IDOT contract 72255 bid tabulation
Section (B,150)RS-3. Let by Illinois DOT on March 7, 2025, Sangamon, District 06. 3 bids received; low bid $2,490,973 by P. H. Broughton & Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 63
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | P. H. Broughton & Sons, Inc. | $2,490,973 | Low |
| 2 | Truman L. Flatt & Sons Co., Inc. | $2,501,179 | 0.0% |
| 3 | Illinois Valley Paving, a div of UCM, Inc. | $2,789,146 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. P. H. Broughton & Sons, Inc. | 2. Truman L. Flatt & Sons Co., Inc. | 3. Illinois Valley Paving, a div of UCM, Inc. |
|---|---|---|---|---|---|---|
| 1 | Part dep rem T2 6 (X4406260) | SY | 29 | $83.03 | $52.70 | $66.95 |
| 2 | Part dep rem T3 6 (X4406460) | SY | 53 | $83.03 | $52.55 | $66.95 |
| 3 | Partial depth patch (X4421000) | TON | 28 | $319.04 | $241.20 | $415.42 |
| 4 | Rem conc end sec (X5010523) | EACH | 1 | $616.93 | $586.50 | $603.75 |
| 5 | Construction layout (Z0013798) | LS | 1 | $10,729 | $14,280 | $10,122 |
| 6 | Trainees (Z0076600) | HR | 2,000 | $0.80 | $0.80 | $0.80 |
| 7 | Trainees TPG (Z0076604) | HR | 2,000 | $15.00 | $15.00 | $15.00 |
| 8 | Tree remov 6-15 (20100110) | UNIT | 105 | $118.02 | $102.00 | $105.00 |
| 9 | Tree remov over 15 (20100210) | UNIT | 99 | $118.02 | $102.00 | $105.00 |
| 10 | Grading & shap ditch (21400100) | LF | 1,973 | $16.09 | $15.30 | $15.75 |
| 11 | Seeding CL 2 (25000200) | ACRE | 0.50 | $3,755.26 | $3,570.00 | $3,675.00 |
| 12 | Nitrogen fert nutr (25000400) | LB | 49 | $3.22 | $3.06 | $3.15 |
| 13 | Phosphorus fert nutr (25000500) | LB | 49 | $3.22 | $3.06 | $3.15 |
| 14 | Potassium fert nutr (25000600) | LB | 49 | $3.22 | $3.06 | $3.15 |
| 15 | Agr ground limestone (25000700) | TON | 1 | $214.59 | $204.00 | $210.00 |
| 16 | Mulch method 2 (25100115) | ACRE | 0.50 | $3,755.26 | $3,570.00 | $3,675.00 |
| 17 | Temp eros contr seed (28000250) | LB | 54 | $7.51 | $7.14 | $7.35 |
| 18 | Temp ditch checks (28000305) | LF | 176 | $13.95 | $27.03 | $27.83 |
| 19 | Inlet & pipe protect (28000500) | EACH | 8 | $209.22 | $367.20 | $378.00 |
| 20 | Stone riprap CL A4 (28100207) | TON | 388 | $386.25 | $188.70 | $194.25 |
| 21 | Filter fabric (28200200) | SY | 875 | $2.41 | $2.30 | $2.36 |
| 22 | Sub gran mat B (31101000) | TON | 17 | $53.65 | $56.92 | $87.01 |
| 23 | Agg surf course TY B (40200800) | TON | 10 | $53.65 | $51.00 | $52.50 |
| 24 | Bit matls tack CT (40600290) | LB | 61,244 | $0.56 | $0.68 | $1.12 |
| 25 | Long joint sealant (40600370) | LF | 33,704 | $2.74 | $2.51 | $2.56 |
| 26 | Matl transfer device (40600405) | TON | 8,129 | $3.49 | $3.25 | $3.76 |
| 27 | HMA surf rem butt JT (40600982) | SY | 1,083 | $22.42 | $22.96 | $24.28 |
| 28 | Temporary ramp (40600990) | SY | 254 | $10.30 | $16.58 | $7.34 |
| 29 | HMA BC IL-9.5FG N50 (40602965) | TON | 5,776 | $108.56 | $109.19 | $119.34 |
| 30 | HMA SC IL-9.5 C N50 (40604050) | TON | 7,014 | $103.55 | $107.06 | $119.11 |
| 31 | P HMA SC IL-9.5 D N90 (40604164) | TON | 1,115 | $140.57 | $148.22 | $162.89 |
| 32 | Bit matls tack CT (40800029) | LB | 480 | $1.00 | $0.69 | $0.85 |
| 33 | Incidental HMA surf (40800050) | TON | 127 | $277.89 | $325.56 | $342.77 |
| 34 | Welded wire reinf (42000060) | SY | 89 | $37.55 | $20.94 | $29.80 |
| 35 | HMA surf rem 1 (44000153) | SY | 37,255 | $1.45 | $1.79 | $2.20 |
| 36 | HMA surf rem 1 1/2 (44000155) | SY | 44,756 | $1.45 | $2.12 | $2.20 |
| 37 | HMA surf rem 2 (44000157) | SY | 11,351 | $1.45 | $4.51 | $4.85 |
| 38 | HMA surf rem 2 3/4 (44000160) | SY | 1,421 | $1.45 | $5.69 | $6.61 |
| 39 | CL B patch T4 14 (44201025) | SY | 89 | $348.70 | $254.34 | $479.70 |
| 40 | Dowel bars 1 1/2 (44201299) | EACH | 60 | $32.19 | $53.16 | $36.60 |
| 41 | Saw cuts (44213200) | LF | 82 | $10.73 | $10.29 | $42.25 |
| 42 | Agg wedge SHLD type B (48102100) | TON | 1,060 | $47.21 | $44.88 | $44.07 |
| 43 | HMA shoulders (48203100) | TON | 163 | $103.55 | $163.71 | $176.63 |
| 44 | PRC flar end sec 24 (54213669) | EACH | 1 | $2,682.32 | $2,550.00 | $2,625.00 |
| 45 | Box cul to BE cleaned (60905305) | LF | 46 | $134.12 | $127.50 | $131.25 |
| 46 | Engr field office A (67000400) | CAL MO | 12 | $3,081.76 | $2,456.72 | $3,495.03 |
| 47 | Mobilization (67100100) | LS | 1 | $47,328 | $38,832 | $60,595 |
| 48 | Traf cont-prot 701201 (70100450) | LS | 1 | $5,471.94 | $909.02 | $0.01 |
| 49 | Traf cont-prot 701306 (70100460) | LS | 1 | $13,948 | $13,828 | $24,232 |
| 50 | Traf cont-prot 701336 (70100600) | LS | 1 | $107.29 | $1,513.13 | $0.01 |
| 51 | TR cont & prot 701701 (70102635) | LS | 1 | $107.29 | $6,010.90 | $2,191.83 |
| 52 | Changeable message SN (70107025) | CAL DAY | 21 | $128.75 | $85.49 | $225.23 |
| 53 | Short term pavt mking (70300100) | LF | 9,887 | $1.61 | $0.42 | $1.22 |
| 54 | SHRT TRM pavt MK rem (70300150) | SF | 3,296 | $1.76 | $2.80 | $0.01 |
| 55 | Mod ureth PM LTR-sym (78009000) | SF | 255 | $5.36 | $12.24 | $12.60 |
| 56 | Mod ureth PM line 5 (78009005) | LF | 83,202 | $0.86 | $0.55 | $0.57 |
| 57 | Mod ureth PM line 6 (78009006) | LF | 1,075 | $1.07 | $0.60 | $0.62 |
| 58 | Mod ureth PM line 8 (78009008) | LF | 548 | $3.22 | $4.08 | $4.20 |
| 59 | Mod ureth PM line 12 (78009012) | LF | 1,320 | $2.15 | $8.16 | $8.40 |
| 60 | Mod ureth PM line 24 (78009024) | LF | 190 | $5.36 | $12.24 | $12.60 |
| 61 | Raised refl pavt MKR (78100100) | EACH | 500 | $45.40 | $43.16 | $44.43 |
| 62 | Curb reflectors (78200020) | EACH | 47 | $5.36 | $5.10 | $5.25 |
| 63 | Raised ref PVT MK rem (78300200) | EACH | 500 | $9.79 | $17.75 | $11.63 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.