INDOT contract B-43231-A bid tabulation
BRIDGE PAINTING. Let by Indiana DOT on February 12, 2025, Crawford, Sullivan, Vanderburgh, Vincennes. 4 bids received; low bid $1,594,462 by Eagle Painting & Maintenance Company Inc.
- Owner
- Indiana DOT
- Letting
- 12 FEB 2025
- Pay items
- 53
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eagle Painting & Maintenance Company Inc | $1,594,462 | Low |
| 2 | American Industrial Coatings Inc | $1,613,527 | +1.0% |
| 3 | Three Star Painting Inc | $1,713,440 | +7.0% |
| 4 | Civil Coatings and Construction Inc | $1,858,125 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Painting & Maintenance Company Inc | 2. American Industrial Coatings Inc | 3. Three Star Painting Inc | 4. Civil Coatings and Construction Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $500.00 | $10,000 | $15,000 | $1.00 |
| 0002 | Railroad flagging budget (107-12976) | DOL | 50,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $79,000 | $52,700 | $125,520 | $80,000 |
| 0011 | Conduit, remove , existing conduit attached to bridge (202-01845) | LFT | 225 | $10.00 | $25.00 | $4.50 | $5.00 |
| 0012 | Remove , existing walkway hardware (202-07003) | LS | 1 | $5,000.00 | $3,000.00 | $2,000.00 | $2,000.00 |
| 0013 | Clean steel bridge, QP-2, bridge no. 1 (619-11052) | LS | 1 | $129,000 | $80,518 | $184,278 | $241,000 |
| 0014 | Clean steel bridge, QP-2, bridge no. 2 (619-11052) | LS | 1 | $86,000 | $80,518 | $104,880 | $130,000 |
| 0015 | Clean steel bridge, QP-2, bridge no. 3 (619-11052) | LS | 1 | $98,000 | $80,518 | $152,778 | $160,000 |
| 0016 | Clean steel bridge, QP-2, bridge no. 4 (619-11052) | LS | 1 | $164,150 | $80,518 | $232,078 | $265,702 |
| 0017 | Clean steel bridge, QP-2, bridge no. 5 (619-11052) | LS | 1 | $164,150 | $80,518 | $232,078 | $265,702 |
| 0018 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $12,000 | $5,000.00 | $1,280.00 | $1.00 |
| 0019 | Disposal of cleaning waste, hazardous, bridge no. 2 (619-12459) | LS | 1 | $8,000.00 | $5,000.00 | $1,280.00 | $1.00 |
| 0020 | Disposal of cleaning waste, hazardous, bridge no. 3 (619-12459) | LS | 1 | $10,000 | $5,000.00 | $1,280.00 | $1.00 |
| 0021 | Disposal of cleaning waste, hazardous, bridge no. 4 (619-12459) | LS | 1 | $14,000 | $5,000.00 | $1,280.00 | $1.00 |
| 0022 | Disposal of cleaning waste, hazardous, bridge no. 5 (619-12459) | LS | 1 | $14,000 | $5,000.00 | $1,280.00 | $1.00 |
| 0023 | Coat steel bridge, bridge no. 1 (619-51859) | LS | 1 | $38,750 | $48,499 | $16,278 | $25,000 |
| 0024 | Coat steel bridge, bridge no. 2 (619-51859) | LS | 1 | $25,000 | $48,499 | $9,456.00 | $15,000 |
| 0025 | Coat steel bridge, bridge no. 3 (619-51859) | LS | 1 | $30,300 | $48,499 | $12,778 | $20,000 |
| 0026 | Coat steel bridge, bridge no. 4 (619-51859) | LS | 1 | $57,140 | $48,499 | $21,397 | $30,000 |
| 0027 | Coat steel bridge, bridge no. 5 (619-51859) | LS | 1 | $57,140 | $48,499 | $21,397 | $30,000 |
| 0028 | Computer system equipment (628-11976) | EACH | 2 | $300.00 | $500.00 | $100.00 | $50.00 |
| 0029 | Field office, type D (628-12683) | MOS | 8 | $800.00 | $500.00 | $2,000.00 | $50.00 |
| 0030 | Repair , pack rust and sealant (711-05728) | EACH | 22 | $3,637.00 | $2,280.00 | $4,750.00 | $2,280.00 |
| 0031 | Repair weld (711-11599) | IN | 44.38 | $456.00 | $456.00 | $375.00 | $456.00 |
| 0032 | Structural steel (711-51038) | LS | 1 | $20,350 | $20,350 | $10,000 | $20,350 |
| 0033 | Drilled hole , bridge no. 1 (711-51864) | EACH | 216 | $300.00 | $300.00 | $300.00 | $300.00 |
| 0034 | Construction sign, type D (801-03291) | EACH | 2 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0035 | Road closure sign assembly (801-04308) | EACH | 2 | $200.00 | $200.00 | $200.00 | $200.00 |
| 0036 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 61,330 | $1.90 | $2.25 | $2.25 | $2.25 |
| 0037 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0038 | Detour route marker assembly (801-06625) | EACH | 61 | $85.00 | $85.00 | $85.00 | $85.00 |
| 0039 | Construction sign, type A (801-06640) | EACH | 62 | $225.00 | $225.00 | $225.00 | $225.00 |
| 0040 | Construction sign, type B (801-06645) | EACH | 11 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0041 | Flashing arrow sign (801-06710) | DAY | 90 | $35.00 | $35.00 | $35.00 | $35.00 |
| 0042 | Maintaining traffic (801-06775) | LS | 1 | $52,000 | $100,000 | $60,000 | $104,576 |
| 0043 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 3 | $10,000 | $11,884 | $4,000.00 | $8,000.00 |
| 0044 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $12,000 | $19,000 | $4,000.00 | $12,000 |
| 0045 | Barricade, type III-B (801-07119) | LFT | 108 | $18.00 | $18.00 | $18.00 | $18.00 |
| 0046 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,080 | $26.00 | $130.00 | $5.00 | $5.00 |
| 0047 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 700 | $24.00 | $171.00 | $5.00 | $5.00 |
| 0048 | Portable changeable message sign (801-11642) | EACH | 6 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0049 | Truck mounted attenuator (801-12042) | DAY | 28 | $200.00 | $200.00 | $200.00 | $200.00 |
| 0050 | Portable signal (801-12081) | LS | 1 | $7,400.00 | $4,750.00 | $5,000.00 | $5,000.00 |
| 0051 | Law enforcement officer (801-12324) | HRS | 120 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0052 | Driveway assistance device (801-12482) | EACH | 2 | $1,900.00 | $3,000.00 | $1,500.00 | $1,500.00 |
| 0053 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 8 | $500.00 | $500.00 | $500.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.