IDOT contract 74608 bid tabulation
Section (105)RS-3. Let by Illinois DOT on September 19, 2025, Effingham, District 07. 1 bid received; low bid $947,329 by Howell Paving, Inc..
- Owner
- Illinois DOT
- Letting
- 19 SEP 2025
- Pay items
- 66
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Howell Paving, Inc. | $947,329 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Howell Paving, Inc. |
|---|---|---|---|---|
| 1 | Relocate EX mailbox (X0327301) | EACH | 8 | $489.02 |
| 2 | Temporary ramp SPL (X4060995) | SY | 224 | $65.57 |
| 3 | PCC PVT 8 SPL (X4200408) | SY | 69 | $204.25 |
| 4 | Class SI conc out SPL (X6060097) | CY | 0.50 | $5,245.72 |
| 5 | Reloc sign panel&post (X7240505) | EACH | 4 | $150.00 |
| 6 | RR prot liability ins (Z0048665) | LS | 1 | $8,180.63 |
| 7 | Prot reset survey MRK (Z0049799) | EACH | 3 | $2,404.56 |
| 8 | SS 1 wat MN 15 (Z0056650) | LF | 29 | $231.10 |
| 9 | Earth excavation (20200100) | CY | 195 | $235.57 |
| 10 | Trench backfill (20800150) | CY | 1 | $397.18 |
| 11 | Topsoil F & P 4 (21101615) | SY | 316 | $21.67 |
| 12 | Sodding (25200100) | SY | 790 | $49.50 |
| 13 | Supple watering (25200200) | UNIT | 23.70 | $450.00 |
| 14 | PCC bse cse 10 (35300500) | SY | 208 | $121.97 |
| 15 | Agg surf course TY B (40200800) | TON | 13 | $145.50 |
| 16 | Bit matls tack CT (40600290) | LB | 3,261 | $3.06 |
| 17 | Long joint sealant (40600370) | LF | 1,491 | $14.49 |
| 18 | Temporary ramp (40600990) | SY | 217 | $26.06 |
| 19 | P HMA BC IL-9.5FG N90 (40603219) | TON | 377 | $178.17 |
| 20 | HMA SC IL-9.5 C N70 (40604052) | TON | 130 | $193.87 |
| 21 | P HMA SC IL-9.5 D N90 (40604164) | TON | 431 | $251.36 |
| 22 | PCC PVT 8 (42000300) | SY | 65 | $196.68 |
| 23 | PCC driveway pavt 8 (42300400) | SY | 6 | $387.49 |
| 24 | PC conc sidewalk 6 (42400300) | SF | 1,015 | $48.27 |
| 25 | Detectable warnings (42400800) | SF | 92 | $44.04 |
| 26 | Pavement rem (44000100) | SY | 435 | $55.31 |
| 27 | HMA surf rem 1 1/2 (44000155) | SY | 1,265 | $11.90 |
| 28 | HMA surf rem 3 3/4 (44000164) | SY | 3,849 | $10.19 |
| 29 | Drive pavement rem (44000200) | SY | 6 | $284.21 |
| 30 | Comb curb gutter rem (44000500) | LF | 44 | $143.86 |
| 31 | Sidewalk rem (44000600) | SF | 970 | $13.03 |
| 32 | CL C patch T1 12 (44201373) | SY | 30 | $541.15 |
| 33 | CL C patch T2 12 (44201377) | SY | 41 | $431.35 |
| 34 | CL C patch T3 12 (44201381) | SY | 19 | $449.07 |
| 35 | CL C patch T4 12 (44201383) | SY | 47 | $393.63 |
| 36 | Aggregate SHLDS B 8 (48101600) | SY | 170 | $86.54 |
| 37 | HMA shoulders 8 (48203029) | SY | 429 | $163.38 |
| 38 | Water valves adjust (56109210) | EACH | 2 | $333.50 |
| 39 | Inlets TA T3F&G (60235700) | EACH | 1 | $3,888.40 |
| 40 | Man adjust (60255500) | EACH | 2 | $1,112.02 |
| 41 | Comb CC&G TB6.18 (60604400) | LF | 127 | $135.14 |
| 42 | Non SPL waste disposl (66900200) | CY | 75 | $265.71 |
| 43 | Soil disposal analy (66900530) | EACH | 1 | $1,450.00 |
| 44 | Reg sub P-const plan (66901001) | LS | 1 | $2,200.00 |
| 45 | Reg sub F con report (66901003) | LS | 1 | $2,200.00 |
| 46 | Reg sub mon (66901006) | CAL DAY | 2 | $1,225.00 |
| 47 | Engr field office A (67000400) | CAL MO | 6 | $3,288.53 |
| 48 | Engr field lab (67000600) | CAL MO | 4 | $4,191.80 |
| 49 | Mobilization (67100100) | LS | 1 | $25,548 |
| 50 | Traf cont-prot 701306 (70100460) | LS | 1 | $1,224.42 |
| 51 | TR cont & prot 701501 (70102620) | LS | 1 | $58,309 |
| 52 | TR cont & prot 701801 (70102640) | LS | 1 | $1,474.42 |
| 53 | TR cont surveillance (70103815) | CAL DAY | 10 | $0.01 |
| 54 | Changeable message SN (70107025) | CAL DAY | 28 | $150.00 |
| 55 | Short term pavt mking (70300100) | LF | 717 | $4.36 |
| 56 | SHRT TRM pavt MK rem (70300150) | SF | 159 | $19.46 |
| 57 | Sign panel T1 (72000100) | SF | 3 | $32.00 |
| 58 | Teles STL sin support (72800100) | LF | 33 | $29.00 |
| 59 | THPL PVT MK LTR & sym (78000100) | SF | 126 | $14.00 |
| 60 | THPL PVT MK line 4 (78000200) | LF | 3,516 | $2.36 |
| 61 | THPL PVT MK line 6 (78000400) | LF | 262 | $3.54 |
| 62 | THPL PVT MK line 24 (78000650) | LF | 84 | $14.50 |
| 63 | GRV RCSD PM LTR & sym (78011000) | SF | 122 | $14.50 |
| 64 | GRV RCSD PVT MRKG 5 (78011025) | LF | 3,265 | $1.61 |
| 65 | GRV RCSD PVT MRKG 7 (78011035) | LF | 262 | $4.00 |
| 66 | GRV RCSD PVT MRKG 25 (78011125) | LF | 84 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.