INDOT contract B-44268-A bid tabulation

BRIDGE REHABILITATION OR REPAIR. Let by Indiana DOT on November 5, 2026, Delaware, Greenfield. 5 bids received; low bid $640,057 by Duncan Robertson Inc.

Owner
Indiana DOT
Letting
05 NOV 2026
Pay items
65
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Duncan Robertson Inc$640,057Low
2Milestone Contractors LP$677,409+6.0%
3E & B Paving LLC$699,750+9.0%
4Pontem Contractors Inc$717,743+12%
5His Constructors Inc$789,644+23%
INDOT contract B-44268-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Duncan Robertson Inc2. Milestone Contractors LP3. E & B Paving LLC4. Pontem Contractors Inc5. His Constructors Inc
0001Construction engineering (105-06845)LS1$10,000$15,000$15,000$20,000$22,046
0002Inspection hole, deeper than 3 FT (107-09358)EACH1$2,500.00$1,500.00$1,500.00$900.00$4,245.03
0003Inspection hole, 3 FT deep or less (107-09367)EACH1$1,000.00$1,300.00$1,500.00$600.00$4,245.03
0004Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00
0005Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00
0007Quality adjustments, temporary traffic control devices and markings (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00
0008Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, pavement traffic markings (109-09377)DOL1$1.00$1.00$1.00$1.00$1.00
0010Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00
0011Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00
0012Mobilization and demobilization (110-01001)LS1$32,500$33,500$44,796$35,750$46,663
0013Clearing right-of-way (201-52370)LS1$6,500.00$6,700.00$7,000.00$7,150.00$49,000
0014Present structure, remove portions, structure no. 1 (202-51328)LS1$150,000$118,274$204,027$158,211$75,000
0015Excavation, common (203-02000)CYS79$75.00$180.00$300.00$250.00$161.77
0016Borrow (203-02070)CYS7$1.00$96.00$15.00$175.00$354.78
0017Pump around (205-11626)EACH1$5,000.00$11,000$1,500.00$35,000$21,186
0018Stormwater management budget (205-12108)DOL13,976$1.00$1.00$1.00$1.00$1.00
0019Stormwater management implementation (205-12616)LS1$12,000$5,500.00$5,000.00$12,500$16,869
0020Excavation, foundation, unclassified (206-51230)CYS14$200.00$115.00$150.00$170.00$257.35
0021Cofferdam , bridge no. 1 (206-51235)LS1$1.00$4,800.00$2,000.00$25,000$11,970
0022Subgrade treatment, type II (207-08264)SYS72$30.00$54.00$25.00$42.00$47.51
0023Subgrade treatment, type IC (207-09935)SYS110$60.00$65.00$100.00$45.00$90.55
0024Structure backfill, type 4 (211-09267)CYS14$300.00$550.00$300.00$250.00$475.19
0025Geotextile for pavement, type 2B (214-12239)SYS110$3.50$19.00$10.00$17.00$26.64
0026Compacted aggregate, no. 53 (303-01180)TON217$45.00$76.00$75.00$52.00$74.89
0027Milling, transition (306-08043)SYS660$10.00$17.00$10.00$10.00$6.41
0028QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON63$176.00$275.00$410.00$170.00$217.66
0029QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON13$357.00$245.00$680.00$345.00$294.14
0030QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON31$220.00$225.00$390.00$212.00$305.90
0031Joint adhesive (401-11526)LFT346$5.50$1.50$0.60$6.00$0.95
0032Asphalt for tack coat (406-05521)SYS918$1.90$0.50$0.01$2.00$0.59
0033Guardrail, remove (601-02241)LFT259$6.60$6.50$6.00$6.50$7.06
0034Guardrail transition, type TTT , modified (601-08186)EACH1$4,180.00$4,000.00$3,800.00$4,028.00$4,470.90
0035Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT13$57.00$55.00$52.00$56.00$61.18
0036Guardrail transition, MGS without curb (601-12292)EACH2$4,565.00$4,360.00$4,150.00$4,399.00$4,882.69
0037Guardrail end treatment, type OS (601-94689)EACH2$3,550.00$3,385.00$3,225.00$3,419.00$3,794.38
0038Barrier delineator (602-06729)EACH4$30.00$40.00$20.00$150.00$39.22
0039HMA for approaches, type B (610-07487)TON16$220.00$340.00$250.00$212.00$217.66
0040Mailbox assembly, single (611-06497)EACH1$350.00$340.00$325.00$345.00$382.38
0041Right-of-way marker (615-06490)EACH10$280.00$265.00$255.00$271.00$300.02
0042Monument, type B (615-06505)EACH2$1,350.00$1,290.00$1,230.00$1,304.00$1,447.16
0043Riprap, revetment (616-06405)TON260$55.00$81.00$100.00$85.00$93.50
0044Geotextile for riprap, type 1A (616-12246)SYS350$3.00$4.00$3.00$5.00$8.38
0045Mobilization and demobilization for seeding (621-01004)EACH1$1,650.00$1,550.00$1,500.00$1,590.00$764.76
0046Mulched seeding, type R (621-06559)SYS1,000$2.30$2.25$2.10$3.00$3.62
0047Field office, type A (628-09401)MOS6$2,500.00$3,900.00$2,500.00$3,275.00$3,235.52
0048Reinforcing bars, epoxy coated (703-06029)LBS27,552$2.00$2.00$1.75$1.50$2.24
0049Embedded galvanic anode (703-08247)EACH64$35.00$40.00$35.00$38.00$85.47
0050Concrete, C, superstructure (704-51002)CYS73.50$2,000.00$1,950.00$1,500.00$1,650.00$2,505.55
0051Concrete bridge railing transition, type TPF-1 (706-06351)EACH4$2,250.00$7,500.00$2,000.00$5,000.00$5,841.06
0052Railing, concrete type PF-1 (706-09962)LFT60$200.00$275.00$200.00$212.00$203.76
0053Railing, steel type PF-1 (706-11404)LFT77$105.00$155.00$96.00$102.00$120.20
0054Surface seal , bridge no. 1 (709-51821)LS1$1,000.00$2,500.00$1.00$2,193.00$1,764.82
0055Patching concrete structures (710-09158)SFT200$60.00$45.00$40.00$43.00$154.66
0056Road closure sign assembly (801-04308)EACH5$192.00$221.00$412.62$224.00$382.38
0057Detour route marker assembly (801-06625)EACH27$82.50$130.00$125.31$132.00$158.83
0058Construction sign, type A (801-06640)EACH13$165.00$177.00$233.69$180.00$229.43
0059Construction sign, type B (801-06645)EACH2$55.00$106.00$132.52$110.00$141.19
0060Maintaining traffic (801-06775)LS1$20,000$7,500.00$5,000.00$20,000$6,428.17
0061Barricade, type III-A (801-07118)LFT48$16.50$15.00$11.26$16.00$20.00
0062Barricade, type III-B (801-07119)LFT48$16.50$15.00$11.26$16.00$20.00
0063Sign, sheet, remove (802-04089)EACH4$50.00$104.00$100.00$106.00$117.66
0064Line, paint, solid, white, 6 in. (808-75007)LFT740$1.10$1.50$1.63$2.00$1.12
0065Line, paint, solid, yellow, 6 in. (808-75047)LFT740$1.10$1.50$1.63$2.00$1.12
INDOT contract B-44268-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of November 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy