Eagle Painting & Maintenance Company Inc: INDOT bid record
Eagle Painting & Maintenance Company Inc submitted 19 bids on Indiana DOT contracts in the data, from 16 NOV 2022 to 05 NOV 2026, and was the low bidder on 10 of them (53%). When it was not low, its total sat a median +42% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $5,002,824
- Latest bid
- 05 NOV 2026
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 1 | 0 | 0% |
| 2023 | 3 | 1 | 33% |
| 2024 | 5 | 3 | 60% |
| 2025 | 5 | 4 | 80% |
| 2026 | 5 | 2 | 40% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Seymour | 4 | 3 | 75% |
| LaPorte | 4 | 2 | 50% |
| Crawfordsville | 3 | 2 | 67% |
| Vincennes | 3 | 1 | 33% |
| Greenfield | 3 | 2 | 67% |
| Fort Wayne | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 18 | 18 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 18 | 18 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 18 | 18 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 13 | 13 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 11 | 11 (100%) | $1.00 | $1.00 |
| Construction sign, type A | 801-06640 | EACH | 14 | 10 (71%) | $200.00 | $200.00 |
| Stormwater management budget | 205-12108 | DOL | 10 | 10 (100%) | $1.00 | $1.00 |
| Project estimate adjustment | 109-08463 | DOL | 10 | 10 (100%) | $1.00 | $1.00 |
| Flashing arrow sign | 801-06710 | DAY | 10 | 9 (90%) | $25.00 | $17.00 |
| Mobilization and demobilization for seeding | 621-01004 | EACH | 9 | 9 (100%) | $100.00 | $525.00 |
| Construction sign, type B | 801-06645 | EACH | 9 | 8 (89%) | $100.00 | $105.00 |
| Road closure sign assembly | 801-04308 | EACH | 7 | 7 (100%) | $200.00 | $280.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Civil Coatings and Construction Inc | 15 | 2 of 15 |
| Three Star Painting Inc | 14 | 4 of 14 |
| Olympus Painting LLC | 8 | 4 of 8 |
| Central Painting Inc | 7 | 3 of 7 |
| Venus Painting Company | 4 | 2 of 4 |
| Pioneer Associates Inc | 3 | 2 of 3 |
| Milestone Contractors LP | 3 | 2 of 3 |
| N I Spanos Painting Inc | 3 | 1 of 3 |
| Rieth-Riley Construction Co., Inc. | 2 | 0 of 2 |
| American Industrial Coatings Inc | 2 | 0 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 NOV 2026 | B-44653-A | LaPorte | BRIDGE COATING | 1 of 2 | $431,170 | Low, 131% under the second |
| 05 AUG 2026 | B-44638-A | LaPorte | BRIDGE COATING | 2 of 4 | $243,166 | +12% |
| 05 AUG 2026 | B-44931-A | Fort Wayne | BRIDGE COATING | 3 of 4 | $612,853 | +82% |
| 08 JUL 2026 | B-43938-A | Greenfield | BRIDGE COATING | 1 of 5 | $417,021 | Low, 2.0% under the second |
| 11 FEB 2026 | B-44930-A | Fort Wayne | SCOUR PROTECTION | 2 of 5 | $453,239 | +30% |
| 13 NOV 2025 | B-43778-A | Seymour | BRIDGE COATING | 1 of 7 | $196,966 | Low, 3.0% under the second |
| 08 OCT 2025 | B-44650-A | Greenfield | SUBSTRUCTURE REPAIR AND REHABILITATION | 7 of 7 | $507,090 | +101% |
| 12 FEB 2025 | B-43231-A | Vincennes | BRIDGE PAINTING | 1 of 4 | $1,594,462 | Low, 1.0% under the second |
| 12 FEB 2025 | B-45003-A | Greenfield | BRIDGE PAINTING | 1 of 4 | $481,758 | Low, 12% under the second |
| 15 JAN 2025 | B-44689-A | LaPorte | SUBSTRUCTURE REPAIR AND REHABILITATION | 1 of 4 | $229,000 | Low, 5.0% under the second |
| 14 NOV 2024 | B-43413-A | Seymour | BRIDGE PAINTING | 2 of 4 | $141,703 | +43% |
| 14 NOV 2024 | B-44937-A | Crawfordsville | BRIDGE MAINTENANCE AND REPAIR | 1 of 5 | $238,505 | Low, 15% under the second |
| 10 APR 2024 | B-44416-A | Seymour | BRIDGE PAINTING | 1 of 4 | $178,504 | Low, 15% under the second |
| 13 MAR 2024 | B-43063-A | LaPorte | BRIDGE PAINTING | 5 of 6 | $664,204 | +272% |
| 13 MAR 2024 | B-44045-A | Crawfordsville | BRIDGE MAINTENANCE AND REPAIR | 1 of 4 | $439,710 | Low, 22% under the second |
| 09 AUG 2023 | B-42740-B | Vincennes | BRIDGE PAINTING | 2 of 5 | $2,586,583 | +22% |
| 10 MAY 2023 | B-42882-A | Seymour | BRIDGE PAINTING | 1 of 4 | $795,730 | Low, 12% under the second |
| 19 JAN 2023 | B-42820-A | Vincennes | BRIDGE PAINTING | 6 of 7 | $4,409,791 | +41% |
| 16 NOV 2022 | B-43207-A | Crawfordsville | BRIDGE PAINTING | 6 of 7 | $1,648,437 | +48% |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.