IDOT contract 97789 bid tabulation
Godfrey, section 19-00032-02-SW. Let by Illinois DOT on January 17, 2025, Madison, District 08. 1 bid received; low bid $116,495 by Stutz Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 20
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stutz Excavating, Inc. | $116,495 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stutz Excavating, Inc. |
|---|---|---|---|---|
| 1 | Conc curb SPL (X6060505) | LF | 23 | $87.00 |
| 2 | Traf cont & prot SPL (X7010216) | LS | 1 | $3,075.00 |
| 3 | Construction layout (Z0013798) | LS | 1 | $6,700.00 |
| 4 | RR prot liability ins (Z0048665) | LS | 1 | $18,000 |
| 5 | Earth excavation (20200100) | CY | 15 | $235.00 |
| 6 | Agg base cse A 4 (35100300) | SY | 141 | $22.00 |
| 7 | PCC PVT 8 jointed (42000301) | SY | 72 | $157.00 |
| 8 | PCC driveway pavt 6 (42300200) | SY | 47 | $150.00 |
| 9 | PC conc sidewalk 4 (42400100) | SF | 583 | $28.00 |
| 10 | Detectable warnings (42400800) | SF | 60 | $25.00 |
| 11 | Pavement rem (44000100) | SY | 95 | $33.00 |
| 12 | Drive pavement rem (44000200) | SY | 47 | $45.00 |
| 13 | Gutter rem (44000400) | LF | 60 | $35.00 |
| 14 | Sidewalk rem (44000600) | SF | 47 | $8.00 |
| 15 | Man adj new T1F CL (60255800) | EACH | 1 | $850.00 |
| 16 | Comb CC&G TY B-6.24 (60605000) | LF | 58 | $111.00 |
| 17 | Mobilization (67100100) | LS | 1 | $28,250 |
| 18 | Remov sign panel T1 (72400310) | SF | 2 | $65.00 |
| 19 | Reloc sin pan assy TB (72400600) | EACH | 1 | $260.00 |
| 20 | RM rel GRND MNT S sup (73500300) | EACH | 1 | $260.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.