Morphey Construction Inc.: INDOT bid record

Morphey Construction Inc. submitted 387 bids on Indiana DOT contracts in the data, from 12 JAN 2022 to 05 NOV 2026, and was the low bidder on 75 of them (19%). When it was not low, its total sat a median +27% above the low bid.

Owner
Indiana DOT
Low bid volume
$122,909,864
Latest bid
05 NOV 2026
Data through
05 NOV 2026
387Bids
75Low bids
19Win rate, percent
+27%Median gap to the low bid when not low, 307 bids

By year

YearBidsLow bidsWin rate
202254713%
2023471532%
2024951718%
2025901719%
20261011919%
Morphey Construction Inc., INDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
Greenfield1232319%
Crawfordsville972324%
Seymour8689%
Fort Wayne471634%
Vincennes1600%
LaPorte14321%
Greenfield, Seymour22100%
Crawfordsville, Greenfield100%
Crawfordsville, Vincennes100%
Morphey Construction Inc., INDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Liquidated damages109-08359DOL367367 (100%)$1.00$1.00
Contract liens109-08360DOL367367 (100%)$1.00$1.00
Quality adjustments, failed materials109-08444DOL361361 (100%)$1.00$1.00
Stormwater management budget205-12108DOL316316 (100%)$1.00$1.00
Quality adjustments, failure to maintain temporary erosion and sediment control measures109-11362DOL315315 (100%)$1.00$1.00
Quality adjustments, temporary traffic control devices109-08443DOL310310 (100%)$1.00$1.00
Quality adjustments, HMA109-08440DOL219219 (100%)$1.00$1.00
Payment adjustment, PG asphalt binder109-09489DOL191191 (100%)$1.00$1.00
Construction sign, type A801-06640EACH281155 (55%)$190.00$200.00
Project estimate adjustment109-08463DOL137137 (100%)$1.00$1.00
Road closure sign assembly801-04308EACH202126 (62%)$217.00$280.00
Detour route marker assembly801-06625EACH190124 (65%)$104.75$140.00
Morphey Construction Inc., INDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Milestone Contractors LP15294 of 152
E & B Paving LLC11480 of 114
Rieth-Riley Construction Co., Inc.7443 of 74
Olco Inc7359 of 73
5 Star Company Inc7359 of 73
Yarberry Companies Inc5716 of 57
Paul H Rohe Company Inc5340 of 53
Calumet Civil Contractors Inc5040 of 50
Dave Omara Contractor Inc4727 of 47
3D Company Inc4625 of 46
Morphey Construction Inc., INDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
05 NOV 2026R-39073-AGreenfieldBIKE AND PEDESTRIAN FACILITIES1 of 7$2,047,000Low, 1.0% under the second
05 NOV 2026R-42227-AGreenfieldINTERSECTION IMPROVEMENT, ROUNDABOUT, BIKE AND PED FACILITY6 of 7$4,249,415+17%
05 NOV 2026R-44392-ACrawfordsvilleSMALL STRUCTURES AND DRAINS CONSTRUCTION5 of 5$1,390,000+60%
05 NOV 2026R-44432-ASeymourSMALL STRUCTURE REPLACEMENT AND PIPE LINING4 of 4$1,514,600+35%
05 NOV 2026R-44492-AVincennesSMALL STRUCTURE REPLACEMENT AND PIPE LINING7 of 7$969,000+21%
05 NOV 2026R-45886-ACrawfordsvillePAVEMENT MARKINGS AND SIGN MODERNIZATION5 of 5$471,436+83%
05 NOV 2026R-46935-AGreenfieldTREE REMOVAL AND TRIMMING6 of 6$4,456,000+1133%
05 NOV 2026B-44548-AFort WayneBRIDGE REPLACEMENT AND REHABILITATION3 of 5$1,684,000+7.0%
05 NOV 2026B-44588-AGreenfieldSMALL STRUCTURES AND DRAINS CONSTRUCTION5 of 5$188,001+40%
05 NOV 2026B-46218-ASeymourSMALL STRUCTURE REPLACEMENT7 of 7$611,000+37%
05 NOV 2026B-46893-AGreenfieldTREE REMOVAL AND TRIMMING1 of 4$185,000Low, 29% under the second
05 NOV 2026M-46855-ALaPorteTREE REMOVAL AND TRIMMING3 of 5$226,000+91%
05 NOV 2026T-46195-ACrawfordsvilleTRAFFIC SIGNALS MODERNIZATION3 of 3$2,173,000+10%
07 OCT 2026R-43755-ASeymourSIGHT DISTANCE IMPROVEMENT5 of 5$461,500+31%
07 OCT 2026R-44279-ASeymourINTERSECTION IMPROVMENT WITH TRAFFIC SIGNAL MODERNIZATION3 of 4$1,395,000+26%
07 OCT 2026R-44384-ACrawfordsvilleSLIDE CORRECTION1 of 5$1,294,000Low, 8.0% under the second
07 OCT 2026R-44395-ACrawfordsvilleSMALL STRUCTURES AND DRAINS CONSTRUCTION1 of 3$396,000Low, 5.0% under the second
07 OCT 2026R-44440-ASeymourSMALL STRUCTURES AND DRAINS CONSTRUCTION4 of 4$2,900,000+71%
07 OCT 2026R-44462-ASeymourSMALL STRUCTURE REPLACEMENT, PIPE LINING AND DRAINS CONSTR3 of 5$1,921,000+15%
07 OCT 2026R-44469-ASeymourSMALL STRUCTURE PIPE LINING3 of 4$406,385+10%
07 OCT 2026R-44572-AFort WayneSMALL STRUCTURE PIPE LINING1 of 3$313,633Low, 2.0% under the second
07 OCT 2026R-44607-AGreenfieldSMALL STRUCTURES AND DRAINS CONSTRUCTION4 of 4$685,000+46%
07 OCT 2026R-44658-ALaPorteSMALL STRUCTURE REPLACEMENT3 of 6$931,346+4.0%
07 OCT 2026B-42320-AGreenfieldSCOUR PROTECTION5 of 5$2,678,887+49%
07 OCT 2026B-43499-AGreenfieldBRIDGE REPLACEMENT5 of 6$13,200,000+21%
Morphey Construction Inc.: latest INDOT bids in the data

How this record was read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy