IDOT contract 62W50 bid tabulation
Section 2023-928-RS,SW. Let by Illinois DOT on April 25, 2025, Cook, District 01. 3 bids received; low bid $458,691 by Schroeder Asphalt Services, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 51
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Schroeder Asphalt Services, Inc. | $458,691 | Low |
| 2 | Builders Paving, LLC | $519,894 | +13% |
| 3 | Peter Baker & Son Co. | $522,910 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Schroeder Asphalt Services, Inc. | 2. Builders Paving, LLC | 3. Peter Baker & Son Co. |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $8,500.00 | $5,000.00 | $3,000.00 |
| 2 | Grading & shap SHLDRS (X2020110) | UNIT | 51 | $40.00 | $150.00 | $50.00 |
| 3 | Driveway remov & repl (X4400080) | SY | 11 | $60.00 | $95.00 | $35.00 |
| 4 | CC&G RMVL repl < = 10 (X4400501) | LF | 65 | $73.00 | $200.00 | $65.00 |
| 5 | CC&G RMVL repl > 10FT (X4400503) | LF | 130 | $73.00 | $200.00 | $65.00 |
| 6 | SS cleaned 12 (X5537800) | LF | 150 | $5.50 | $5.00 | $3.50 |
| 7 | FR & lids adjust SPL (X6030310) | EACH | 6 | $1,850.00 | $1,650.00 | $1,350.00 |
| 8 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $3,000.00 | $3,300.00 | $1,000.00 |
| 9 | Drainage STR cleaned (Z0018500) | EACH | 10 | $550.00 | $500.00 | $300.00 |
| 10 | Temp info signing (Z0030850) | SF | 52 | $20.00 | $20.00 | $18.00 |
| 11 | Earth excavation (20200100) | CY | 15 | $80.00 | $95.00 | $65.00 |
| 12 | Topsoil F & P 4 (21101615) | SY | 65 | $12.00 | $10.00 | $30.00 |
| 13 | Sodding salt tolerant (25200110) | SY | 65 | $10.00 | $90.00 | $54.00 |
| 14 | Perimeter eros bar (28000400) | LF | 2,575 | $3.75 | $3.25 | $2.85 |
| 15 | Bit matls tack CT (40600290) | LB | 9,007 | $0.01 | $0.01 | $0.01 |
| 16 | Long joint sealant (40600370) | LF | 7,500 | $3.20 | $3.12 | $3.60 |
| 17 | Mix CR JTS flangewys (40600400) | TON | 31 | $300.00 | $590.00 | $150.00 |
| 18 | HMA surf rem butt JT (40600982) | SY | 140 | $8.00 | $15.00 | $1.00 |
| 19 | HMA repl over patch (40601005) | TON | 50 | $130.00 | $132.00 | $80.00 |
| 20 | HMA SC IL-9.5 D N70 (40604062) | TON | 1,685 | $89.00 | $77.50 | $89.00 |
| 21 | Protective coat (42001300) | SY | 130 | $3.30 | $1.00 | $3.00 |
| 22 | PC conc sidewalk 5 (42400200) | SF | 450 | $16.50 | $20.00 | $15.00 |
| 23 | Detectable warnings (42400800) | SF | 90 | $72.00 | $45.00 | $65.00 |
| 24 | HMA surf rem 1 1/2 (44000155) | SY | 20,015 | $1.65 | $3.00 | $3.00 |
| 25 | Sidewalk rem (44000600) | SF | 450 | $5.50 | $10.00 | $5.00 |
| 26 | HMA RM OV patch 2 1/2 (44002210) | SY | 340 | $45.00 | $11.60 | $3.00 |
| 27 | CL D patch T2 10 (44201765) | SY | 105 | $98.00 | $130.00 | $207.50 |
| 28 | CL D patch T3 10 (44201769) | SY | 130 | $94.00 | $130.00 | $173.00 |
| 29 | CL D patch T4 10 (44201771) | SY | 105 | $98.00 | $130.00 | $164.00 |
| 30 | Agg wedge SHLD type B (48102100) | TON | 127 | $65.00 | $54.00 | $87.00 |
| 31 | FR & lids T1 CL (60406100) | EACH | 1 | $600.00 | $550.00 | $352.00 |
| 32 | Non SPL waste disposl (66900200) | CY | 15 | $80.00 | $100.00 | $65.00 |
| 33 | Soil disposal analy (66900530) | EACH | 3 | $1,175.00 | $1,050.00 | $1,050.00 |
| 34 | Reg sub P-const plan (66901001) | LS | 1 | $500.00 | $4,650.00 | $4,650.00 |
| 35 | Reg sub F con report (66901003) | LS | 1 | $550.00 | $500.00 | $500.00 |
| 36 | Reg sub mon (66901006) | CAL DAY | 4 | $800.00 | $700.00 | $700.00 |
| 37 | Mobilization (67100100) | LS | 1 | $10,000 | $47,688 | $68,299 |
| 38 | TR cont & prot 701501 (70102620) | LS | 1 | $13,000 | $8,985.43 | $22,930 |
| 39 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 40 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 41 | Short term pavt mking (70300100) | LF | 5,135 | $2.00 | $0.01 | $0.01 |
| 42 | SHRT TRM pavt MK rem (70300150) | SF | 1,715 | $3.00 | $0.01 | $0.01 |
| 43 | Temp PVT MK line 4 - paint (70300221) | LF | 18,810 | $0.36 | $0.35 | $0.32 |
| 44 | Temp PVT MK line 6 - paint (70300241) | LF | 250 | $0.60 | $0.50 | $0.55 |
| 45 | Temp PVT MK line 24 - paint (70300281) | LF | 150 | $1.95 | $2.05 | $1.75 |
| 46 | THPL PVT MK line 4 (78000200) | LF | 9,405 | $1.17 | $0.75 | $0.95 |
| 47 | THPL PVT MK line 6 (78000400) | LF | 110 | $1.65 | $1.15 | $6.00 |
| 48 | THPL PVT MK line 24 (78000650) | LF | 70 | $6.60 | $4.50 | $15.00 |
| 49 | Raised refl pavt MKR (78100100) | EACH | 175 | $72.00 | $55.50 | $54.00 |
| 50 | Raised ref PVT MK rem (78300200) | EACH | 175 | $15.00 | $10.00 | $13.00 |
| 51 | PVT MKG rem WTR blast (78300202) | SF | 3,395 | $1.55 | $1.40 | $1.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.