Section 101RS-7,. Let by Illinois DOT on June 12, 2026, Sangamon, District 06. 3 bids received; low bid $2,868,316 by P. H. Broughton & Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 48
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | P. H. Broughton & Sons, Inc. | $2,868,316 | Low |
| 2 | Illinois Valley Paving, a div of UCM, Inc. | $2,879,688 | 0.0% |
| 3 | Truman L. Flatt & Sons Co., Inc. | $2,937,001 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. P. H. Broughton & Sons, Inc. | 2. Illinois Valley Paving, a div of UCM, Inc. | 3. Truman L. Flatt & Sons Co., Inc. |
|---|---|---|---|---|---|---|
| 1 | Traffic counter- tirtl system (X0320089) | EACH | 1 | $45,669 | $42,550 | $43,401 |
| 2 | Construction layout (Z0013798) | LS | 1 | $8,049.69 | $6,184.55 | $7,650.00 |
| 3 | RR prot liability ins (Z0048665) | LS | 1 | $17,449 | $12,359 | $6,725.00 |
| 4 | Trainees (Z0076600) | HR | 2,500 | $0.80 | $0.80 | $0.80 |
| 5 | Trainees TPG (Z0076604) | HR | 2,500 | $15.00 | $15.00 | $15.00 |
| 6 | Earth excavation (20200100) | CY | 48 | $69.76 | $107.08 | $72.06 |
| 7 | Agg surf course TY B (40200800) | TON | 38 | $32.18 | $66.23 | $97.08 |
| 8 | Bit matls tack CT (40600290) | LB | 65,715 | $0.61 | $0.96 | $0.68 |
| 9 | Long joint sealant (40600370) | LF | 29,891 | $2.75 | $2.45 | $2.62 |
| 10 | Matl transfer device (40600405) | TON | 7,858 | $3.63 | $2.56 | $3.08 |
| 11 | HMA surf rem butt JT (40600982) | SY | 2,609 | $23.35 | $9.65 | $18.69 |
| 12 | PCC surf rem butt JT (40600985) | SY | 218 | $23.09 | $10.19 | $21.30 |
| 13 | Temporary ramp (40600990) | SY | 340 | $10.30 | $8.44 | $11.41 |
| 14 | HMA BC IL-9.5FG N50 (40602965) | TON | 6,537 | $118.02 | $116.28 | $116.35 |
| 15 | P HMA SC IL-9.5 D N50 (40604160) | TON | 7,858 | $130.39 | $130.97 | $132.51 |
| 16 | Incidental HMA surf (40800050) | TON | 549 | $221.42 | $223.82 | $247.68 |
| 17 | HMA surf rem 1 1/2 (44000155) | SY | 68,197 | $1.50 | $1.91 | $2.15 |
| 18 | HMA surf rem 2 3/4 (44000160) | SY | 28,448 | $1.65 | $3.29 | $3.06 |
| 19 | Drive pavement rem (44000200) | SY | 207 | $19.25 | $54.87 | $16.56 |
| 20 | Agg wedge SHLD type B (48102100) | TON | 1,317 | $32.18 | $38.25 | $40.75 |
| 21 | HMA shoulders (48203100) | TON | 606 | $138.80 | $109.02 | $133.44 |
| 22 | Misc concrete (61100605) | CY | 8.60 | $536.65 | $700.35 | $0.01 |
| 23 | Sinusoidal rum STP 14 (64200214) | LF | 21,676 | $0.54 | $0.54 | $0.40 |
| 24 | Engr field office A (67000400) | CAL MO | 12 | $3,722.53 | $3,223.62 | $3,076.51 |
| 25 | Mobilization (67100100) | LS | 1 | $41,158 | $46,200 | $32,713 |
| 26 | Traf cont-prot 701201 (70100450) | LS | 1 | $80.50 | $0.01 | $0.01 |
| 27 | Traf cont-prot 701306 (70100460) | LS | 1 | $10,465 | $19,750 | $29,616 |
| 28 | TR cont & prot 701701 (70102635) | LS | 1 | $1,663.60 | $500.00 | $3,601.82 |
| 29 | Changeable message SN (70107025) | CAL DAY | 450 | $69.76 | $50.25 | $69.47 |
| 30 | Short term pavt mking (70300100) | LF | 8,125 | $1.61 | $0.81 | $1.22 |
| 31 | SHRT TRM pavt MK rem (70300150) | SF | 2,708 | $1.14 | $2.02 | $3.26 |
| 32 | Pref PL PM TD STD LTR/sym (78004600) | SF | 296 | $52.38 | $48.80 | $49.78 |
| 33 | Pref PL PM TD STD L24 (78004720) | LF | 299 | $21.47 | $20.00 | $20.40 |
| 34 | Mod ureth PM line 5 (78009005) | LF | 101,907 | $0.73 | $0.68 | $0.69 |
| 35 | Mod ureth PM line 6 (78009006) | LF | 576 | $3.22 | $3.00 | $3.06 |
| 36 | Mod ureth PM line 8 (78009008) | LF | 128 | $5.37 | $5.00 | $5.10 |
| 37 | Mod ureth PM line 12 (78009012) | LF | 287 | $10.73 | $10.00 | $10.20 |
| 38 | GRV RCSD PM LTR & sym (78011000) | SF | 296 | $5.37 | $5.00 | $5.10 |
| 39 | GRV RCSD PVT MRKG 6 (78011030) | LF | 101,907 | $0.17 | $0.16 | $0.16 |
| 40 | GRV RCSD PVT MRKG 7 (78011035) | LF | 576 | $1.07 | $1.00 | $1.02 |
| 41 | GRV RCSD PVT MRKG 9 (78011045) | LF | 128 | $3.22 | $3.00 | $3.06 |
| 42 | GRV RCSD PVT MRKG 13 (78011065) | LF | 287 | $4.29 | $4.00 | $4.08 |
| 43 | GRV RCSD PVT MRKG 25 (78011125) | LF | 299 | $5.37 | $5.00 | $5.10 |
| 44 | Raised refl pavt MKR (78100100) | EACH | 560 | $46.30 | $43.14 | $38.03 |
| 45 | Curb reflectors (78200020) | EACH | 121 | $3.76 | $3.50 | $18.36 |
| 46 | Raised ref PVT MK rem (78300200) | EACH | 560 | $10.71 | $12.80 | $0.01 |
| 47 | LP F M 15BC 8 5/8X6 (83600356) | EACH | 2 | $3,085.72 | $2,875.00 | $2,932.50 |
| 48 | TS post galvs 12 (87502460) | EACH | 2 | $5,124.97 | $4,775.00 | $4,870.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.