INDOT contract R-46652-A bid tabulation
HMA OVERLAY, PREVENTIVE MAINTENANCE. Let by Indiana DOT on October 7, 2026, Madison, Greenfield. 3 bids received; low bid $228,457 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 07 OCT 2026
- Pay items
- 33
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $228,457 | Low |
| 2 | Calumet Civil Contractors Inc | $256,000 | +12% |
| 3 | Paul H Rohe Company Inc | $260,734 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Calumet Civil Contractors Inc | 3. Paul H Rohe Company Inc |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $8,500.00 | $8,500.00 | $7,500.00 |
| 0002 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 3 | $1,200.00 | $470.00 | $1,300.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $24,663 | $10,061 | $11,585 |
| 0011 | Pavement removal (202-02240) | SYS | 24 | $85.00 | $37.00 | $90.00 |
| 0013 | Stormwater management budget (205-12108) | DOL | 1,191 | $1.00 | $1.00 | $1.00 |
| 0014 | Stormwater management implementation (205-12616) | LS | 1 | $1,200.00 | $9,400.00 | $2,500.00 |
| 0015 | Subgrade treatment, type II (207-08264) | SYS | 900 | $6.00 | $40.00 | $30.00 |
| 0016 | Structure backfill, type 2 (211-09265) | CYS | 2.20 | $27.00 | $100.00 | $300.00 |
| 0017 | Geogrid, type IB (214-11796) | SYS | 900 | $1.25 | $5.00 | $3.50 |
| 0018 | Compacted aggregate, no. 53 (303-01180) | TON | 97 | $59.00 | $70.00 | $90.00 |
| 0019 | HMA patching, full depth, type B (304-12623) | TON | 243 | $275.00 | $200.00 | $230.00 |
| 0020 | Milling, scarification (306-08042) | SYS | 4,685 | $2.60 | $4.00 | $3.00 |
| 0021 | Milling, transition (306-08043) | SYS | 625 | $3.60 | $11.00 | $4.00 |
| 0022 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 496 | $114.00 | $145.00 | $175.00 |
| 0023 | QC/QA-HMA, 2, 58S, base, 19.0 MM (401-000052) | TON | 6.60 | $155.00 | $450.00 | $280.00 |
| 0024 | HMA wedge and level, type B (402-07451) | TON | 53 | $107.00 | $200.00 | $180.00 |
| 0025 | Asphalt for tack coat (406-05520) | TON | 1.80 | $660.00 | $0.01 | $1,000.00 |
| 0026 | Cracks in asphalt pavement, fill (408-12028) | TON | 0.20 | $7,500.00 | $12,000 | $8,500.00 |
| 0027 | Sewer sanitary lateral reconnect (715-92253) | EACH | 1 | $13,829 | $5,000.00 | $6,460.00 |
| 0028 | Casting, inlet, adjust to grade (720-12797) | EACH | 2 | $3,500.00 | $1,100.00 | $2,640.00 |
| 0029 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 13 | $40.00 | $72.00 | $72.00 |
| 0030 | Sign, sheet, and supports, remove (802-07059) | EACH | 1 | $100.00 | $1,500.00 | $250.00 |
| 0031 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 3.50 | $45.00 | $265.00 | $265.00 |
| 0032 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 1,048 | $4.50 | $2.50 | $2.50 |
| 0033 | Line, paint, solid, blue, 4 in. (808-09314) | LFT | 174 | $6.00 | $6.00 | $6.00 |
| 0034 | Pavement message marking, paint, ADA accessible symbol (808-97222) | EACH | 2 | $200.00 | $350.00 | $350.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.