INDOT contract R-43748-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on October 7, 2026, Harrison, Seymour. 5 bids received; low bid $1,076,573 by Blankenberger Brothers Inc.
- Owner
- Indiana DOT
- Letting
- 07 OCT 2026
- Pay items
- 65
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blankenberger Brothers Inc | $1,076,573 | Low |
| 2 | Mac Construction & Excavating Inc | $1,097,000 | +2.0% |
| 3 | Milestone Contractors LP | $1,227,977 | +14% |
| 4 | Ragle, Inc. | $1,252,120 | +16% |
| 5 | E & B Paving LLC | $1,333,000 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blankenberger Brothers Inc | 2. Mac Construction & Excavating Inc | 3. Milestone Contractors LP | 4. Ragle, Inc. | 5. E & B Paving LLC |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $19,000 | $15,000 | $15,000 | $11,000 | $30,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $55,000 | $47,235 | $61,250 | $62,000 | $65,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $21,500 | $25,000 | $75,000 | $2,000.00 | $24,000 |
| 0011 | Pavement removal (202-02240) | SYS | 484 | $77.00 | $26.00 | $34.90 | $40.00 | $26.00 |
| 0012 | Excavation, common (203-02000) | CYS | 110 | $93.00 | $100.00 | $210.00 | $180.00 | $265.00 |
| 0013 | Borrow (203-02070) | CYS | 140 | $1.00 | $115.00 | $76.30 | $50.00 | $10.00 |
| 0014 | Pump around (205-11626) | EACH | 1 | $28,000 | $17,500 | $24,500 | $30,000 | $15,000 |
| 0015 | Stormwater management budget (205-12108) | DOL | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $7,500.00 | $20,000 | $3,520.00 | $6,000.00 | $38,500 |
| 0017 | Excavation, X (206-51215) | CYS | 10 | $135.00 | $750.00 | $520.00 | $300.00 | $250.00 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 534 | $30.00 | $47.00 | $69.20 | $45.00 | $75.00 |
| 0019 | Structure backfill, type 2 (211-09265) | CYS | 824 | $82.00 | $70.00 | $63.40 | $40.00 | $62.00 |
| 0020 | Geogrid, type IB (214-11796) | SYS | 534 | $6.00 | $21.00 | $6.80 | $3.50 | $2.00 |
| 0021 | Compacted aggregate, no. 8 (301-12233) | CYS | 85 | $105.00 | $280.00 | $200.00 | $125.00 | $139.00 |
| 0022 | Compacted aggregate, no. 53 (303-01180) | TON | 161 | $78.00 | $60.00 | $73.70 | $45.00 | $115.00 |
| 0023 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 880 | $19.00 | $15.50 | $20.20 | $18.00 | $25.75 |
| 0024 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 118 | $281.00 | $225.00 | $330.00 | $255.00 | $255.00 |
| 0025 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 68 | $512.00 | $450.00 | $350.00 | $465.00 | $465.00 |
| 0026 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 320 | $185.00 | $210.00 | $183.40 | $166.00 | $166.00 |
| 0027 | Joint adhesive (401-11526) | LFT | 1,260 | $0.20 | $0.82 | $3.35 | $0.10 | $0.10 |
| 0028 | Asphalt for tack coat (406-05520) | TON | 1 | $1.00 | $0.01 | $660.00 | $1.00 | $1.00 |
| 0029 | Milled HMA corrugations, conventional (606-12399) | LFT | 620 | $15.00 | $8.85 | $8.85 | $10.00 | $24.00 |
| 0030 | Monument, type C (615-06510) | EACH | 2 | $670.00 | $625.00 | $625.00 | $625.00 | $625.00 |
| 0031 | Riprap, class 2 (616-05689) | TON | 78 | $79.00 | $113.00 | $88.40 | $140.00 | $106.00 |
| 0032 | Riprap, revetment (616-06405) | TON | 12 | $203.00 | $213.00 | $200.00 | $265.00 | $165.00 |
| 0033 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,017 | $7.00 | $4.40 | $7.30 | $3.50 | $4.00 |
| 0034 | Geotextile for riprap, type 2A (616-12248) | SYS | 124 | $11.00 | $9.30 | $10.90 | $9.00 | $6.25 |
| 0035 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $220.00 | $1,100.00 | $1,100.00 | $200.00 | $200.00 |
| 0036 | Erosion control blanket (621-02770) | SYS | 3,250 | $2.00 | $2.35 | $2.35 | $1.75 | $1.75 |
| 0037 | Mulched seeding, type R (621-06559) | SYS | 3,250 | $2.00 | $0.48 | $0.48 | $2.00 | $2.00 |
| 0038 | Cable barrier system, type TL-4, reset (627-11647) | LFT | 155 | $60.00 | $54.00 | $54.00 | $79.00 | $54.00 |
| 0039 | Field office, type C (628-09403) | MOS | 12 | $2,600.00 | $3,000.00 | $4,260.00 | $3,500.00 | $2,550.00 |
| 0040 | Computer system equipment (628-11976) | EACH | 2 | $600.00 | $900.00 | $610.00 | $1,750.00 | $850.00 |
| 0041 | Temporary shoring (702-04325) | LS | 1 | $72,000 | $90,000 | $66,800 | $100,000 | $203,900 |
| 0042 | Waterproofing membrane, type 2 (714-000086) | SFT | 4,725 | $4.00 | $6.65 | $2.50 | $4.00 | $4.50 |
| 0043 | Structure, reinforced concrete, box sections, 5 FT X 5 FT (714-11190) | LFT | 225 | $815.00 | $895.00 | $640.00 | $1,350.00 | $785.00 |
| 0044 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 110 | $28.00 | $75.00 | $82.10 | $25.00 | $30.00 |
| 0045 | Outlet protector, type 2 (718-06529) | EACH | 1 | $2,750.00 | $1,715.00 | $3,210.00 | $3,500.00 | $12,000 |
| 0046 | Geotextile for underdrains, type 1A (718-12305) | SYS | 76 | $10.00 | $16.00 | $11.00 | $9.00 | $4.50 |
| 0047 | Aggregate for underdrains (718-52610) | CYS | 10 | $130.00 | $70.00 | $51.90 | $100.00 | $51.00 |
| 0048 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 19,105 | $2.00 | $1.85 | $1.50 | $1.50 | $1.85 |
| 0049 | Construction sign, type A (801-06640) | EACH | 46 | $215.00 | $175.00 | $195.00 | $195.00 | $175.00 |
| 0050 | Flashing arrow sign (801-06710) | DAY | 180 | $22.00 | $20.00 | $13.00 | $13.00 | $20.00 |
| 0051 | Maintaining traffic (801-06775) | LS | 1 | $60,000 | $30,000 | $95,065 | $74,000 | $101,312 |
| 0052 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $9,650.00 | $8,750.00 | $8,750.01 | $10,600 | $8,750.00 |
| 0053 | Temporary traffic barrier, type 2 (801-08401) | LFT | 2,600 | $31.00 | $26.00 | $56.20 | $60.00 | $33.00 |
| 0054 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 310 | $72.00 | $86.00 | $90.10 | $65.00 | $135.00 |
| 0055 | Portable changeable message sign (801-11642) | EACH | 2 | $3,500.00 | $4,500.00 | $2,920.00 | $2,920.00 | $4,500.00 |
| 0056 | Truck mounted attenuator (801-12042) | DAY | 14 | $325.00 | $750.00 | $1,790.00 | $350.00 | $820.00 |
| 0057 | Law enforcement officer (801-12324) | HRS | 100 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 0058 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 8 | $385.00 | $350.00 | $291.00 | $291.00 | $350.00 |
| 0059 | Grooving for pavement markings (808-12032) | LFT | 930 | $3.00 | $3.00 | $2.00 | $2.00 | $3.00 |
| 0060 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 310 | $3.00 | $3.50 | $1.00 | $1.00 | $3.50 |
| 0061 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 310 | $3.00 | $3.50 | $1.00 | $1.00 | $3.50 |
| 0062 | Prismatic reflector (808-75994) | EACH | 12 | $11.00 | $10.00 | $2.00 | $24.00 | $10.00 |
| 0063 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 12 | $39.00 | $50.00 | $98.30 | $50.00 | $40.00 |
| 0064 | Snowplowable raised pavement marker (808-75998) | EACH | 12 | $110.00 | $100.00 | $517.60 | $517.60 | $517.20 |
| 0065 | Line, thermoplastic, broken, white, 6 in. (808-96075) | LFT | 310 | $3.00 | $3.50 | $2.00 | $2.00 | $3.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.