IDOT contract 68J42 bid tabulation
Section (6BR-1)BRR. Let by Illinois DOT on June 13, 2025, Tazewell, District 04. 3 bids received; low bid $547,991 by Stark Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 45
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Excavating, Inc. | $547,991 | Low |
| 2 | Otto Baum Company, Inc. | $636,400 | +16% |
| 3 | William Charles Construction Company, LLC | $739,000 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Excavating, Inc. | 2. Otto Baum Company, Inc. | 3. William Charles Construction Company, LLC |
|---|---|---|---|---|---|---|
| 1 | Pipe culvert rem SPL (X5015225) | LF | 24 | $132.00 | $208.24 | $125.00 |
| 2 | Struct steel repair (X5051206) | LB | 310 | $57.00 | $47.87 | $75.00 |
| 3 | Fill inlets SPL (X6050310) | EACH | 2 | $1,367.00 | $5,513.88 | $1,000.00 |
| 4 | GDRL agg eros cont (Z0001002) | TON | 210 | $91.00 | $85.95 | $100.00 |
| 5 | Jack & rem EX bearing (Z0001899) | EACH | 12 | $2,000.00 | $1,292.45 | $3,200.00 |
| 6 | STR rep con DP = < 5 (Z0012754) | SF | 91 | $275.00 | $581.17 | $200.00 |
| 7 | Temp shoring & crib (Z0073200) | EACH | 3 | $3,583.00 | $16,888 | $25,000 |
| 8 | Exc & GR EX shoulder (20200600) | UNIT | 10.60 | $1,711.00 | $1,555.98 | $800.00 |
| 9 | Perimeter eros bar (28000400) | LF | 127 | $12.40 | $6.92 | $8.00 |
| 10 | Stone riprap CL A4 (28100107) | SY | 23 | $182.00 | $201.54 | $175.00 |
| 11 | Filter fabric (28200200) | SY | 23 | $9.00 | $14.43 | $30.00 |
| 12 | Bit matls tack CT (40600290) | LB | 572 | $1.26 | $1.40 | $6.13 |
| 13 | HMA surf rem butt JT (40600982) | SY | 50 | $45.00 | $50.55 | $77.29 |
| 14 | HMA SC IL-9.5 D N50 (40604060) | TON | 4 | $890.00 | $999.73 | $2,140.68 |
| 15 | HMA surf rem 2 (44000157) | SY | 38 | $45.00 | $50.55 | $106.26 |
| 16 | HMA shoulders 8 (48203029) | SY | 354 | $105.00 | $117.95 | $153.62 |
| 17 | Conc rem (50102400) | CY | 11 | $5,200.00 | $3,155.31 | $8,000.00 |
| 18 | Conc sup-STR (50300255) | CY | 11 | $4,100.00 | $4,372.36 | $6,000.00 |
| 19 | Protective coat (50300300) | SY | 27 | $22.00 | $29.58 | $25.00 |
| 20 | F & E struct steel (50500405) | LB | 1,330 | $15.00 | $12.47 | $25.00 |
| 21 | Reinf bars, epoxy CTD (50800205) | LB | 1,500 | $4.57 | $4.71 | $7.00 |
| 22 | Bar splicers (50800515) | EACH | 24 | $63.00 | $49.17 | $200.00 |
| 23 | Pref JT strip seal (52000110) | LF | 72 | $273.00 | $392.96 | $250.00 |
| 24 | Elast bearing assy T1 (52100010) | EACH | 12 | $1,600.00 | $2,276.19 | $1,250.00 |
| 25 | Anchor bolts 1 (52100520) | EACH | 24 | $190.00 | $158.40 | $125.00 |
| 26 | Epoxy crack injection (59000200) | LF | 93 | $68.00 | $64.93 | $90.00 |
| 27 | SPBGR TY A 6FT posts (63000001) | LF | 638 | $36.50 | $41.00 | $36.65 |
| 28 | Traf bar term T6 (63100085) | EACH | 4 | $3,250.00 | $3,650.71 | $4,935.00 |
| 29 | TR bar TRM T1 SPL FLR (63100169) | EACH | 4 | $3,650.00 | $4,100.03 | $4,590.00 |
| 30 | Guardrail remov (63200310) | LF | 804 | $6.00 | $6.74 | $19.15 |
| 31 | Mobilization (67100100) | LS | 1 | $38,000 | $61,831 | $44,340 |
| 32 | Traf cont-prot 701321 (70100405) | EACH | 1 | $26,950 | $17,411 | $16,950 |
| 33 | Traf cont-prot 701326 (70100500) | LS | 1 | $1,550.00 | $1,741.11 | $1,200.00 |
| 34 | Temp BR traf signals (70106500) | EACH | 1 | $20,000 | $19,782 | $27,150 |
| 35 | Temp rumble strips (70106700) | EACH | 6 | $1,380.00 | $1,550.15 | $1,450.00 |
| 36 | Changeable message SN (70107025) | CAL DAY | 14 | $150.00 | $168.49 | $80.00 |
| 37 | Temp conc barrier (70400100) | LF | 313 | $55.00 | $55.63 | $75.00 |
| 38 | Rel temp conc barrier (70400200) | LF | 313 | $14.00 | $16.34 | $8.00 |
| 39 | Imp attn temp NRD TL3 (70600250) | EACH | 2 | $5,000.00 | $5,477.15 | $2,500.00 |
| 40 | Imp attn rel NRD TL3 (70600350) | EACH | 2 | $800.00 | $922.29 | $1,250.00 |
| 41 | Terminal marker - DA (72501000) | EACH | 4 | $50.00 | $56.17 | $50.00 |
| 42 | Paint PVT MK line 4 (78001110) | LF | 1,629 | $2.05 | $2.29 | $3.00 |
| 43 | Grdrail ref type B (78200006) | EACH | 18 | $45.00 | $50.55 | $15.00 |
| 44 | Barr wall ref type C (78200011) | EACH | 12 | $15.00 | $56.17 | $25.00 |
| 45 | PVT MKG rem WTR blast (78300202) | SF | 543 | $8.75 | $9.82 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.