $92.00 | $78.00 | $100.00 |
| 18 | HMA SC IL-9.5 D N70 (40604062) | TON | 6,469 | $94.00 | $80.00 | $93.00 |
| 19 | PC conc sidewalk 5 (42400200) | SF | 7,275 | $11.00 | $16.00 | $12.00 |
| 20 | Detectable warnings (42400800) | SF | 660 | $33.00 | $26.50 | $36.00 |
| 21 | HMA surf rem 3 (44000161) | SY | 91,231 | $3.90 | $5.15 | $5.50 |
| 22 | HMA surf rem 4 (44000165) | SY | 452 | $23.00 | $24.50 | $10.00 |
| 23 | Sidewalk rem (44000600) | SF | 7,275 | $2.00 | $1.50 | $2.00 |
| 24 | CL D patch T1 9 (44201749) | SY | 550 | $45.00 | $40.00 | $40.00 |
| 25 | CL D patch T2 9 (44201753) | SY | 1,090 | $45.00 | $40.00 | $30.00 |
| 26 | CL D patch T3 9 (44201757) | SY | 2,190 | $45.00 | $40.00 | $30.00 |
| 27 | CL D patch T4 9 (44201759) | SY | 1,640 | $45.00 | $40.00 | $30.00 |
| 28 | Agg wedge SHLD type B (48102100) | TON | 684 | $55.00 | $40.00 | $76.00 |
| 29 | Man reconst (60257900) | EACH | 2 | $1,850.00 | $1,200.00 | $1,200.00 |
| 30 | FR & lids T1 ADA compl OL (60406001) | EACH | 2 | $450.00 | $480.00 | $480.00 |
| 31 | FR & lids T1 CL (60406100) | EACH | 1 | $450.00 | $480.00 | $480.00 |
| 32 | Corrugated med mod (60624620) | SF | 4,068 | $12.00 | $15.50 | $13.00 |
| 33 | Mobilization (67100100) | LS | 1 | $188,500 | $178,862 | $203,460 |
| 34 | TR cont & prot 701501 (70102620) | LS | 1 | $55,000 | $16,000 | $86,200 |
| 35 | TR cont & prot 701502 (70102622) | LS | 1 | $10,000 | $2,000.00 | $2,000.00 |
| 36 | TR cont & prot 701601 (70102630) | LS | 1 | $10,000 | $3,000.00 | $3,000.00 |
| 37 | TR cont & prot 701701 (70102635) | LS | 1 | $10,000 | $2,000.00 | $2,000.00 |
| 38 | TR cont & prot 701801 (70102640) | LS | 1 | $10,000 | $1,000.00 | $1,000.00 |
| 39 | Short term pavt mking (70300100) | LF | 18,060 | $1.00 | $1.15 | $0.75 |
| 40 | SHRT TRM pavt MK rem (70300150) | SF | 6,020 | $1.00 | $2.00 | $0.01 |
| 41 | THPL PVT MK LTR & sym (78000100) | SF | 875 | $5.50 | $5.00 | $5.00 |
| 42 | THPL PVT MK line 4 (78000200) | LF | 47,216 | $0.76 | $0.85 | $0.85 |
| 43 | THPL PVT MK line 6 (78000400) | LF | 7,303 | $1.25 | $1.25 | $1.25 |
| 44 | THPL PVT MK line 12 (78000600) | LF | 3,740 | $2.70 | $3.00 | $3.00 |
| 45 | THPL PVT MK line 24 (78000650) | LF | 934 | $5.50 | $5.00 | $5.00 |
| 46 | GRV RCSD PM LTR & sym (78011000) | SF | 875 | $9.40 | $3.00 | $3.00 |
| 47 | GRV RCSD PVT MRKG 5 (78011025) | LF | 47,216 | $0.38 | $0.35 | $0.35 |
| 48 | GRV RCSD PVT MRKG 7 (78011035) | LF | 7,303 | $0.65 | $0.50 | $0.50 |
| 49 | GRV RCSD PVT MRKG 13 (78011065) | LF | 3,740 | $1.42 | $1.00 | $1.00 |
| 50 | GRV RCSD PVT MRKG 25 (78011125) | LF | 934 | $6.50 | $3.00 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.