Section 1W-1. Let by Illinois DOT on January 17, 2025, Jersey, District 08. 2 bids received; low bid $1,403,493 by Stutz Excavating, Inc..

Owner
Illinois DOT
Letting
17 JAN 2025
Pay items
64
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Stutz Excavating, Inc.$1,403,493Low
2Charles E. Mahoney Co.$1,649,260+18%
IDOT contract 76P16: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Stutz Excavating, Inc.2. Charles E. Mahoney Co.
1Centerln rum strip 8 (X0326697)LF106$44.10$52.85
2Box culvert removal (X1200050)LF54$160.00$99.00
3Traf cont-prot BLR 21 (X7011800)LS1$4,000.00$4,402.42
4Construction layout (Z0013798)LS1$18,700$11,500
5Section corner MKRS (Z0064505)EACH1$1,665.00$400.00
6Trainees (Z0076600)HR500$0.80$0.80
7Trainees TPG (Z0076604)HR500$15.00$15.00
8Earth excavation (20200100)CY3,550$42.35$74.00
9Trench backfill (20800150)CY168.90$74.00$63.00
10Seeding CL 2A (25000210)ACRE1.25$5,670.00$2,400.00
11Nitrogen fert nutr (25000400)LB113$8.40$4.00
12Phosphorus fert nutr (25000500)LB113$8.40$4.00
13Potassium fert nutr (25000600)LB113$8.40$4.00
14Mulch method 2 (25100115)ACRE1.25$7,770.00$4,100.00
15Temp eros contr seed (28000250)LB250$10.50$7.25
16Temp ditch checks (28000305)LF324$26.25$18.00
17Inlet & pipe protect (28000500)EACH9$525.00$408.00
18Sub gran mat A 4 (31100300)SY1,592$11.35$18.59
19Agg base cse A 12 (35101100)SY3,418$27.50$55.47
20HMA BC wid 8 (35600708)SY3,499$72.80$87.41
21Agg surf course TY B (40200800)TON117.30$68.50$87.76
22Bit matls PR CT (40600275)LB7,874$2.80$1.28
23Bit matls tack CT (40600290)LB3,646$2.65$2.19
24Long joint sealant (40600370)LF3,658$3.50$3.99
25Temporary ramp (40600990)SY147$35.00$9.13
26HMA BC IL-9.5FG N70 (40602970)TON880.40$153.25$133.44
27HMA SC IL-9.5 C N70 (40604052)TON581.80$168.25$149.81
28Pavement rem (44000100)SY765$24.00$65.00
29HMA surf rem 3 3/4 (44000164)SY3,594$7.40$9.41
30Paved SHLD removal (44004250)SY519$24.00$55.95
31CL D patch T2 8 (44201741)SY20$310.00$361.46
32CL D patch T3 8 (44201745)SY44$310.00$336.50
33Aggregate SHLDS B 6 (48101500)SY683$30.35$23.24
34HMA shoulders 8 (48203029)SY1,410$82.50$73.37
35Conc headwall removal (50104400)EACH2$850.00$2,400.00
36Pipe culvert remov (50105220)LF185$19.50$14.00
37P cul CL A 1 15 (542A0220)LF47$119.50$113.00
38P cul CL A 1 24 (542A0229)LF186$121.00$199.00
39P cul CL D 1 15 (542D0220)LF255$99.00$104.00
40PRC flar end sec 15 (54213660)EACH2$1,280.00$2,375.00
41PRC flar end sec 24 (54213669)EACH6$2,333.00$3,100.00
42Metal FL end sec 15" (54262715)EACH10$490.00$1,400.00
43Shoulder rum strip 8 (64200108)LF2,429$6.60$2.93
44Fur erect row markers (66600105)EACH24$280.00$498.86
45Mobilization (67100100)LS1$52,700$77,084
46Traf cont-prot 701201 (70100450)LS1$300.00$2,374.04
47Traf cont-prot 701306 (70100460)LS1$16,890$9,580.56
48Traf cont-prot 701326 (70100500)LS1$600.00$14,028
49TR cont surveillance (70103815)CAL DAY70$704.00$0.01
50Changeable message SN (70107025)CAL DAY42$111.65$101.50
51Short term pavt mking (70300100)LF936$2.85$2.29
52SHRT TRM pavt MK rem (70300150)SF2,246$3.30$0.01
53Temp PVT MK L4 T4 tape (70307120)LF5,871$2.00$3.39
54Reloc sin pan assy TB (72400600)EACH7$430.00$398.00
55Reloc sign panel T1 (72400710)SF8$46.00$87.00
56Reloc sign panel T2 (72400720)SF20$10.00$70.00
57Wood sin support (73000100)LF72.50$29.00$48.00
58THPL PVT MK LTR & sym (78000100)SF78$16.00$5.50
59THPL PVT MK line 6 (78000400)LF9,168$2.45$1.32
60THPL PVT MK line 12 (78000600)LF241$7.25$2.64
61THPL PVT MK line 24 (78000650)LF45$18.10$5.28
62Raised refl pavt MKR (78100100)EACH92$55.00$62.20
63Raised ref PVT MK rem (78300200)EACH19$61.00$12.73
64Reloc EX FL beacon (89501510)EACH1$635.00$2,250.00
IDOT contract 76P16: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy