INDOT contract B-44930-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on February 11, 2026, Whitley, Fort Wayne. 5 bids received; low bid $349,330 by Pioneer Associates Inc.
- Owner
- Indiana DOT
- Letting
- 11 FEB 2026
- Pay items
- 26
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pioneer Associates Inc | $349,330 | Low |
| 2 | Eagle Painting & Maintenance Company Inc | $453,239 | +30% |
| 3 | Milestone Contractors LP | $455,285 | +30% |
| 4 | Yarberry Companies Inc | $526,152 | +51% |
| 5 | Morphey Construction Inc. | $582,120 | +67% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pioneer Associates Inc | 2. Eagle Painting & Maintenance Company Inc | 3. Milestone Contractors LP | 4. Yarberry Companies Inc | 5. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $1,500.00 | $500.00 | $5,000.00 | $15,000 | $5,000.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $17,500 | $8,000.00 | $22,264 | $25,000 | $50,000 |
| 0008 | Clearing right-of-way (201-52370) | LS | 1 | $10,500 | $500.00 | $23,000 | $25,000 | $50,000 |
| 0009 | Stormwater management budget (205-12108) | DOL | 24,790 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Stormwater management implementation (205-12616) | LS | 1 | $1,500.00 | $18,000 | $1,400.00 | $27,000 | $2,500.00 |
| 0011 | Cofferdam (206-51235) | LS | 1 | $19,700 | $55,000 | $62,000 | $35,000 | $40,000 |
| 0012 | Riprap, class 2 (616-05689) | TON | 879 | $135.00 | $180.00 | $201.00 | $200.00 | $200.00 |
| 0013 | Geotextile for riprap, type 2B (616-12249) | SYS | 601 | $6.00 | $7.00 | $9.00 | $15.00 | $8.00 |
| 0014 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $250.00 | $15,000 | $250.00 | $1,000.00 | $250.00 |
| 0015 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $500.00 | $100.00 | $500.00 | $750.00 | $1,500.00 |
| 0016 | Seeding wetland (621-02356) | LBS | 7 | $425.00 | $30.00 | $425.00 | $300.00 | $3,000.00 |
| 0017 | Erosion control blanket (621-02770) | SYS | 215 | $2.75 | $12.00 | $2.75 | $8.00 | $12.00 |
| 0018 | Mulched seeding, type R (621-06559) | SYS | 1,206 | $3.00 | $1.30 | $3.00 | $2.00 | $13.00 |
| 0019 | Clean and epoxy coat existing piles (701-93790) | LS | 1 | $49,000 | $55,000 | $17,500 | $20,000 | $17,500 |
| 0020 | Concrete, A, substructure (702-51005) | CYS | 38 | $1,325.00 | $1,945.00 | $700.00 | $2,500.00 | $2,500.00 |
| 0021 | Reinforcing bars, epoxy coated (703-06029) | LBS | 2,700 | $2.00 | $3.00 | $2.50 | $7.00 | $2.50 |
| 0022 | Patching concrete structures (710-09158) | SFT | 12 | $200.00 | $600.00 | $175.00 | $300.00 | $211.00 |
| 0023 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 4 | $80.00 | $120.00 | $76.00 | $100.00 | $76.00 |
| 0024 | Epoxy injection, crack preparation (727-90308) | LFT | 143 | $70.00 | $83.00 | $106.00 | $120.00 | $106.00 |
| 0025 | Epoxy injection, furnishing equipment (727-93560) | LS | 1 | $750.00 | $1,000.00 | $965.00 | $1,500.00 | $965.00 |
| 0026 | Maintaining traffic (801-06775) | LS | 1 | $25,400 | $7,000.00 | $57,426 | $25,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.