IDOT contract 72307 bid tabulation
Section 34RS-5. Let by Illinois DOT on January 16, 2026, Pike, District 06. 2 bids received; low bid $7,106,857 by Illinois Valley Paving, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 58
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Illinois Valley Paving, a div of UCM, Inc. | $7,106,857 | Low |
| 2 | Diamond Construction Company | $7,699,901 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Illinois Valley Paving, a div of UCM, Inc. | 2. Diamond Construction Company |
|---|---|---|---|---|---|
| 1 | Clearing & grubbing (X2010512) | SY | 234 | $9.76 | $47.00 |
| 2 | Exc & GR EX SHLD SPL (X2020060) | UNIT | 7 | $4,924.60 | $5,000.00 |
| 3 | Partial depth patch (X4421000) | TON | 112 | $605.71 | $250.00 |
| 4 | Part depth patch SPL (X4421002) | SY | 667 | $88.66 | $45.00 |
| 5 | Construction layout (Z0013798) | LS | 1 | $35,883 | $75,000 |
| 6 | Rumble strip (Z0055300) | EACH | 6 | $1,234.13 | $4,000.00 |
| 7 | Trainees (Z0076600) | HR | 3,000 | $0.80 | $0.80 |
| 8 | Trainees TPG (Z0076604) | HR | 3,000 | $15.00 | $15.00 |
| 9 | Furnished excavation (20400800) | CY | 171 | $215.45 | $120.00 |
| 10 | Seeding CL 2 (25000200) | ACRE | 0.75 | $7,562.51 | $7,650.00 |
| 11 | Nitrogen fert nutr (25000400) | LB | 62 | $11.00 | $11.00 |
| 12 | Phosphorus fert nutr (25000500) | LB | 62 | $11.00 | $11.00 |
| 13 | Potassium fert nutr (25000600) | LB | 62 | $11.00 | $11.00 |
| 14 | Agr ground limestone (25000700) | TON | 1.40 | $110.00 | $105.00 |
| 15 | Mulch method 2 (25100115) | ACRE | 0.75 | $7,562.51 | $7,650.00 |
| 16 | Temp eros contr seed (28000250) | LB | 75 | $15.99 | $15.00 |
| 17 | Stone riprap CL A4 (28100207) | TON | 355 | $397.99 | $145.00 |
| 18 | Filter fabric (28200200) | SY | 474 | $25.80 | $4.50 |
| 19 | Sub gran mat B (31101000) | TON | 1,644 | $78.60 | $42.00 |
| 20 | Preparation of base (35800100) | SY | 350 | $23.09 | $50.00 |
| 21 | Agg surf course TY B (40200800) | TON | 22 | $448.61 | $500.00 |
| 22 | Bit matls tack CT (40600290) | LB | 84,466 | $1.54 | $4.00 |
| 23 | Long joint sealant (40600370) | LF | 48,416 | $2.88 | $5.00 |
| 24 | Matl transfer device (40600405) | TON | 10,891 | $4.58 | $8.00 |
| 25 | HMA surf rem butt JT (40600982) | SY | 2,649 | $18.77 | $50.00 |
| 26 | Temporary ramp (40600990) | SY | 105 | $21.76 | $25.00 |
| 27 | HMA BC IL-9.5FG N50 (40602965) | TON | 8,363 | $166.61 | $192.00 |
| 28 | P HMA SC IL-9.5 C N50 (40604150) | TON | 10,891 | $168.17 | $190.00 |
| 29 | Bit matls tack CT (40800029) | LB | 1,192 | $4.91 | $4.00 |
| 30 | Incidental HMA surf (40800050) | TON | 331 | $433.82 | $400.00 |
| 31 | HMA surf rem 1 1/2 (44000155) | SY | 131,395 | $3.51 | $5.00 |
| 32 | Gutter rem (44000400) | LF | 7,522 | $43.11 | $19.00 |
| 33 | Agg wedge SHLD type B (48102100) | TON | 2,528 | $54.82 | $65.00 |
| 34 | HMA shoulders 6 1/2 (48203023) | SY | 273 | $168.07 | $161.00 |
| 35 | HMA shoulders (48203100) | TON | 286 | $188.90 | $275.00 |
| 36 | Class SI conc outlet (60600095) | CY | 78 | $1,776.39 | $1,555.00 |
| 37 | Concrete gutter TY A (60602500) | LF | 6,748 | $72.70 | $51.00 |
| 38 | SPBGR TY B 6FT posts (63000007) | LF | 50 | $50.71 | $51.00 |
| 39 | SPBGR TY B 9FT posts (63000009) | LF | 350 | $69.30 | $70.00 |
| 40 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $4,004.00 | $4,005.00 |
| 41 | Guardrail remov (63200310) | LF | 602 | $10.40 | $10.50 |
| 42 | Engr field office A (67000400) | CAL MO | 12 | $4,128.72 | $5,550.00 |
| 43 | Mobilization (67100100) | LS | 1 | $422,765 | $385,000 |
| 44 | Traf cont-prot 701316 (70100100) | EACH | 5 | $31,574 | $25,000 |
| 45 | Traf cont-prot 701201 (70100450) | LS | 1 | $110.00 | $20,000 |
| 46 | Traf cont-prot 701306 (70100460) | LS | 1 | $34,121 | $97,500 |
| 47 | Traf cont-prot 701326 (70100500) | LS | 1 | $22,990 | $42,500 |
| 48 | Temp BR traf signals (70106500) | EACH | 5 | $23,625 | $10,000 |
| 49 | Changeable message SN (70107025) | CAL DAY | 480 | $159.57 | $75.00 |
| 50 | Short term pavt mking (70300100) | LF | 14,469 | $1.53 | $3.00 |
| 51 | SHRT TRM pavt MK rem (70300150) | SF | 1,608 | $6.89 | $5.00 |
| 52 | Terminal marker - DA (72501000) | EACH | 4 | $55.00 | $55.00 |
| 53 | Pref PL PM TD STD L24 (78004720) | LF | 79 | $30.80 | $42.00 |
| 54 | Mod ureth PM line 5 (78009005) | LF | 144,515 | $0.62 | $0.85 |
| 55 | GRV RCSD PVT MRKG 25 (78011125) | LF | 79 | $13.20 | $18.00 |
| 56 | Raised refl pavt MKR (78100100) | EACH | 610 | $45.24 | $49.00 |
| 57 | Grdrail ref type A (78200005) | EACH | 8 | $11.00 | $11.00 |
| 58 | Raised ref PVT MK rem (78300200) | EACH | 610 | $26.12 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.