IDOT contract 78A68 bid tabulation

Section 102RS-5. Let by Illinois DOT on January 17, 2025, Perry, District 09. 2 bids received; low bid $726,553 by E. T. Simonds Construction Company.

Owner
Illinois DOT
Letting
17 JAN 2025
Pay items
23
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1E. T. Simonds Construction Company$726,553Low
2Samron Midwest Contracting, Inc.$757,898+4.0%
IDOT contract 78A68: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. E. T. Simonds Construction Company2. Samron Midwest Contracting, Inc.
1Bit matls tack CT (40600290)LB22,070$0.01$0.01
2Long joint sealant (40600370)LF16,893$2.43$2.60
3Matl transfer device (40600405)TON4,123$2.98$1.30
4Temporary ramp (40600990)SY157$29.86$15.00
5HMA SC IL-9.5 C N70 (40604052)TON4,123$84.93$85.00
6Incidental HMA surf (40800050)TON42$215.60$450.00
7HMA surf rem 1 1/2 (44000155)SY48,804$1.05$1.30
8CL C patch T2 14 (44201403)SY381$210.00$240.00
9CL C patch T3 14 (44201407)SY224$205.00$235.00
10Agg wedge SHLD type B (48102100)TON268$61.30$65.00
11Engr field office A (67000400)CAL MO2$2,200.00$1,800.00
12Mobilization (67100100)LS1$64,830$45,000
13Traf cont-prot 701201 (70100450)LS1$0.01$0.01
14Traf cont-prot 701306 (70100460)LS1$13,172$25,000
15Traf cont-prot 701336 (70100600)LS1$11,404$9,700.00
16Changeable message SN (70107025)CAL DAY28$39.38$85.00
17Short term pavt mking (70300100)LF3,131$1.63$1.70
18SHRT TRM pavt MK rem (70300150)SF1,566$0.01$2.15
19Temp PVT MK line 4 - paint (70300221)LF39,923$0.01$0.01
20Paint PVT MK line 4 (78001110)LF39,923$0.14$0.15
21Raised refl pavt MKR (78100100)EACH217$37.04$36.50
22Raised ref PVT MK rem (78300200)EACH217$5.97$13.50
23PVT MKG rem grinding (78300201)SF13,309$0.01$0.01
IDOT contract 78A68: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy