His Constructors Inc: INDOT bid record

His Constructors Inc submitted 102 bids on Indiana DOT contracts in the data, from 12 JAN 2022 to 05 NOV 2026, and was the low bidder on 22 of them (22%). When it was not low, its total sat a median +14% above the low bid.

Owner
Indiana DOT
Low bid volume
$63,202,634
Latest bid
05 NOV 2026
Data through
05 NOV 2026
102Bids
22Low bids
22Win rate, percent
+14%Median gap to the low bid when not low, 80 bids

By year

YearBidsLow bidsWin rate
202215320%
202314536%
20242329%
202533618%
202617635%
His Constructors Inc, INDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
Greenfield391333%
Crawfordsville26312%
Seymour20210%
Fort Wayne10440%
LaPorte500%
Vincennes200%
His Constructors Inc, INDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Liquidated damages109-08359DOL101101 (100%)$1.00$1.00
Contract liens109-08360DOL101101 (100%)$1.00$1.00
Quality adjustments, failed materials109-08444DOL100100 (100%)$1.00$1.00
Quality adjustments, temporary traffic control devices109-08443DOL9696 (100%)$1.00$1.00
Stormwater management budget205-12108DOL9292 (100%)$1.00$1.00
Quality adjustments, failure to maintain temporary erosion and sediment control measures109-11362DOL9191 (100%)$1.00$1.00
Quality adjustments, HMA109-08440DOL9090 (100%)$1.00$1.00
Payment adjustment, PG asphalt binder109-09489DOL7373 (100%)$1.00$1.00
Excavation, common203-02000CYS8333 (40%)$46.70$63.00
Project estimate adjustment109-08463DOL3232 (100%)$1.00$1.00
Subgrade treatment, type IC207-09935SYS6323 (37%)$40.25$45.00
Compacted aggregate, no. 53303-01180TON6622 (33%)$50.50$62.00
His Constructors Inc, INDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

His Constructors Inc, INDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
05 NOV 2026B-44268-AGreenfieldBRIDGE REHABILITATION OR REPAIR5 of 5$789,644+23%
08 JUL 2026T-41617-ACrawfordsvilleTRAFFIC SIGNALS MODERNIZATION2 of 2$391,570+7.0%
08 JUL 2026T-45932-ASeymourTRAFFIC SIGNALS3 of 4$343,065+8.0%
08 JUL 2026T-46006-AGreenfieldLIGHTING AND SIGN INSTALLATION1 of 8$387,176Low, 1.0% under the second
08 JUL 2026TM-46080-AGreenfieldTRAFFIC SIGNAL MAINTENANCE1 of 3$272,092Low, 29% under the second
07 MAY 2026T-46034-BLaPorteSIGNING5 of 6$1,679,932+51%
08 APR 2026R-42521-ACrawfordsvilleROAD REHABILITATION AND BRIDGE REHABILITATION4 of 4$6,658,869+20%
08 APR 2026R-43683-ACrawfordsvilleSMALL STRUCTURE REPLACEMENT2 of 10$758,069+2.0%
08 APR 2026T-43854-AFort WayneTRAFFIC SIGNALS MODERNIZATION AND SAFETY REVISIONS1 of 3$1,183,749Low, 1.0% under the second
08 APR 2026TM-45396-AFort WayneLIGHTING MAINTENANCE1 of 3$569,876Low, 22% under the second
11 MAR 2026B-43949-AGreenfieldBRIDGE REPLACEMENT1 of 6$1,593,977Low, 10% under the second
11 FEB 2026R-41916-ACrawfordsvilleROAD RECONSTRUCTION AND BRIDGE REPLACEMENT1 of 3$13,526,943Low, 31% under the second
11 FEB 2026R-43476-AGreenfieldINTERSECTION IMPROVEMENT, ROUNDABOUT5 of 7$2,242,728+13%
11 FEB 2026R-43599-ACrawfordsvilleINTERSECTION IMPROVEMENT, ROUNDABOUT6 of 7$2,241,014+19%
11 FEB 2026B-44426-ACrawfordsvilleBRIDGE MAINTENANCE AND REPAIR5 of 9$679,380+11%
14 JAN 2026R-42755-AGreenfieldNEW ROAD CONSTRUCTION3 of 10$3,385,689+1.0%
14 JAN 2026B-43516-AGreenfieldSMALL STRUCTURE REPLACEMENT8 of 12$838,936+26%
10 DEC 2025R-43621-AGreenfieldADDED TRAVEL LANES1 of 8$6,628,214Low, 4.0% under the second
10 DEC 2025R-44051-ASeymourSMALL STRUCTURE REPLACEMENT4 of 8$1,630,546+17%
10 DEC 2025B-42319-AGreenfieldREPLACE SUPERSTRUCTURE8 of 9$4,215,258+37%
10 DEC 2025B-42436-ALaPorteBRIDGE REPLACEMENT2 of 7$4,234,197+1.0%
10 DEC 2025B-43819-AFort WayneBRIDGE DECK OVERLAY AND THIN DECK OVERLAY2 of 5$637,030+1.0%
10 DEC 2025B-44247-ACrawfordsvilleBRIDGE REPLACEMENT4 of 7$1,616,855+13%
10 DEC 2025B-44249-ACrawfordsvilleBRIDGE REPLACEMENT5 of 7$1,469,538+20%
10 DEC 2025B-44276-AGreenfieldBRIDGE REPLACEMENT1 of 10$1,496,461Low, 1.0% under the second
His Constructors Inc: latest INDOT bids in the data

How this record was read

INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

  • Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy