IDOT contract 80B18 bid tabulation
Section 2025-1092-RS. Let by Illinois DOT on January 16, 2026, Cook, District 01. 3 bids received; low bid $556,373 by Everlast Blacktop Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 49
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Everlast Blacktop Inc. | $556,373 | Low |
| 2 | Schroeder Asphalt Services, Inc. | $562,934 | +1.0% |
| 3 | Plote Construction, Inc. | $675,191 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Everlast Blacktop Inc. | 2. Schroeder Asphalt Services, Inc. | 3. Plote Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | Tree rem < 6 unit dia (X2010106) | UNIT | 150 | $33.00 | $34.00 | $30.00 |
| 2 | Tree remov acres SPL (X2010350) | ACRE | 0.25 | $22,000 | $23,000 | $20,000 |
| 3 | Selective clearing (X2010516) | UNIT | 2 | $700.00 | $700.00 | $600.00 |
| 4 | PCC surf rem var DP (X4400100) | SY | 1,193 | $12.57 | $8.00 | $10.00 |
| 5 | Median surf removal (X4403800) | SF | 239 | $36.00 | $6.00 | $20.00 |
| 6 | SS cleaned 12 (X5537800) | LF | 240 | $2.00 | $2.00 | $1.00 |
| 7 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $3,500.00 | $3,250.00 | $3,600.00 |
| 8 | Temp info signing (X7200061) | SF | 102.80 | $18.00 | $22.00 | $16.00 |
| 9 | Det loop repl (X8860105) | LF | 331 | $37.00 | $38.50 | $34.00 |
| 10 | Drainage STR cleaned (Z0018500) | EACH | 8 | $550.00 | $530.00 | $450.00 |
| 11 | Tree remov 6-15 (20100110) | UNIT | 250 | $33.00 | $34.00 | $30.00 |
| 12 | Tree remov over 15 (20100210) | UNIT | 100 | $44.00 | $45.00 | $40.00 |
| 13 | Mowing (25000750) | ACRE | 2 | $600.00 | $600.00 | $500.00 |
| 14 | Sub gran mat B (31101100) | CY | 44 | $58.00 | $60.00 | $75.00 |
| 15 | Bit matls tack CT (40600290) | LB | 5,364 | $0.01 | $0.01 | $0.01 |
| 16 | Long joint sealant (40600370) | LF | 4,037 | $3.90 | $4.20 | $4.80 |
| 17 | Mix CR JTS flangewys (40600400) | TON | 11.90 | $925.00 | $350.00 | $600.00 |
| 18 | HMA surf rem butt JT (40600982) | SY | 101 | $36.00 | $10.00 | $65.00 |
| 19 | P HMA BC IL19.0 N90 (40603240) | TON | 1,002 | $104.96 | $105.00 | $135.00 |
| 20 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 779 | $126.16 | $145.00 | $150.00 |
| 21 | Protective coat (42001300) | SY | 219 | $4.00 | $0.02 | $1.00 |
| 22 | HMA surf rem 4 (44000165) | SY | 7,946 | $4.47 | $4.10 | $6.00 |
| 23 | Comb curb gutter rem (44000500) | LF | 142 | $11.00 | $13.00 | $12.00 |
| 24 | Median removal (44003100) | SF | 1,411 | $5.00 | $5.00 | $9.00 |
| 25 | CL D patch T2 10 (44201765) | SY | 299 | $103.90 | $120.00 | $125.00 |
| 26 | CL D patch T3 10 (44201769) | SY | 18 | $290.00 | $160.00 | $124.00 |
| 27 | CL D patch T4 10 (44201771) | SY | 94 | $118.40 | $150.00 | $123.00 |
| 28 | Comb CC&G TM4.12 (60608562) | LF | 349 | $34.30 | $80.00 | $45.00 |
| 29 | Conc median surf 4 (60618300) | SF | 1,325 | $15.18 | $16.50 | $18.00 |
| 30 | Rem & rein delineator (63500310) | EACH | 1 | $2,000.00 | $6,000.00 | $200.00 |
| 31 | Mobilization (67100100) | LS | 1 | $22,059 | $25,000 | $37,000 |
| 32 | Traf cont-prot 701421 (70100310) | LS | 1 | $30,000 | $6,000.00 | $100.00 |
| 33 | TR cont & prot 701601 (70102630) | LS | 1 | $3,800.00 | $6,000.00 | $90,700 |
| 34 | TR cont & prot 701701 (70102635) | LS | 1 | $3,800.00 | $6,000.00 | $1.00 |
| 35 | Short term pavt mking (70300100) | LF | 4,840 | $1.00 | $2.00 | $0.10 |
| 36 | SHRT TRM pavt MK rem (70300150) | SF | 404 | $1.00 | $4.00 | $0.10 |
| 37 | Temp PVT MK LTR & sym paint (70300211) | SF | 438 | $2.00 | $2.00 | $1.75 |
| 38 | Temp PVT MK line 4 - paint (70300221) | LF | 3,928 | $0.45 | $0.45 | $0.44 |
| 39 | Temp PVT MK line 6 - paint (70300241) | LF | 2,291 | $0.68 | $0.62 | $0.68 |
| 40 | Temp PVT MK line 24 - paint (70300281) | LF | 136 | $2.00 | $1.80 | $6.75 |
| 41 | Temp PVT MK L4 T4 tape (70307120) | LF | 1,211 | $1.40 | $1.40 | $1.75 |
| 42 | THPL PVT MK LTR & sym (78000100) | SF | 219 | $12.00 | $17.00 | $6.00 |
| 43 | THPL PVT MK line 4 (78000200) | LF | 1,384 | $1.75 | $2.10 | $1.10 |
| 44 | THPL PVT MK line 6 (78000400) | LF | 1,145 | $3.30 | $3.35 | $1.78 |
| 45 | THPL PVT MK line 24 (78000650) | LF | 68 | $18.00 | $14.00 | $6.00 |
| 46 | Pref PL PM TD STD L 6 (78004630) | LF | 580 | $16.00 | $17.00 | $8.50 |
| 47 | GRV RCSD PVT MRKG 7 (78011035) | LF | 580 | $3.30 | $4.80 | $4.00 |
| 48 | Raised refl pavt MKR (78100100) | EACH | 92 | $92.00 | $82.00 | $62.00 |
| 49 | Raised ref PVT MK rem (78300200) | EACH | 84 | $40.00 | $15.00 | $18.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.