INDOT contract B-44532-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on October 7, 2026, Wells, Fort Wayne. 4 bids received; low bid $2,352,913 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 07 OCT 2026
- Pay items
- 126
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $2,352,913 | Low |
| 2 | Pioneer Associates Inc | $2,502,366 | +6.0% |
| 3 | E & B Paving LLC | $2,556,000 | +9.0% |
| 4 | R L McCoy Inc | $2,733,217 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Pioneer Associates Inc | 3. E & B Paving LLC | 4. R L McCoy Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $75,000 | $14,500 | $60,000 | $30,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $144,121 | $285,085 | $127,809 | $136,600 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $15,900 | $22,500 | $25,375 | $27,300 |
| 0012 | Debris, remove, structure no. 1 (201-90788) | LS | 1 | $78,800 | $25,000 | $170,000 | $43,000 |
| 0013 | Pavement removal (202-02240) | SYS | 366 | $69.00 | $40.00 | $85.00 | $70.00 |
| 0014 | Curb, concrete, remove (202-02278) | LFT | 52 | $23.20 | $32.00 | $20.00 | $60.00 |
| 0015 | Curb and gutter, remove (202-02279) | LFT | 145 | $17.50 | $18.00 | $20.00 | $40.00 |
| 0016 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $25,000 | $17,900 | $50,000 | $200,000 |
| 0017 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $60,000 | $34,200 | $100,000 | $200,000 |
| 0018 | Sidewalk concrete, remove (202-52710) | SYS | 28 | $38.00 | $200.00 | $25.00 | $65.00 |
| 0019 | Excavation, common (203-02000) | CYS | 305 | $50.50 | $80.00 | $60.00 | $80.00 |
| 0020 | Linear grading (203-08607) | LFT | 424 | $9.65 | $14.00 | $10.00 | $20.00 |
| 0021 | Stormwater management budget (205-12108) | DOL | 7,500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0022 | Stormwater management implementation (205-12616) | LS | 1 | $3,600.00 | $800.00 | $7,500.00 | $8,000.00 |
| 0023 | Cofferdam , bridge no. 2 (206-51235) | LS | 1 | $36,000 | $18,500 | $100,000 | $100,000 |
| 0024 | Subgrade treatment, type II (207-08264) | SYS | 47 | $57.00 | $55.00 | $60.00 | $135.00 |
| 0025 | Subgrade treatment, type IC (207-09935) | SYS | 336 | $76.50 | $55.00 | $75.00 | $90.00 |
| 0026 | Geogrid, type IB (214-11796) | SYS | 12 | $60.75 | $15.00 | $25.00 | $80.00 |
| 0027 | Geotextile for pavement, type 2B (214-12239) | SYS | 672 | $7.50 | $10.00 | $5.00 | $8.00 |
| 0028 | Compacted aggregate, no. 53 (301-12234) | CYS | 44 | $139.25 | $150.00 | $125.00 | $150.00 |
| 0029 | Dense graded subbase (302-07455) | CYS | 2 | $250.00 | $400.00 | $150.00 | $500.00 |
| 0030 | Compacted aggregate, no. 53 (303-01180) | TON | 102 | $86.00 | $65.00 | $55.00 | $60.00 |
| 0031 | Milling, transition (306-08043) | SYS | 1,622 | $10.25 | $4.00 | $5.00 | $6.00 |
| 0032 | Lean concrete base, 9 in. (309-12695) | SYS | 336 | $66.60 | $115.00 | $90.00 | $115.00 |
| 0033 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 95 | $147.00 | $147.00 | $198.73 | $147.00 |
| 0034 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 68 | $210.00 | $210.00 | $273.33 | $210.00 |
| 0035 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 14 | $257.00 | $257.00 | $329.36 | $257.00 |
| 0036 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 30 | $272.00 | $272.00 | $245.66 | $272.00 |
| 0037 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 167 | $172.00 | $172.00 | $164.74 | $172.00 |
| 0038 | Joint adhesive (401-11526) | LFT | 1,320 | $0.50 | $0.50 | $1.63 | $0.50 |
| 0039 | Asphalt for tack coat (406-05520) | TON | 2 | $800.00 | $800.00 | $1.00 | $800.00 |
| 0040 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 1 | $2,500.00 | $2,500.00 | $7,302.87 | $2,500.00 |
| 0041 | Terminal joint, type HMA , modified (503-12477) | LFT | 95 | $192.00 | $280.00 | $350.00 | $375.00 |
| 0042 | Joints in PCCP, filled (507-08271) | LFT | 94 | $24.50 | $15.00 | $15.00 | $15.00 |
| 0043 | Guardrail, remove (601-02241) | LFT | 374 | $6.00 | $5.00 | $6.00 | $6.00 |
| 0044 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 63 | $25.00 | $23.00 | $25.00 | $25.00 |
| 0045 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $1,281.00 | $1,025.00 | $1,281.00 | $1,281.00 |
| 0046 | Guardrail transition, MGS without curb (601-12292) | EACH | 3 | $3,237.00 | $3,770.00 | $3,237.00 | $3,237.00 |
| 0047 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $3,211.00 | $4,000.00 | $3,211.00 | $3,211.00 |
| 0048 | Sidewalk, concrete (604-06070) | SYS | 28 | $110.00 | $190.00 | $237.99 | $225.00 |
| 0049 | Curb, concrete (605-06120) | LFT | 52 | $38.00 | $95.00 | $81.95 | $115.00 |
| 0050 | Curb and gutter, concrete (605-06140) | LFT | 147 | $45.00 | $75.00 | $88.96 | $110.00 |
| 0051 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 336 | $167.50 | $300.00 | $225.00 | $200.00 |
| 0052 | HMA for approaches, type B (610-07487) | TON | 8 | $150.00 | $150.00 | $703.43 | $150.00 |
| 0053 | PCCP for approaches, 9 in. (610-09108) | SYS | 12 | $200.00 | $300.00 | $406.94 | $300.00 |
| 0054 | Right-of-way marker (615-06490) | EACH | 13 | $178.00 | $178.00 | $178.00 | $178.00 |
| 0055 | Monument, type B (615-06505) | EACH | 2 | $1,035.00 | $185.00 | $1,035.00 | $1,035.00 |
| 0056 | Casting adjust to grade, monument (615-06525) | EACH | 1 | $1,142.00 | $1,075.00 | $1,142.00 | $1,142.00 |
| 0057 | Riprap, revetment (616-06405) | TON | 345 | $75.00 | $110.00 | $125.00 | $170.00 |
| 0058 | Geotextile for riprap, type 1A (616-12246) | SYS | 345 | $4.50 | $6.00 | $5.00 | $6.00 |
| 0059 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $525.00 | $525.00 | $525.00 | $525.00 |
| 0060 | Mulched seeding, type R (621-06559) | SYS | 987 | $2.70 | $3.00 | $2.70 | $2.70 |
| 0061 | Mulched seeding, type U (621-06560) | SYS | 53 | $17.90 | $18.00 | $17.90 | $17.90 |
| 0062 | Sodding (621-06574) | SYS | 18 | $92.00 | $92.00 | $92.00 | $92.00 |
| 0063 | Field office, type D (628-12683) | MOS | 12 | $6,850.00 | $4,500.00 | $4,000.00 | $3,400.00 |
| 0064 | Grates, basins, and fittings, cast iron , modified (702-12076) | EACH | 1 | $3,650.00 | $4,500.00 | $15,000 | $6,500.00 |
| 0065 | Field drilled hole in concrete (702-51863) | EACH | 462 | $12.50 | $30.00 | $15.00 | $30.00 |
| 0066 | Reinforcing bars, epoxy coated (703-06029) | LBS | 21,640 | $2.40 | $2.00 | $1.60 | $1.70 |
| 0067 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 44 | $53.75 | $80.00 | $15.00 | $58.00 |
| 0068 | Concrete, C, superstructure (704-51002) | CYS | 7.90 | $1,100.00 | $4,000.00 | $2,500.00 | $4,000.00 |
| 0069 | Railing, concrete type FC , modified (706-11600) | CYS | 1.90 | $2,200.00 | $3,900.00 | $2,250.00 | $5,500.00 |
| 0070 | Concrete bridge railing transition, type TFC , modified (706-11620) | EACH | 3 | $2,700.00 | $4,500.00 | $3,500.00 | $3,500.00 |
| 0071 | Fiber wrap concrete casing system , bridge no. 1 (709-04647) | LS | 1 | $116,000 | $116,000 | $152,074 | $116,000 |
| 0072 | Fiber wrap concrete casing system , bridge no. 2 (709-04647) | LS | 1 | $28,500 | $28,500 | $38,619 | $28,500 |
| 0073 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $4,000.00 | $2,250.00 | $5,272.25 | $4,000.00 |
| 0074 | Surface seal , bridge no. 1 decorative stain (709-51821) | LS | 1 | $2,000.00 | $3,200.00 | $3,950.31 | $2,000.00 |
| 0075 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $1,500.00 | $2,250.00 | $2,057.07 | $1,500.00 |
| 0076 | Surface seal , bridge no. 3 (709-51821) | LS | 1 | $1,500.00 | $2,250.00 | $1,540.06 | $1,500.00 |
| 0077 | Patching concrete structures (710-09158) | SFT | 1,620 | $175.00 | $175.00 | $100.00 | $175.00 |
| 0078 | Casting, inlet, adjust to grade (720-12797) | EACH | 4 | $200.00 | $750.00 | $3,000.00 | $1,500.00 |
| 0079 | Casting, manhole, adjust to grade (720-12798) | EACH | 1 | $200.00 | $750.00 | $3,000.00 | $1,500.00 |
| 0080 | Bridge deck overlay, rigid (722-000134) | SYS | 2,004 | $80.00 | $180.00 | $130.00 | $120.00 |
| 0081 | Hydrodemolition (722-01066) | SYS | 1,984 | $71.75 | $110.00 | $100.00 | $110.00 |
| 0082 | Bridge deck overlay budget (722-12380) | DOL | 41,100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0083 | Bridge deck, remove concrete surface (722-12464) | SYS | 2,004 | $8.75 | $10.00 | $10.00 | $13.00 |
| 0084 | Longitudinal grooving (722-12732) | SYS | 2,330 | $6.90 | $5.00 | $5.00 | $8.00 |
| 0085 | Bridge deck patching, full depth (722-51401) | SFT | 338 | $60.50 | $55.00 | $20.00 | $15.00 |
| 0086 | Bridge deck patching, partial depth (722-51852) | SFT | 158 | $2.50 | $5.00 | $15.00 | $2.50 |
| 0087 | Overlay dam (722-51874) | SFT | 197 | $67.00 | $50.00 | $90.00 | $100.00 |
| 0088 | Bridge expansion joint seal, type PCF, replace (724-12779) | LFT | 1,226 | $71.40 | $56.00 | $20.00 | $90.00 |
| 0089 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 32 | $10.00 | $10.00 | $100.00 | $10.00 |
| 0090 | Epoxy injection, crack preparation (727-90308) | LFT | 975 | $25.00 | $25.00 | $30.88 | $25.00 |
| 0091 | Epoxy injection, furnishing equipment , bridge no. 1 (727-93560) | LS | 1 | $100.00 | $100.00 | $5,000.00 | $100.00 |
| 0092 | Epoxy injection, furnishing equipment , bridge no. 2 (727-93560) | LS | 1 | $100.00 | $100.00 | $5,000.00 | $100.00 |
| 0093 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 352 | $57.50 | $57.50 | $55.29 | $57.50 |
| 0094 | Polymer overlay, other concrete surface (738-12856) | SYS | 279 | $57.50 | $57.50 | $43.54 | $57.50 |
| 0095 | Bridge deck, remove existing polymer overlay system (738-12917) | SYS | 631 | $7.50 | $17.50 | $13.75 | $17.50 |
| 0096 | Road closure sign assembly (801-04308) | EACH | 29 | $175.00 | $244.00 | $250.00 | $175.00 |
| 0097 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 5,882 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0098 | Temporary pavement message marking, removable, lane indication arrow (801-06211) | EACH | 8 | $150.00 | $211.00 | $250.00 | $150.00 |
| 0099 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $10.00 | $10.50 | $18.00 | $10.00 |
| 0100 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 1,808 | $3.00 | $3.00 | $3.25 | $3.00 |
| 0101 | Detour route marker assembly (801-06625) | EACH | 70 | $75.00 | $139.00 | $250.00 | $75.00 |
| 0102 | Construction sign, type A (801-06640) | EACH | 66 | $175.00 | $176.00 | $225.00 | $175.00 |
| 0103 | Construction sign, type B (801-06645) | EACH | 12 | $75.00 | $101.00 | $150.00 | $75.00 |
| 0104 | Maintaining traffic (801-06775) | LS | 1 | $261,220 | $82,500 | $150,000 | $35,000 |
| 0105 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $7,074.00 | $6,200.00 | $3,500.00 | $7,074.00 |
| 0106 | Barricade, type III-A (801-07118) | LFT | 138 | $12.00 | $15.00 | $15.00 | $12.00 |
| 0107 | Barricade, type III-B (801-07119) | LFT | 764 | $12.00 | $15.00 | $15.00 | $12.00 |
| 0108 | Temporary traffic barrier, type 2 (801-08401) | LFT | 500 | $45.50 | $23.00 | $15.00 | $55.00 |
| 0109 | Temporary pavement marking, removable, 25 in. (801-12389) | LFT | 50 | $25.00 | $15.00 | $18.00 | $25.00 |
| 0110 | Temporary pedestrian channelizer (801-12862) | LFT | 48 | $20.00 | $35.00 | $20.00 | $20.00 |
| 0111 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 4 | $350.00 | $894.00 | $400.00 | $350.00 |
| 0112 | Signal head relocate (801-94295) | EACH | 12 | $500.00 | $500.00 | $950.00 | $500.00 |
| 0113 | Pavement message marking, remove (808-05866) | SYS | 18 | $50.00 | $59.00 | $100.00 | $50.00 |
| 0114 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 258 | $1.00 | $1.50 | $1.00 | $1.00 |
| 0115 | Line, remove (808-06716) | LFT | 339 | $1.00 | $1.58 | $5.00 | $1.00 |
| 0116 | Line, multi-component, broken, yellow, 4 in. (808-10036) | LFT | 50 | $3.00 | $3.00 | $5.00 | $3.00 |
| 0117 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 65 | $3.00 | $1.20 | $4.00 | $3.00 |
| 0118 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 994 | $3.00 | $1.20 | $4.00 | $3.00 |
| 0119 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 296 | $3.00 | $3.00 | $4.00 | $3.00 |
| 0120 | Grooving for pavement markings (808-12032) | LFT | 597 | $2.00 | $5.50 | $4.00 | $2.00 |
| 0121 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 88 | $1.00 | $1.20 | $1.00 | $1.00 |
| 0122 | Line, thermoplastic, solid, yellow, 10 in. (808-12858) | LFT | 145 | $10.00 | $3.60 | $6.00 | $10.00 |
| 0123 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 704 | $1.00 | $1.20 | $1.00 | $1.00 |
| 0124 | Pavement message marking, preformed plastic, lane indication arrow (808-75071) | EACH | 8 | $350.00 | $691.00 | $400.00 | $350.00 |
| 0125 | Transverse marking, thermoplastic, crosshatch line, yellow, 24 in. (808-75290) | LFT | 22 | $20.00 | $14.00 | $20.00 | $20.00 |
| 0126 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 5 | $30.00 | $126.00 | $5.00 | $120.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.