INDOT contract B-42320-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on October 7, 2026, Marion, Greenfield. 5 bids received; low bid $1,801,428 by Yarberry Companies Inc.
- Owner
- Indiana DOT
- Letting
- 07 OCT 2026
- Pay items
- 65
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Yarberry Companies Inc | $1,801,428 | Low |
| 2 | Superior Construction Co Inc | $1,895,376 | +5.0% |
| 3 | Beaty Construction Inc | $1,924,098 | +7.0% |
| 4 | Milestone Contractors LP | $2,567,000 | +42% |
| 5 | Morphey Construction Inc. | $2,678,887 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Yarberry Companies Inc | 2. Superior Construction Co Inc | 3. Beaty Construction Inc | 4. Milestone Contractors LP | 5. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $35,000 | $100,000 | $7,817.68 | $26,500 | $50,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $86,000 | $95,000 | $83,927 | $197,100 | $300,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $30,000 | $30,000 | $37,000 | $228,742 | $10,000 |
| 0011 | Debris, remove, structure no. 1 (201-90788) | LS | 1 | $20,000 | $6,354.59 | $10,530 | $41,607 | $25,000 |
| 0012 | Cable barrier, remove (202-12024) | LFT | 500 | $8.00 | $4.00 | $4.04 | $5.50 | $30.00 |
| 0013 | Safety terminal, remove (202-12026) | EACH | 2 | $1,200.00 | $500.00 | $505.00 | $925.00 | $30.00 |
| 0014 | Inlet, remove (202-91385) | EACH | 1 | $1,000.00 | $325.13 | $3,538.83 | $1,426.44 | $1,100.00 |
| 0015 | Pipe, remove (202-96133) | LFT | 60 | $50.00 | $23.27 | $61.92 | $80.00 | $15.00 |
| 0016 | Excavation, common (203-02000) | CYS | 630 | $130.00 | $20.00 | $82.84 | $105.00 | $70.00 |
| 0017 | Temporary turbidity curtain (205-09387) | LFT | 550 | $70.00 | $58.85 | $44.46 | $75.00 | $70.00 |
| 0018 | Stormwater management budget (205-12108) | DOL | 22,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $18,000 | $7,500.00 | $32,454 | $23,560 | $2,500.00 |
| 0020 | SWQCP preparation (205-12618) | LS | 1 | $5,000.00 | $1,700.00 | $3,608.16 | $5,000.00 | $1,700.00 |
| 0021 | Subgrade treatment, type III (207-08266) | SYS | 1,130 | $30.00 | $2.66 | $5.24 | $6.00 | $10.00 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,130 | $7.00 | $4.55 | $9.04 | $7.00 | $5.00 |
| 0023 | Compacted aggregate, no. 2 (301-12231) | CYS | 280 | $120.00 | $132.48 | $103.19 | $220.00 | $115.00 |
| 0024 | Compacted aggregate, no. 53 (301-12234) | CYS | 480 | $90.00 | $125.00 | $112.88 | $146.00 | $130.00 |
| 0025 | Compacted aggregate, no. 53 (303-01180) | TON | 124 | $55.00 | $75.00 | $50.46 | $170.00 | $80.00 |
| 0026 | HMA patching, full depth, type C (304-12625) | TON | 1,012 | $165.00 | $300.00 | $220.22 | $251.00 | $300.00 |
| 0027 | HMA patching, partial depth, type C (304-12626) | TON | 468 | $140.00 | $190.00 | $206.05 | $445.00 | $250.00 |
| 0028 | Asphalt for tack coat (406-05520) | TON | 2 | $1,000.00 | $1.00 | $400.00 | $540.00 | $500.00 |
| 0029 | Guardrail, remove (601-02241) | LFT | 590 | $9.00 | $6.00 | $6.06 | $6.00 | $6.00 |
| 0030 | Guardrail, MGS W-beam, double faced, 6 FT 3 in. spacing (601-12284) | LFT | 426 | $40.00 | $34.00 | $34.34 | $36.00 | $36.00 |
| 0031 | Guardrail transition, MGS without curb (601-12292) | EACH | 2 | $4,400.00 | $3,350.00 | $3,383.50 | $3,975.00 | $3,975.00 |
| 0032 | Guardrail end treatment, type MS (601-94690) | EACH | 2 | $6,160.00 | $6,000.00 | $6,060.00 | $5,600.00 | $5,600.00 |
| 0033 | Riprap, class 1 (616-05688) | TON | 1,800 | $130.00 | $68.99 | $157.20 | $186.00 | $160.00 |
| 0034 | Riprap, class 2 (616-05689) | TON | 1,120 | $130.00 | $98.98 | $182.52 | $190.00 | $200.00 |
| 0035 | Geotextile for riprap, type 1A (616-12246) | SYS | 3,480 | $12.00 | $2.35 | $11.35 | $3.80 | $3.00 |
| 0036 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $700.00 | $425.00 | $962.18 | $800.00 | $800.00 |
| 0037 | Erosion control blanket (621-02770) | SYS | 1,270 | $6.00 | $6.68 | $9.62 | $8.00 | $30.00 |
| 0038 | Fertilizer for permanent seeding (621-06545) | TON | 0.20 | $1,500.00 | $2,115.00 | $962.18 | $800.00 | $800.00 |
| 0039 | Seed mixture, type R (621-06553) | LBS | 54 | $35.00 | $10.98 | $6.01 | $5.00 | $500.00 |
| 0040 | Cable barrier system, type TL-4 (627-09327) | LFT | 500 | $41.00 | $49.00 | $59.50 | $37.00 | $37.00 |
| 0041 | Safety terminal, type TL-3 (627-09330) | EACH | 2 | $8,877.00 | $11,500 | $13,964 | $8,070.00 | $8,070.00 |
| 0042 | Cable barrier system, type TL-4, spare parts (627-10178) | LS | 1 | $21,340 | $18,050 | $21,917 | $19,400 | $19,400 |
| 0043 | Field office, type C (628-09403) | MOS | 10 | $3,000.00 | $3,347.00 | $6,664.96 | $4,000.00 | $2,200.00 |
| 0044 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 40 | $40.00 | $30.80 | $91.04 | $30.69 | $80.00 |
| 0045 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 60 | $140.00 | $58.98 | $129.04 | $100.00 | $110.00 |
| 0046 | Pipe end section, diameter 12 in. (715-46000) | EACH | 1 | $1,500.00 | $662.27 | $1,661.36 | $1,224.93 | $1,800.00 |
| 0047 | Outlet protector, type 1 (718-06528) | EACH | 2 | $1,800.00 | $1,302.50 | $2,819.83 | $8,000.00 | $2,500.00 |
| 0048 | Inlet, type N12 (720-45065) | EACH | 1 | $6,500.00 | $7,073.54 | $13,509 | $10,000 | $10,000 |
| 0049 | Construction sign, type C (801-03290) | EACH | 28 | $240.00 | $217.00 | $240.54 | $250.00 | $217.00 |
| 0050 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 38,870 | $2.50 | $1.94 | $1.85 | $1.50 | $2.00 |
| 0051 | Construction sign, type A (801-06640) | EACH | 52 | $210.00 | $188.00 | $180.40 | $125.00 | $188.00 |
| 0052 | Construction sign, type B (801-06645) | EACH | 8 | $115.00 | $101.00 | $90.21 | $57.00 | $101.00 |
| 0053 | Maintaining traffic (801-06775) | LS | 1 | $125,000 | $472,216 | $78,755 | $251,690 | $155,000 |
| 0054 | Energy absorbing terminal, CZ, TL-3 , 3 (801-07024) | EACH | 6 | $7,370.00 | $5,000.00 | $6,435.38 | $6,700.00 | $6,700.00 |
| 0055 | Barricade, type III-B (801-07119) | LFT | 384 | $17.00 | $14.91 | $12.03 | $9.00 | $15.00 |
| 0056 | Temporary traffic barrier, type 2 (801-08401) | LFT | 2,480 | $40.00 | $10.55 | $67.78 | $50.00 | $38.00 |
| 0057 | Portable changeable message sign (801-11642) | EACH | 6 | $4,600.00 | $4,192.00 | $3,608.16 | $2,000.00 | $4,192.00 |
| 0058 | Truck mounted attenuator (801-12042) | DAY | 8 | $1,100.00 | $900.00 | $240.54 | $1,800.00 | $900.00 |
| 0059 | Delineator with post, type D2 (804-06740) | EACH | 2 | $140.00 | $33.00 | $40.07 | $125.00 | $500.00 |
| 0060 | Line, remove (808-06716) | LFT | 17,192 | $0.70 | $0.52 | $0.50 | $0.44 | $1.00 |
| 0061 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 800 | $1.20 | $1.01 | $4.00 | $3.00 | $1.00 |
| 0062 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 800 | $1.20 | $1.01 | $4.00 | $3.00 | $1.00 |
| 0063 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 200 | $1.20 | $1.01 | $4.00 | $4.00 | $1.00 |
| 0064 | Cofferdam (206-51235) | LS | 1 | $60,000 | $0.01 | $1.00 | $1.00 | $450,000 |
| 0065 | Flashing arrow sign (801-06710) | DAY | 90 | $50.00 | $16.00 | $411.04 | $10.00 | $16.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.