IDOT contract 72762 bid tabulation
Section 119RS-4,120RS-5,CLV. Let by Illinois DOT on February 27, 2026, Schuyler, District 06. 2 bids received; low bid $5,590,001 by Illinois Valley Paving, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 77
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Illinois Valley Paving, a div of UCM, Inc. | $5,590,001 | Low |
| 2 | W. L. Miller Company | $5,858,113 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Illinois Valley Paving, a div of UCM, Inc. | 2. W. L. Miller Company |
|---|---|---|---|---|---|
| 1 | Helical ground anchor (X0323992) | EACH | 2 | $20,481 | $18,700 |
| 2 | PCC surf rem var DP (X4400100) | SY | 397 | $42.69 | $30.00 |
| 3 | Aggregate SHLDS SPL (X4811900) | TON | 33 | $274.32 | $100.00 |
| 4 | Struct steel repair (X5051206) | LB | 220 | $42.45 | $65.00 |
| 5 | Width restrict sign (X7200201) | LS | 1 | $7,290.00 | $2,145.00 |
| 6 | Approach slab rem (Z0004552) | SY | 139 | $194.85 | $80.00 |
| 7 | Construction layout (Z0013798) | LS | 1 | $61,010 | $35,000 |
| 8 | JT sealing (patches) (Z0032500) | LF | 166 | $17.49 | $12.50 |
| 9 | Temp wall bracing sys (Z0073700) | LS | 1 | $17,893 | $59,400 |
| 10 | Trainees (Z0076600) | HR | 4,000 | $0.80 | $0.80 |
| 11 | Trainees TPG (Z0076604) | HR | 4,000 | $15.00 | $15.00 |
| 12 | Earth excavation (20200100) | CY | 203 | $57.24 | $58.00 |
| 13 | Earth exc wid (20200500) | CY | 101 | $187.45 | $95.00 |
| 14 | Stone riprap CL A4 (28100107) | SY | 249 | $144.43 | $92.40 |
| 15 | Stone riprap CL A5 (28100109) | SY | 212 | $172.33 | $122.00 |
| 16 | Stone riprap CL A3 (28100205) | TON | 239 | $129.60 | $132.00 |
| 17 | Stone riprap CL A4 (28100207) | TON | 23 | $243.00 | $247.00 |
| 18 | Filter fabric (28200200) | SY | 530 | $3.24 | $4.00 |
| 19 | Sub gran mat B (31101000) | TON | 250 | $69.12 | $75.00 |
| 20 | Base cse widening 8 (35650300) | SY | 555 | $83.26 | $195.50 |
| 21 | Bit matls tack CT (40600290) | LB | 66,688 | $1.49 | $1.25 |
| 22 | Long joint sealant (40600370) | LF | 60,625 | $3.37 | $3.20 |
| 23 | Matl transfer device (40600405) | TON | 16,598 | $4.41 | $4.50 |
| 24 | HMA surf rem butt JT (40600982) | SY | 147 | $19.79 | $65.00 |
| 25 | Temporary ramp (40600990) | SY | 49 | $28.33 | $50.00 |
| 26 | HMA SC IL-9.5 C N50 (40604050) | TON | 16,598 | $148.62 | $160.00 |
| 27 | Bit matls tack CT (40800029) | LB | 1,423 | $1.81 | $4.00 |
| 28 | Incidental HMA surf (40800050) | TON | 310 | $335.44 | $375.00 |
| 29 | PVT con HMA BR app SL (42000070) | SY | 53.30 | $470.78 | $350.00 |
| 30 | Pavement rem (44000100) | SY | 107 | $63.51 | $56.00 |
| 31 | HMA surf rem 1 1/2 (44000155) | SY | 163,295 | $3.42 | $3.00 |
| 32 | Gutter rem (44000400) | LF | 1,941 | $15.12 | $15.50 |
| 33 | Paved SHLD removal (44004250) | SY | 126 | $78.93 | $70.00 |
| 34 | Agg wedge SHLD type B (48102100) | TON | 851 | $48.51 | $45.00 |
| 35 | HMA shoulders (48203100) | TON | 182 | $207.05 | $250.00 |
| 36 | Conc rem (50102400) | CY | 39.80 | $2,053.00 | $1,550.00 |
| 37 | Bridge rail removal (50104000) | LF | 67 | $99.17 | $30.00 |
| 38 | Conc struct (50300225) | CY | 23.50 | $951.75 | $1,205.00 |
| 39 | Conc sup-STR (50300255) | CY | 40.10 | $3,530.85 | $2,420.00 |
| 40 | Protective coat (50300300) | SY | 523 | $5.84 | $5.00 |
| 41 | Conc supstr app slab (50301350) | CY | 108.30 | $1,009.88 | $730.00 |
| 42 | Reinf bars, epoxy CTD (50800205) | LB | 53,910 | $1.77 | $1.90 |
| 43 | Bar splicers (50800515) | EACH | 380 | $47.69 | $85.00 |
| 44 | Steel railing TY SM (50901050) | LF | 127 | $308.29 | $870.00 |
| 45 | Name plates (51500100) | EACH | 1 | $1,804.25 | $1,500.00 |
| 46 | STR rep con DP = < 5 (53212754) | SF | 40 | $431.48 | $285.00 |
| 47 | Conc HDWL for P drain (60100060) | EACH | 2 | $677.16 | $690.00 |
| 48 | Inlets adj new T3F&G (60260500) | EACH | 8 | $1,215.00 | $1,250.00 |
| 49 | Class SI conc outlet (60600095) | CY | 28 | $1,807.19 | $1,840.00 |
| 50 | Concrete gutter TY A (60602500) | LF | 1,653 | $82.44 | $83.60 |
| 51 | SPBGR TY A 6FT posts (63000001) | LF | 200 | $31.70 | $45.10 |
| 52 | Traf bar term T6A (63100087) | EACH | 4 | $4,525.20 | $6,725.00 |
| 53 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $3,796.20 | $5,775.00 |
| 54 | Guardrail remov (63200310) | LF | 586 | $15.66 | $18.00 |
| 55 | Engr field office A (67000400) | CAL MO | 12 | $3,892.04 | $4,500.00 |
| 56 | Mobilization (67100100) | LS | 1 | $114,699 | $250,000 |
| 57 | Traf cont-prot 701316 (70100100) | EACH | 4 | $12,919 | $5,445.00 |
| 58 | Traf cont-prot 701321 (70100405) | EACH | 1 | $22,579 | $6,325.00 |
| 59 | Traf cont-prot 701201 (70100450) | LS | 1 | $108.00 | $14,000 |
| 60 | Traf cont-prot 701306 (70100460) | LS | 1 | $18,630 | $20,350 |
| 61 | Traf cont-prot 701326 (70100500) | LS | 1 | $22,572 | $31,900 |
| 62 | Temp BR traf signals (70106500) | EACH | 5 | $20,790 | $25,000 |
| 63 | Temp rumble strips (70106700) | EACH | 30 | $810.00 | $1,100.00 |
| 64 | Changeable message SN (70107025) | CAL DAY | 200 | $95.04 | $100.00 |
| 65 | Short term pavt mking (70300100) | LF | 12,132 | $2.14 | $1.00 |
| 66 | SHRT TRM pavt MK rem (70300150) | SF | 2,022 | $6.88 | $3.00 |
| 67 | Temp conc barrier (70400100) | LF | 450 | $49.35 | $55.00 |
| 68 | Rel temp conc barrier (70400200) | LF | 450 | $4.69 | $15.00 |
| 69 | Imp attn temp FRN TL3 (70600260) | EACH | 2 | $14,056 | $8,525.00 |
| 70 | Imp attn rel FRN TL3 (70600332) | EACH | 2 | $5,398.32 | $1,595.00 |
| 71 | Terminal marker - DA (72501000) | EACH | 4 | $54.00 | $49.50 |
| 72 | Mod ureth PM line 5 (78009005) | LF | 192,605 | $0.55 | $0.57 |
| 73 | Mod ureth PM line 24 (78009024) | LF | 15 | $27.00 | $27.50 |
| 74 | Raised refl pavt MKR (78100100) | EACH | 762 | $42.38 | $45.00 |
| 75 | Grdrail ref type A (78200005) | EACH | 14 | $10.80 | $12.65 |
| 76 | Raised ref PVT MK rem (78300200) | EACH | 762 | $20.01 | $12.00 |
| 77 | PVT MKG rem grinding (78300201) | SF | 450 | $3.44 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.