IDOT contract 87864 bid tabulation

Project Number: Ivxf-925- / /, section 22-00182-01-TL. Let by Illinois DOT on August 1, 2025, Dekalb, District 03. 1 bid received; low bid $624,037 by Helm Electric Facility Solutions, Inc. d/b/a Helm Electric.

Owner
Illinois DOT
Letting
01 AUG 2025
Pay items
72
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Helm Electric Facility Solutions, Inc. d/b/a Helm Electric$624,037Low
IDOT contract 87864: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Helm Electric Facility Solutions, Inc. d/b/a Helm Electric
1Rel EX UPS bat BU sys (XX005800)EACH1$2,175.00
2Constructn layout SPL (X0320050)LS1$10,000
3EM veh P S LSC 20 3C (X0324085)LF262$1.83
4Ped signal post 10 FT (X1400367)EACH1$2,008.80
5Ped signal post 5 FT (X1400378)EACH2$1,720.80
6GPS clock sync unit (X1400437)EACH4$2,069.55
7Temp info signing (X7200061)SF77$31.50
8Rem EX sign panel (X7240195)EACH8$210.00
9Intercept EX conduit (X8100863)EACH2$850.00
10Fac T4 cab SPL (X8570226)EACH1$32,219
11Fac T super R cab SP (X8570235)EACH1$37,919
12Accessible ped signal (X8760200)EACH8$1,701.30
13Conc FDN TY A 12D (X8780012)LF12$423.75
14Mod EX TY D FDN (X8780402)EACH1$2,740.00
15TS BCKPLT L F PL SPL (X8820014)EACH34$353.12
16Loop det testing (X8860100)EACH1$1,260.00
17Video veh det sys (X8891001)EACH4$35,819
18Vid & rad hyb det sys (X8891301)EACH1$47,603
19Perm TR signal timing (Z0073509)EACH2$630.00
20Inlet filters (28000510)EACH1$210.00
21Agg base cse B 4 (35101600)SY63$10.50
22Incidental HMA surf (40800050)TON1$525.00
23PC conc sidewalk 5 (42400200)SF412$38.85
24Detectable warnings (42400800)SF44$26.25
25Pavement rem (44000100)SY12$36.75
26Comb curb gutter rem (44000500)LF59$42.00
27Sidewalk rem (44000600)SF393$8.40
28Comb CC&G TB6.12 aep (60603900)LF59$194.57
29Non SPL waste disposl (66900200)CY1$63.89
30Soil disposal analy (66900530)EACH1$1,522.50
31Reg sub P-const plan (66901001)LS1$3,150.00
32Reg sub F con report (66901003)LS1$945.00
33Reg sub mon (66901006)CAL DAY1$1,039.50
34Mobilization (67100100)LS1$40,000
35Traf cont-prot 701421 (70100310)LS1$105.00
36TR cont & prot 701701 (70102635)LS1$21,788
37TR cont & prot 701801 (70102640)LS1$105.00
38Sign panel T1 (72000100)SF64.50$57.75
39Sign panel T2 (72000200)SF119$63.00
40THPL PVT MK line 6 (78000400)LF244$13.65
41PVT MKG rem WTR blast (78300202)SF65$63.00
42Undrgrd C galvs 2 (81028200)LF216$38.62
43Undrgrd C galvs 4 (81028240)LF10$81.46
44Undrgrd C PVC 2 (81028350)LF36$25.73
45Undrgrd C PVC 3 (81028370)LF72$30.38
46Handhole (81400100)EACH2$3,255.00
47EC C XLP use 1C 10 (81702110)LF404$1.69
48Main EX TR sig instal (85000200)EACH6$1,750.00
49Uninter power sup STD (86200200)EACH1$8,994.00
50Elcbl C signal 14 2C (87301215)LF1,310$1.72
51Elcbl C signal 14 3C (87301225)LF1,613$1.88
52Elcbl C signal 14 5C (87301245)LF881$2.26
53Elcbl C signal 14 7C (87301255)LF3,331$2.60
54Elcbl C serv 6 2C (87301805)LF544$3.40
55Elcbl C egrdc 6 1C (87301900)LF682$2.33
56TS post galvs 16 (87502500)EACH1$3,337.50
57Conc FDN TY A (87800100)LF4$504.00
58Conc FDN TY C (87800150)LF4$736.25
59Drill EX handhole (87900200)EACH5$890.00
60SH P LED 1F 3S BM (88040070)EACH1$1,825.20
61SH P LED 1F 3S mam (88040090)EACH3$1,974.00
62SH P LED 1F 5S BM (88040150)EACH9$2,674.80
63SH P LED 1F 5S mam (88040160)EACH11$2,842.80
64Ped SH P LED 1F BM CT (88102825)EACH8$844.80
65Det loop T1 (88600100)LF108$55.58
66Rel EM veh PR sys P U (89501410)EACH2$850.00
67Mod EX contr (89502200)EACH1$1,302.00
68Rem elcbl FR con (89502300)LF7,933$0.95
69Rem & RE elcbl FR con (89502350)LF2,548$1.58
70Remov EX TS equip (89502375)EACH2$3,600.00
71Remov EX handhole (89502380)EACH1$850.00
72Remov EX conc FDN (89502385)EACH2$850.00
IDOT contract 87864: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy