INDOT contract B-44530-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on October 7, 2026, Allen, Fort Wayne. 4 bids received; low bid $594,477 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 07 OCT 2026
- Pay items
- 52
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $594,477 | Low |
| 2 | E & B Paving LLC | $624,200 | +5.0% |
| 3 | Pioneer Associates Inc | $627,604 | +6.0% |
| 4 | R L McCoy Inc | $642,827 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. E & B Paving LLC | 3. Pioneer Associates Inc | 4. R L McCoy Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $11,850 | $10,000 | $4,500.00 | $8,000.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $29,724 | $32,000 | $38,500 | $32,000 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $16,950 | $10,000 | $12,500 | $6,400.00 |
| 0010 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $33,300 | $50,000 | $34,500 | $76,000 |
| 0011 | Excavation, common (203-02000) | CYS | 4 | $1,525.00 | $735.00 | $150.00 | $1,600.00 |
| 0012 | Subgrade treatment, type IC (207-09935) | SYS | 547 | $45.75 | $45.00 | $55.00 | $45.00 |
| 0013 | Geotextile for pavement, type 2B (214-12239) | SYS | 547 | $6.25 | $5.50 | $5.00 | $5.00 |
| 0014 | Compacted aggregate, no. 53 (301-12234) | CYS | 69 | $86.00 | $95.00 | $105.00 | $95.00 |
| 0015 | Subbase for PCCP (302-06464) | CYS | 50.20 | $159.00 | $150.00 | $165.00 | $140.00 |
| 0016 | Compacted aggregate, no. 53 (303-01180) | TON | 16 | $78.50 | $250.00 | $75.00 | $150.00 |
| 0017 | Milling, transition (306-08043) | SYS | 920 | $5.75 | $6.00 | $3.00 | $5.00 |
| 0018 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 102 | $150.00 | $200.00 | $150.00 | $150.00 |
| 0019 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 43 | $150.00 | $230.00 | $150.00 | $150.00 |
| 0020 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 102 | $150.00 | $170.00 | $150.00 | $150.00 |
| 0021 | Joint adhesive (401-11526) | LFT | 2,700 | $0.30 | $0.40 | $0.30 | $0.30 |
| 0022 | Asphalt for tack coat (406-05521) | SYS | 4,600 | $0.30 | $0.10 | $0.30 | $0.30 |
| 0023 | Terminal joint, type HMA (503-12477) | LFT | 92 | $362.75 | $200.00 | $335.00 | $450.00 |
| 0024 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $3,246.00 | $3,350.00 | $3,246.00 | $3,246.00 |
| 0025 | Guardrail terminal system, W-beam, curved, type 1 (601-01700) | EACH | 1 | $3,121.00 | $2,950.00 | $3,121.00 | $3,121.00 |
| 0026 | Guardrail, remove (601-02241) | LFT | 205 | $14.00 | $25.00 | $14.00 | $14.00 |
| 0027 | Hand dig guardrail post holes (601-09238) | EACH | 5 | $107.00 | $135.00 | $107.00 | $107.00 |
| 0028 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 25 | $38.00 | $36.00 | $38.00 | $38.00 |
| 0029 | Guardrail height transition, MGS (601-12289) | EACH | 3 | $1,231.00 | $1,150.00 | $1,231.00 | $1,231.00 |
| 0030 | Guardrail transition, MGS without curb (601-12292) | EACH | 3 | $3,214.00 | $3,425.00 | $3,214.00 | $3,214.00 |
| 0031 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 238.40 | $162.00 | $200.00 | $210.00 | $225.00 |
| 0032 | Clean drains (619-98427) | EACH | 2 | $298.75 | $100.00 | $250.00 | $1,000.00 |
| 0033 | Field office, type D (628-12683) | MOS | 12 | $5,000.00 | $3,500.00 | $4,400.00 | $3,400.00 |
| 0034 | Reinforcing bars, epoxy coated (703-06029) | LBS | 16,922 | $2.50 | $2.00 | $2.00 | $1.60 |
| 0035 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $3,475.00 | $4,500.00 | $3,500.00 | $3,500.00 |
| 0036 | Surface seal (709-51821) | LS | 1 | $2,575.00 | $8,000.00 | $6,550.00 | $5,000.00 |
| 0037 | Bridge deck overlay, rigid (722-000134) | SYS | 998 | $59.25 | $90.00 | $90.00 | $72.00 |
| 0038 | Hydrodemolition (722-01066) | SYS | 998 | $58.50 | $75.00 | $75.00 | $85.00 |
| 0039 | Bridge deck overlay budget (722-12380) | DOL | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0040 | Longitudinal grooving (722-12732) | SYS | 1,226 | $6.00 | $7.00 | $4.00 | $6.00 |
| 0041 | Bridge deck patching, full depth (722-51401) | SFT | 75 | $43.75 | $50.00 | $55.00 | $15.00 |
| 0042 | Overlay dam (722-51874) | SFT | 92 | $49.25 | $70.00 | $55.00 | $45.00 |
| 0043 | Road closure sign assembly (801-04308) | EACH | 9 | $225.00 | $233.00 | $233.00 | $150.00 |
| 0044 | Detour route marker assembly (801-06625) | EACH | 41 | $150.00 | $142.00 | $142.00 | $75.00 |
| 0045 | Construction sign, type A (801-06640) | EACH | 2 | $200.00 | $194.00 | $194.00 | $150.00 |
| 0046 | Maintaining traffic (801-06775) | LS | 1 | $24,330 | $6,507.39 | $17,350 | $10,000 |
| 0047 | Barricade, type III-A (801-07118) | LFT | 96 | $15.00 | $14.65 | $15.00 | $15.00 |
| 0048 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 922 | $1.50 | $0.89 | $1.00 | $2.00 |
| 0049 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 461 | $1.50 | $0.89 | $1.00 | $2.00 |
| 0050 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 116 | $1.50 | $1.11 | $1.00 | $3.00 |
| 0051 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 8 | $26.75 | $0.01 | $60.00 | $40.00 |
| 0052 | Bridge deck, remove concrete surface (722-12464) | SYS | 998 | $8.50 | $8.00 | $10.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.