E & B Paving LLC: INDOT bid record
E & B Paving LLC submitted 693 bids on Indiana DOT contracts in the data, from 12 JAN 2022 to 05 NOV 2026, and was the low bidder on 256 of them (37%). When it was not low, its total sat a median +12% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $957,041,573
- Latest bid
- 05 NOV 2026
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 131 | 60 | 46% |
| 2023 | 123 | 45 | 37% |
| 2024 | 149 | 55 | 37% |
| 2025 | 154 | 55 | 36% |
| 2026 | 136 | 41 | 30% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Seymour | 191 | 64 | 34% |
| Greenfield | 158 | 44 | 28% |
| Vincennes | 157 | 60 | 38% |
| Fort Wayne | 112 | 50 | 45% |
| Crawfordsville | 37 | 18 | 49% |
| LaPorte | 30 | 15 | 50% |
| Crawfordsville, Greenfield | 4 | 2 | 50% |
| Fort Wayne, Greenfield | 2 | 1 | 50% |
| Seymour, Vincennes | 1 | 1 | 100% |
| Fort Wayne, LaPorte | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 669 | 669 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 669 | 669 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 666 | 666 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 592 | 592 (100%) | $1.00 | $1.00 |
| Quality adjustments, HMA | 109-08440 | DOL | 570 | 570 (100%) | $1.00 | $1.00 |
| Stormwater management budget | 205-12108 | DOL | 552 | 552 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 548 | 548 (100%) | $1.00 | $1.00 |
| Payment adjustment, PG asphalt binder | 109-09489 | DOL | 418 | 418 (100%) | $1.00 | $1.00 |
| Project estimate adjustment | 109-08463 | DOL | 305 | 305 (100%) | $1.00 | $1.00 |
| Mobilization and demobilization for seeding | 621-01004 | EACH | 473 | 288 (61%) | $625.00 | $525.00 |
| Grooving for pavement markings | 808-12032 | LFT | 321 | 238 (74%) | $0.66 | $0.80 |
| Construction sign, type A | 801-06640 | EACH | 463 | 237 (51%) | $200.00 | $200.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Milestone Contractors LP | 343 | 147 of 343 |
| Rieth-Riley Construction Co., Inc. | 170 | 65 of 170 |
| Ragle, Inc. | 130 | 58 of 130 |
| Morphey Construction Inc. | 114 | 34 of 114 |
| Force Construction Co Inc | 103 | 44 of 103 |
| Beaty Construction Inc | 82 | 35 of 82 |
| Brooks Construction Company Inc | 75 | 34 of 75 |
| Calumet Civil Contractors Inc | 64 | 33 of 64 |
| Mac Construction & Excavating Inc | 57 | 18 of 57 |
| CLR Inc | 57 | 39 of 57 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 NOV 2026 | R-42227-A | Greenfield | INTERSECTION IMPROVEMENT, ROUNDABOUT, BIKE AND PED FACILITY | 3 of 7 | $3,842,081 | +6.0% |
| 05 NOV 2026 | R-43746-A | Seymour | HMA OVERLAY, PREVENTIVE MAINTENANCE | 1 of 3 | $1,068,000 | Low, 30% under the second |
| 05 NOV 2026 | R-44293-A | Seymour | BIKE AND PEDESTRIAN FACILITIES | 3 of 7 | $1,485,952 | +9.0% |
| 05 NOV 2026 | R-44492-A | Vincennes | SMALL STRUCTURE REPLACEMENT AND PIPE LINING | 2 of 7 | $799,700 | 0.0% |
| 05 NOV 2026 | R-45794-A | Greenfield | PAVEMENT PATCHING | 2 of 3 | $4,553,443 | +3.0% |
| 05 NOV 2026 | R-46147-A | Seymour | HMA OVERLAY, PREVENTIVE MAINTENANCE | 3 of 3 | $5,368,844 | +3.0% |
| 05 NOV 2026 | B-44260-A | Crawfordsville | BRIDGE DECK OVERLAY AND REHABILITATION OR REPAIR | 1 of 5 | $1,668,000 | Low, 12% under the second |
| 05 NOV 2026 | B-44268-A | Greenfield | BRIDGE REHABILITATION OR REPAIR | 3 of 5 | $699,750 | +9.0% |
| 05 NOV 2026 | B-44466-A | Seymour | BRIDGE DECK OVERLAY AND COPING REPLACEMENT | 1 of 7 | $1,283,500 | Low, 1.0% under the second |
| 05 NOV 2026 | B-44533-A | Fort Wayne | REPLACE SUPERSTRUCTURE | 1 of 4 | $5,288,075 | Low, 2.0% under the second |
| 05 NOV 2026 | B-44534-A | Fort Wayne | BRIDGE DECK OVERLAY | 1 of 4 | $5,608,000 | Low, 21% under the second |
| 05 NOV 2026 | B-44548-A | Fort Wayne | BRIDGE REPLACEMENT AND REHABILITATION | 1 of 5 | $1,572,250 | Low, 1.0% under the second |
| 05 NOV 2026 | B-45063-A | Fort Wayne | BRIDGE REPLACEMENT | 1 of 6 | $1,890,766 | Low, 5.0% under the second |
| 07 OCT 2026 | R-43748-A | Seymour | SMALL STRUCTURE REPLACEMENT | 5 of 5 | $1,333,000 | +24% |
| 07 OCT 2026 | R-44440-A | Seymour | SMALL STRUCTURES AND DRAINS CONSTRUCTION | 3 of 4 | $2,156,000 | +27% |
| 07 OCT 2026 | R-44523-A | Vincennes | SMALL STRUCTURE REPLACEMENT | 5 of 5 | $995,000 | +40% |
| 07 OCT 2026 | R-44721-A | Seymour | INTERSECTION MODERNIZATIONS AND MULTI-USE PATH | 3 of 4 | $4,960,069 | +13% |
| 07 OCT 2026 | R-46652-A | Greenfield | HMA OVERLAY, PREVENTIVE MAINTENANCE | 1 of 3 | $228,457 | Low, 12% under the second |
| 07 OCT 2026 | B-43499-A | Greenfield | BRIDGE REPLACEMENT | 3 of 6 | $12,187,547 | +12% |
| 07 OCT 2026 | B-43637-A | Seymour | BRIDGE REPLACEMENT | 5 of 8 | $1,947,500 | +14% |
| 07 OCT 2026 | B-44486-A | Greenfield | BRIDGE REPLACEMENT | 4 of 5 | $4,515,000 | +8.0% |
| 07 OCT 2026 | B-44530-A | Fort Wayne | BRIDGE DECK OVERLAY | 2 of 4 | $624,200 | +5.0% |
| 07 OCT 2026 | B-44532-A | Fort Wayne | BRIDGE DECK OVERLAY | 3 of 4 | $2,556,000 | +9.0% |
| 07 OCT 2026 | B-44576-A | Greenfield | BRIDGE DECK REPLACEMENT | 5 of 5 | $6,146,500 | +27% |
| 07 OCT 2026 | B-44578-A | Greenfield | BRIDGE DECK OVERLAY, SUBSTRUCTURE REPAIR AND REHABILITATION | 1 of 4 | $744,300 | Low, 14% under the second |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.