IDOT contract 97887 bid tabulation
Mascoutah, section 24-00031-00-SW. Let by Illinois DOT on April 24, 2026, St. Clair, District 08. 3 bids received; low bid $191,388 by KRB Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 41
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | KRB Excavating, Inc. | $191,388 | Low |
| 2 | Baxmeyer Construction, Inc. | $247,418 | +29% |
| 3 | DMS Contracting, Inc. | $288,151 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. KRB Excavating, Inc. | 2. Baxmeyer Construction, Inc. | 3. DMS Contracting, Inc. |
|---|---|---|---|---|---|---|
| 1 | Pop-UP roof drains (XX009748) | EACH | 1 | $200.00 | $365.00 | $2,350.00 |
| 2 | Constructn layout SPL (X0320050) | LS | 1 | $4,500.00 | $6,190.00 | $4,750.00 |
| 3 | Manhole removal (X1200073) | EACH | 1 | $500.00 | $2,650.00 | $1,210.00 |
| 4 | Potholing (X1700066) | EACH | 5 | $500.00 | $1,080.00 | $669.00 |
| 5 | Topsoil F & P SPL (X2110100) | CY | 30 | $200.00 | $129.00 | $108.30 |
| 6 | Seeding CL 1A SPL (X2500920) | ACRE | 0.25 | $15,000 | $11,200 | $23,065 |
| 7 | Trench drain (X6010202) | EACH | 1 | $1,200.00 | $3,420.00 | $10,400 |
| 8 | Inlets TA SPL F&G SPL (X6023212) | EACH | 1 | $2,000.00 | $3,270.00 | $3,380.00 |
| 9 | Inlets SPL N1 (X6024242) | EACH | 1 | $2,800.00 | $4,215.00 | $4,950.00 |
| 10 | Inlets SPL N2 (X6024244) | EACH | 1 | $3,000.00 | $3,680.00 | $4,640.00 |
| 11 | Inlets SPL N3 (X6024246) | EACH | 1 | $3,000.00 | $5,400.00 | $4,950.00 |
| 12 | Fill inlets SPL (X6050310) | EACH | 1 | $500.00 | $778.00 | $2,360.00 |
| 13 | Remov FR & GR SPL (X6050500) | EACH | 1 | $250.00 | $1,430.00 | $700.00 |
| 14 | Traf cont & prot SPL (X7010216) | LS | 1 | $12,775 | $8,745.00 | $20,000 |
| 15 | P MT FL beac ins SPL (Z0033058) | EACH | 4 | $8,800.00 | $8,800.00 | $9,665.00 |
| 16 | Tree remov over 15 (20100210) | UNIT | 30 | $125.00 | $250.00 | $115.00 |
| 17 | Trench backfill (20800150) | CY | 20 | $45.00 | $63.00 | $122.00 |
| 18 | Grading & shap ditch (21400100) | LF | 20 | $30.00 | $19.00 | $50.00 |
| 19 | Inlet & pipe protect (28000500) | EACH | 15 | $100.00 | $0.01 | $260.00 |
| 20 | Sub gran mat B 4 (31101200) | SY | 274 | $13.00 | $31.00 | $26.25 |
| 21 | PC conc sidewalk 4 (42400100) | SF | 2,083 | $13.00 | $9.00 | $9.80 |
| 22 | PC conc sidewalk 6 (42400300) | SF | 380 | $13.75 | $44.00 | $17.00 |
| 23 | Detectable warnings (42400800) | SF | 102 | $30.00 | $40.00 | $106.00 |
| 24 | Pavement rem (44000100) | SY | 87 | $25.00 | $56.00 | $47.40 |
| 25 | Comb curb gutter rem (44000500) | LF | 193 | $11.00 | $22.00 | $21.40 |
| 26 | Sidewalk rem (44000600) | SF | 1,881 | $2.75 | $2.00 | $2.80 |
| 27 | CL D patch T3 8 (44201745) | SY | 21 | $225.00 | $275.00 | $320.00 |
| 28 | Pipe culvert remov (50105220) | LF | 20 | $8.00 | $24.00 | $69.20 |
| 29 | Concrete collar (54248510) | CY | 3 | $375.00 | $1,501.00 | $528.00 |
| 30 | Storm sew CL A 1 12 (550A0050) | LF | 58 | $98.00 | $82.00 | $110.00 |
| 31 | Storm sew CL A 1 15 (550A0070) | LF | 44 | $105.00 | $128.00 | $146.80 |
| 32 | Storm sewer rem 15 (55100700) | LF | 24 | $8.00 | $28.00 | $57.70 |
| 33 | Man TA 4 dia T3F&G (60218500) | EACH | 1 | $2,950.00 | $3,725.00 | $5,340.00 |
| 34 | Comb CC&G TB6.18 (60604400) | LF | 250 | $54.00 | $141.00 | $97.74 |
| 35 | Mobilization (67100100) | LS | 1 | $10,500 | $15,025 | $35,000 |
| 36 | Sign panel T1 (72000100) | SF | 44 | $27.00 | $26.00 | $87.00 |
| 37 | Remov sin pan assy TA (72400100) | EACH | 2 | $250.00 | $186.00 | $655.00 |
| 38 | Metal post TY A (72900100) | LF | 56 | $17.50 | $17.00 | $30.00 |
| 39 | THPL PVT MK line 4 (78000200) | LF | 172 | $3.25 | $3.25 | $3.50 |
| 40 | THPL PVT MK line 12 (78000600) | LF | 13 | $19.50 | $19.00 | $21.00 |
| 41 | THPL PVT MK line 24 (78000650) | LF | 371 | $30.00 | $29.25 | $32.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.