IDOT contract 66P83 bid tabulation
Section (108BR)BP. Let by Illinois DOT on March 7, 2025, Livingston, District 03. 4 bids received; low bid $143,680 by ERA-Valdivia Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 16
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | ERA-Valdivia Contractors, Inc. | $143,680 | Low |
| 2 | Three Star Painting, Inc. | $181,870 | +27% |
| 3 | Venus Painting Co. | $203,845 | +42% |
| 4 | Civil Coatings and Construction Inc. | $222,096 | +55% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. ERA-Valdivia Contractors, Inc. | 2. Three Star Painting, Inc. | 3. Venus Painting Co. | 4. Civil Coatings and Construction Inc. |
|---|---|---|---|---|---|---|---|
| 1 | C&D N-lead PT C RS N1 (X5060601) | LS | 1 | $42,156 | $5,000.00 | $6,000.00 | $500.00 |
| 2 | BR CLN & PT war #1 (X5067501) | LS | 1 | $1,500.00 | $750.00 | $1,000.00 | $50.00 |
| 3 | Temp rumble strips SP (X7010118) | EACH | 6 | $100.00 | $1,000.00 | $840.00 | $500.00 |
| 4 | Temp info signing (X7200061) | SF | 42 | $10.00 | $10.00 | $145.00 | $45.00 |
| 5 | Clean & PT STL BR N1 (Z0010501) | LS | 1 | $88,312 | $128,250 | $140,000 | $168,881 |
| 6 | Mobilization (67100100) | LS | 1 | $10,000 | $6,750.00 | $15,000 | $10,000 |
| 7 | Traf cont-prot 701321 (70100405) | EACH | 1 | $100.00 | $2,500.00 | $5,000.00 | $9,500.00 |
| 8 | Traf cont-prot 701201 (70100450) | LS | 1 | $100.00 | $100.00 | $3,000.00 | $1.00 |
| 9 | Temp BR traf signals (70106500) | EACH | 1 | $100.00 | $4,500.00 | $8,000.00 | $6,000.00 |
| 10 | Short term pavt mking (70300100) | LF | 60 | $0.10 | $20.00 | $15.00 | $10.00 |
| 11 | SHRT TRM pavt MK rem (70300150) | SF | 20 | $0.10 | $50.00 | $5.00 | $10.00 |
| 12 | Temp conc barrier (70400100) | LF | 225 | $1.00 | $44.44 | $45.00 | $35.00 |
| 13 | Imp attn temp NRN TL3 (70600251) | EACH | 1 | $100.00 | $1,500.00 | $3,000.00 | $1,250.00 |
| 14 | Mod ureth PM line 4 (78009004) | LF | 275 | $0.10 | $15.95 | $1.00 | $16.65 |
| 15 | Mod ureth PM line 6 (78009006) | LF | 150 | $0.10 | $23.92 | $1.00 | $22.65 |
| 16 | PVT MKG rem WTR blast (78300202) | SF | 165 | $0.10 | $35.92 | $1.00 | $26.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.