INDOT contract B-44260-A bid tabulation
BRIDGE DECK OVERLAY AND REHABILITATION OR REPAIR. Let by Indiana DOT on November 5, 2026, Montgomery, Crawfordsville. 5 bids received; low bid $1,668,000 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 05 NOV 2026
- Pay items
- 72
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $1,668,000 | Low |
| 2 | Milestone Contractors LP | $1,859,950 | +12% |
| 3 | Icc Group Inc | $1,951,000 | +17% |
| 4 | Rieth-Riley Construction Co., Inc. | $2,025,425 | +21% |
| 5 | Force Construction Co Inc | $2,237,930 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Milestone Contractors LP | 3. Icc Group Inc | 4. Rieth-Riley Construction Co., Inc. | 5. Force Construction Co Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,000 | $19,500 | $14,000 | $14,000 | $19,660 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $83,439 | $40,000 | $97,550 | $101,271 | $110,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $49,278 | $30,000 | $58,530 | $60,763 | $35,770 |
| 0012 | Pavement removal (202-02240) | SYS | 282 | $50.00 | $50.00 | $80.00 | $60.04 | $30.00 |
| 0013 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $30,000 | $31,000 | $54,612 | $93,203 | $14,210 |
| 0014 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $30,000 | $30,000 | $50,000 | $44,443 | $6,326.00 |
| 0015 | Present structure, remove portions, structure no. 3 (202-51328) | LS | 1 | $30,000 | $31,000 | $58,693 | $86,619 | $14,210 |
| 0016 | Curb turnout, remove (202-94810) | EACH | 3 | $750.00 | $400.00 | $1,500.00 | $865.03 | $991.00 |
| 0017 | Excavation, common (203-02000) | CYS | 261 | $100.00 | $120.00 | $40.00 | $90.21 | $68.00 |
| 0018 | Stormwater management budget (205-12108) | DOL | 6,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $9,000.00 | $5,700.00 | $1.00 | $6,965.29 | $8,153.00 |
| 0020 | Cofferdam , structure no. 1 (206-51235) | LS | 1 | $20,000 | $25,000 | $65,000 | $23,881 | $59,070 |
| 0021 | Cofferdam , structure no. 2 (206-51235) | LS | 1 | $20,000 | $25,000 | $65,000 | $23,881 | $62,850 |
| 0022 | Subgrade treatment, type IC (207-09935) | SYS | 1,112 | $50.00 | $70.50 | $65.00 | $74.59 | $55.00 |
| 0023 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,545 | $5.00 | $4.20 | $6.00 | $3.74 | $4.40 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 72 | $75.00 | $100.00 | $125.00 | $148.15 | $75.00 |
| 0025 | Milling, transition (306-08043) | SYS | 811 | $5.00 | $7.50 | $9.00 | $21.56 | $10.00 |
| 0026 | Lean concrete base, 9 in. (309-12695) | SYS | 433 | $80.00 | $112.00 | $165.00 | $63.00 | $91.00 |
| 0027 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 79 | $355.00 | $380.00 | $370.00 | $370.00 | $381.00 |
| 0028 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 55 | $305.00 | $275.00 | $325.00 | $325.00 | $334.00 |
| 0029 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 61 | $427.00 | $455.00 | $350.00 | $350.00 | $360.00 |
| 0030 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 44 | $362.00 | $300.00 | $295.00 | $295.00 | $304.00 |
| 0031 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 284 | $300.00 | $216.00 | $155.00 | $155.00 | $160.00 |
| 0032 | Joint adhesive (401-11526) | LFT | 1,404 | $1.50 | $2.00 | $1.00 | $1.00 | $1.00 |
| 0033 | Asphalt for tack coat (406-05521) | SYS | 2,390 | $0.25 | $0.20 | $0.20 | $0.20 | $0.20 |
| 0034 | Guardrail, remove (601-02241) | LFT | 956 | $7.50 | $7.50 | $7.50 | $7.50 | $7.70 |
| 0035 | Guardrail transition, MGS without curb (601-12292) | EACH | 12 | $3,275.00 | $3,275.00 | $3,275.00 | $3,275.00 | $3,371.00 |
| 0036 | Guardrail end treatment, type OS (601-94689) | EACH | 12 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,088.00 |
| 0037 | Barrier delineator (602-06729) | EACH | 22 | $20.00 | $25.00 | $24.00 | $34.03 | $33.00 |
| 0038 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 433 | $225.00 | $247.00 | $180.00 | $188.50 | $224.00 |
| 0039 | Right-of-way marker (615-06490) | EACH | 8 | $175.00 | $175.00 | $175.00 | $175.00 | $180.00 |
| 0040 | Riprap, class 1 (616-05688) | TON | 289 | $120.00 | $150.00 | $136.00 | $234.21 | $126.00 |
| 0041 | Riprap, revetment (616-06405) | TON | 674 | $110.00 | $119.00 | $103.00 | $127.38 | $85.00 |
| 0042 | Geotextile for riprap, type 2A (616-12248) | SYS | 1,260 | $5.00 | $2.50 | $5.00 | $2.16 | $4.00 |
| 0043 | Mobilization and demobilization for seeding (621-01004) | EACH | 6 | $550.00 | $550.00 | $550.00 | $550.00 | $566.00 |
| 0044 | Erosion control blanket (621-02770) | SYS | 561 | $3.40 | $3.45 | $3.40 | $3.40 | $3.50 |
| 0045 | Mulched seeding, type R (621-06559) | SYS | 561 | $2.30 | $2.35 | $2.30 | $2.30 | $2.40 |
| 0046 | Sodding (621-06574) | SYS | 77 | $47.00 | $47.00 | $47.00 | $47.00 | $48.00 |
| 0047 | Field office, type C (628-09403) | MOS | 15 | $3,000.00 | $4,300.00 | $2,530.70 | $3,856.19 | $2,779.00 |
| 0048 | Computer system equipment (628-11976) | EACH | 1 | $650.00 | $500.00 | $304.45 | $1,134.17 | $823.00 |
| 0049 | Field drilled hole in concrete (702-51863) | EACH | 1,164 | $15.00 | $24.50 | $20.00 | $30.78 | $20.00 |
| 0050 | Reinforcing bars, epoxy coated (703-06029) | LBS | 42,881 | $1.45 | $1.85 | $1.40 | $1.64 | $1.70 |
| 0051 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 12 | $4,000.00 | $5,000.00 | $2,750.00 | $5,268.97 | $5,901.00 |
| 0052 | Railing, concrete type PF-1 , modified (706-09962) | LFT | 713 | $100.00 | $140.00 | $100.00 | $158.06 | $185.00 |
| 0053 | Railing, steel type PF-1 (706-11404) | LFT | 766 | $86.00 | $86.00 | $86.00 | $86.00 | $89.00 |
| 0054 | Surface seal , structure no. 1 (709-51821) | LS | 1 | $4,000.00 | $3,250.00 | $3,052.00 | $3,052.00 | $2,914.00 |
| 0055 | Surface seal , structure no. 2 (709-51821) | LS | 1 | $4,000.00 | $2,950.00 | $3,014.00 | $3,014.00 | $2,894.00 |
| 0056 | Surface seal , structure no. 3 (709-51821) | LS | 1 | $4,000.00 | $2,950.00 | $3,311.00 | $3,311.00 | $3,029.00 |
| 0057 | Patching concrete structures (710-09158) | SFT | 525 | $169.00 | $169.00 | $169.00 | $169.00 | $153.00 |
| 0058 | Pipe, plug existing (720-02442) | EACH | 6 | $650.00 | $250.00 | $3,500.00 | $401.42 | $735.00 |
| 0059 | Bridge deck overlay, rigid (722-000134) | SYS | 1,061 | $105.00 | $190.00 | $125.00 | $116.22 | $175.00 |
| 0060 | Hydrodemolition (722-01066) | SYS | 1,061 | $100.00 | $130.00 | $150.00 | $131.66 | $129.00 |
| 0061 | Bridge deck overlay budget (722-12380) | DOL | 60,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0062 | Bridge deck, remove concrete surface (722-12464) | SYS | 1,061 | $15.00 | $19.00 | $25.00 | $19.06 | $20.00 |
| 0063 | Longitudinal grooving (722-12732) | SYS | 1,608 | $5.00 | $3.40 | $10.00 | $6.74 | $5.30 |
| 0064 | Bridge deck patching, full depth (722-51401) | SFT | 150 | $25.00 | $20.00 | $122.00 | $268.79 | $128.00 |
| 0065 | Road closure sign assembly (801-04308) | EACH | 12 | $210.00 | $210.00 | $169.00 | $210.00 | $216.00 |
| 0066 | Detour route marker assembly (801-06625) | EACH | 34 | $105.00 | $105.00 | $109.00 | $105.00 | $108.00 |
| 0067 | Construction sign, type A (801-06640) | EACH | 19 | $130.00 | $130.00 | $149.00 | $130.00 | $134.00 |
| 0068 | Maintaining traffic (801-06775) | LS | 1 | $9,000.00 | $3,977.55 | $20,000 | $955.00 | $378,000 |
| 0069 | Barricade, type III-A (801-07118) | LFT | 144 | $14.00 | $14.00 | $13.89 | $14.00 | $14.00 |
| 0070 | Barricade, type III-B (801-07119) | LFT | 144 | $14.00 | $14.00 | $13.89 | $14.00 | $14.00 |
| 0071 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 2,049 | $0.45 | $0.45 | $0.95 | $0.45 | $0.45 |
| 0072 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 2,049 | $0.45 | $0.45 | $0.95 | $0.45 | $0.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of November 5, 2026. Compiled by Mirage Metrics.