IDOT contract 93803 bid tabulation

Project Number: V2L4-333 / /, section 20-00145-00-PV. Let by Illinois DOT on January 17, 2025, Montgomery, District 06. 2 bids received; low bid $512,832 by Illinois Valley Paving, a div of UCM, Inc..

Owner
Illinois DOT
Letting
17 JAN 2025
Pay items
27
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Illinois Valley Paving, a div of UCM, Inc.$512,832Low
2Stutz Excavating, Inc.$535,296+4.0%
IDOT contract 93803: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Illinois Valley Paving, a div of UCM, Inc.2. Stutz Excavating, Inc.
1Traf cont & prot SPL (X7010216)LS1$15,910$9,000.00
2Construction layout (Z0013798)LS1$9,108.88$17,250
3Earth excavation (20200100)CY1,690$27.15$40.25
4Furnished excavation (20400800)CY756$78.98$31.85
5Seeding CL 2 (25000200)ACRE2$2,703.75$6,500.00
6Nitrogen fert nutr (25000400)LB180$1.68$10.00
7Phosphorus fert nutr (25000500)LB180$1.68$10.00
8Potassium fert nutr (25000600)LB180$1.68$10.00
9Agr ground limestone (25000700)TON4$367.50$1,200.00
10Mulch method 2 (25100115)ACRE2$1,863.75$6,200.00
11Temp ditch checks (28000305)LF220$10.70$11.30
12Perimeter eros bar (28000400)LF3,152$5.70$5.95
13Agg base cse A (35100100)TON2,096$49.24$49.90
14Agg base cse B 4 (35101600)SY406$24.86$19.40
15Bit matls PR CT (40600275)LB9,658$0.87$1.25
16Bit matls tack CT (40600290)LB966$0.88$1.80
17HMA BC IL-9.5FG N50 (40602965)TON368$183.84$194.50
18HMA SC IL-9.5 C N50 (40604050)TON361$189.62$195.25
19Pavement rem (44000100)SY4,354$7.94$2.50
20HMA shoulders 6 (48203021)SY338$72.85$67.00
21Fur erect row markers (66600105)EACH15$304.57$1,500.00
22Mobilization (67100100)LS1$20,513$28,755
23Sign panel T1 (72000100)SF12$72.45$74.00
24Remov sign panel T1 (72400310)SF17$67.02$10.75
25Metal post TY A (72900100)LF24$58.80$60.00
26Paint PVT MK line 4 (78001110)LF3,832$1.02$1.10
27Paint PVT MK line 24 (78001180)LF20$6.30$12.65
IDOT contract 93803: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy