INDOT contract B-43949-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on March 11, 2026, Madison, Greenfield. 6 bids received; low bid $1,593,977 by His Constructors Inc.
- Owner
- Indiana DOT
- Letting
- 11 MAR 2026
- Pay items
- 89
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | His Constructors Inc | $1,593,977 | Low |
| 2 | Icc Group Inc | $1,748,000 | +10% |
| 3 | William Charles Construction Company | $1,779,834 | +12% |
| 4 | E & B Paving LLC | $1,819,750 | +14% |
| 5 | Beaty Construction Inc | $1,832,550 | +15% |
| 6 | Milestone Contractors LP | $1,956,200 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. His Constructors Inc | 2. Icc Group Inc | 3. William Charles Construction Company | 4. E & B Paving LLC | 5. Beaty Construction Inc | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $26,000 | $25,000 | $20,000 | $25,000 | $25,992 | $35,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 5 | $679.00 | $800.00 | $2,000.00 | $950.00 | $1,400.00 | $1,100.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $79,699 | $87,000 | $65,850 | $95,000 | $90,500 | $95,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $7,969.88 | $500.00 | $25,600 | $2,000.00 | $9,000.00 | $9,500.00 |
| 0012 | Pavement removal (202-02240) | SYS | 2,316 | $32.00 | $14.00 | $30.00 | $20.00 | $25.00 | $17.00 |
| 0013 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $82,000 | $97,692 | $58,000 | $171,684 | $145,500 | $85,014 |
| 0014 | Pipe, remove (202-96133) | LFT | 125 | $9.00 | $20.00 | $4.00 | $10.00 | $35.00 | $14.00 |
| 0015 | Pipe end section, remove (202-98488) | EACH | 6 | $89.00 | $110.00 | $100.00 | $300.00 | $1.00 | $45.00 |
| 0016 | Excavation, common (203-02000) | CYS | 840 | $35.00 | $24.50 | $40.00 | $120.00 | $25.00 | $70.00 |
| 0017 | Borrow (203-02070) | CYS | 1,330 | $21.00 | $65.00 | $0.01 | $1.00 | $25.00 | $50.00 |
| 0018 | Excavation, waterway (203-51223) | CYS | 890 | $38.00 | $30.00 | $20.00 | $75.00 | $35.00 | $35.00 |
| 0019 | Stormwater management budget (205-12108) | DOL | 19,010 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Stormwater management implementation (205-12616) | LS | 1 | $8,750.00 | $6,600.00 | $11,000 | $20,000 | $4,000.00 | $12,500 |
| 0021 | SWQCP preparation (205-12618) | LS | 1 | $3,250.00 | $3,000.00 | $2,000.00 | $17,500 | $4,000.00 | $3,250.00 |
| 0022 | Excavation, foundation, unclassified (206-51230) | CYS | 95 | $70.00 | $34.00 | $35.00 | $75.00 | $36.00 | $40.00 |
| 0023 | Cofferdam (206-51235) | LS | 1 | $16,000 | $26,000 | $10,000 | $5,000.00 | $90,000 | $15,000 |
| 0024 | Subgrade treatment, type II (207-08264) | SYS | 68 | $36.00 | $25.00 | $60.00 | $40.00 | $30.00 | $40.00 |
| 0025 | Subgrade treatment, type IC (207-09935) | SYS | 3,974 | $25.00 | $35.00 | $35.00 | $40.00 | $28.00 | $35.00 |
| 0026 | Aggregate for end bent backfill (211-06467) | CYS | 46 | $52.00 | $100.00 | $100.00 | $150.00 | $200.00 | $195.00 |
| 0027 | Structure backfill, type 1 (211-09264) | CYS | 20 | $44.00 | $70.00 | $75.00 | $100.00 | $82.00 | $295.00 |
| 0028 | Geotextile for pavement, type 2B (214-12239) | SYS | 4,210 | $5.00 | $4.00 | $4.00 | $3.00 | $4.50 | $6.50 |
| 0029 | Compacted aggregate, no. 53 (301-12234) | CYS | 12 | $95.00 | $100.00 | $180.00 | $300.00 | $320.00 | $95.00 |
| 0030 | Subbase for PCCP (302-06464) | CYS | 60 | $155.00 | $85.00 | $150.00 | $150.00 | $110.00 | $250.00 |
| 0031 | Compacted aggregate, no. 53 (303-01180) | TON | 311 | $38.00 | $60.00 | $55.00 | $50.00 | $62.75 | $75.00 |
| 0032 | Milling, transition (306-08043) | SYS | 268 | $4.00 | $8.50 | $13.00 | $75.00 | $25.00 | $7.00 |
| 0033 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 288 | $130.00 | $130.00 | $152.00 | $152.00 | $130.00 | $190.00 |
| 0034 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 476 | $100.00 | $100.00 | $133.00 | $133.00 | $100.00 | $160.00 |
| 0035 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 1,063 | $95.00 | $95.00 | $109.00 | $109.00 | $95.00 | $150.00 |
| 0036 | Joint adhesive (401-11526) | LFT | 4,878 | $0.20 | $0.20 | $1.00 | $1.00 | $0.20 | $0.60 |
| 0037 | Asphalt for tack coat (406-05521) | SYS | 13,620 | $0.25 | $0.25 | $1.00 | $0.01 | $0.25 | $0.50 |
| 0038 | Guardrail, remove (601-02241) | LFT | 768 | $2.00 | $2.00 | $2.00 | $2.00 | $4.25 | $2.15 |
| 0039 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 100 | $20.00 | $20.00 | $20.00 | $20.00 | $23.00 | $21.00 |
| 0040 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,550.00 | $3,150.00 |
| 0041 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,900.00 | $2,900.00 | $2,900.00 | $2,900.00 | $2,425.00 | $3,045.00 |
| 0042 | Barrier delineator (602-06729) | EACH | 8 | $14.06 | $28.00 | $75.00 | $5.00 | $28.00 | $30.00 |
| 0043 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 236 | $225.00 | $195.00 | $200.00 | $160.00 | $190.00 | $189.00 |
| 0044 | HMA for approaches, type B (610-07487) | TON | 15 | $200.00 | $200.00 | $500.00 | $500.00 | $200.00 | $325.00 |
| 0045 | Right-of-way marker (615-06490) | EACH | 10 | $120.00 | $120.00 | $120.00 | $120.00 | $205.00 | $125.00 |
| 0046 | Monument, type B (615-06505) | EACH | 3 | $962.00 | $962.00 | $962.00 | $962.00 | $1,400.00 | $1,010.00 |
| 0047 | Riprap, revetment (616-06405) | TON | 1,440 | $39.00 | $60.00 | $80.00 | $50.00 | $70.00 | $55.00 |
| 0048 | Geotextile for riprap, type 2A (616-12248) | SYS | 1,910 | $4.00 | $3.50 | $2.00 | $3.00 | $5.00 | $4.50 |
| 0049 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $500.00 | $1,500.00 | $1,500.00 | $800.00 | $500.00 | $525.00 |
| 0050 | Mulched seeding, type R (621-06559) | SYS | 2,950 | $1.15 | $1.00 | $1.00 | $1.00 | $1.10 | $1.25 |
| 0051 | Water (621-06567) | KGAL | 1 | $1.00 | $0.10 | $0.10 | $0.02 | $1.00 | $1.00 |
| 0052 | Sodding (621-06574) | SYS | 34 | $50.00 | $120.00 | $120.00 | $70.00 | $50.00 | $53.00 |
| 0053 | Field office, type C (628-09403) | MOS | 12 | $1,500.00 | $1,850.00 | $2,500.00 | $3,000.00 | $2,750.00 | $4,300.00 |
| 0054 | Topsoil processing and distribution (629-000149) | SYS | 2,950 | $3.00 | $5.00 | $7.00 | $1.75 | $3.75 | $9.00 |
| 0055 | Topsoil amendment budget (629-000150) | DOL | 5,900 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0056 | Test pile, indicator, production (701-09558) | LFT | 120 | $136.00 | $175.00 | $140.00 | $100.00 | $114.00 | $56.00 |
| 0057 | Test pile, indicator, restrike (701-09560) | EACH | 2 | $750.00 | $1,300.00 | $1,240.00 | $2,500.00 | $1,650.00 | $2,600.00 |
| 0058 | Pile shoe, HP 12 X 53 (701-09739) | EACH | 14 | $250.00 | $300.00 | $500.00 | $300.00 | $175.00 | $175.00 |
| 0059 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 600 | $81.00 | $75.00 | $120.00 | $95.00 | $114.00 | $124.00 |
| 0060 | Concrete, C, substructure (702-92857) | CYS | 47 | $950.00 | $1,050.00 | $1,080.00 | $1,000.00 | $1,150.00 | $1,500.00 |
| 0061 | Reinforcing bars, epoxy coated (703-06029) | LBS | 57,856 | $1.75 | $1.60 | $1.50 | $1.25 | $1.45 | $1.75 |
| 0062 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 46 | $50.00 | $50.00 | $70.00 | $20.00 | $45.00 | $42.00 |
| 0063 | Concrete, C, superstructure (704-51002) | CYS | 118.70 | $1,250.00 | $875.00 | $1,550.00 | $750.00 | $1,265.00 | $1,250.00 |
| 0064 | Railing, concrete type FC (706-11600) | CYS | 13.40 | $1,500.00 | $1,375.00 | $1,200.00 | $1,375.00 | $1,060.00 | $1,500.00 |
| 0065 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $3,000.00 | $1,350.00 | $2,500.00 | $1,350.00 | $2,000.00 | $3,500.00 |
| 0066 | Structural member, concrete, bulb-T beam, 36 in. X 49 in. (707-09865) | LFT | 278 | $750.00 | $1,100.00 | $775.00 | $700.00 | $725.00 | $700.00 |
| 0067 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $1,500.00 | $0.01 | $2,500.00 | $1.00 | $1.00 | $100.00 |
| 0068 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 52 | $40.00 | $55.00 | $90.00 | $60.00 | $130.00 | $78.00 |
| 0069 | Pipe, type 3, circular, diameter 18 in. (715-05171) | LFT | 110 | $42.00 | $60.00 | $60.00 | $70.00 | $135.00 | $89.00 |
| 0070 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 100 | $14.00 | $15.00 | $15.00 | $20.00 | $12.00 | $24.00 |
| 0071 | Pipe end section, diameter 15 in. (715-46005) | EACH | 2 | $498.00 | $350.00 | $830.00 | $1,200.00 | $1,350.00 | $566.00 |
| 0072 | Pipe end section, diameter 18 in. (715-46010) | EACH | 4 | $538.00 | $400.00 | $930.00 | $1,200.00 | $1,400.00 | $616.00 |
| 0073 | Geotextile for underdrains, type 1A (718-12305) | SYS | 104 | $9.00 | $4.00 | $6.00 | $3.00 | $7.75 | $7.00 |
| 0074 | Longitudinal grooving (722-12732) | SYS | 531 | $6.00 | $15.00 | $5.00 | $3.00 | $7.75 | $5.50 |
| 0075 | Road closure sign assembly (801-04308) | EACH | 6 | $258.00 | $258.00 | $258.00 | $500.00 | $260.00 | $271.00 |
| 0076 | Detour route marker assembly (801-06625) | EACH | 24 | $153.00 | $153.00 | $153.00 | $200.00 | $155.00 | $161.00 |
| 0077 | Construction sign, type A (801-06640) | EACH | 14 | $207.00 | $207.00 | $207.00 | $275.00 | $210.00 | $218.00 |
| 0078 | Maintaining traffic (801-06775) | LS | 1 | $2,147.57 | $10,000 | $15,000 | $5,000.00 | $10,000 | $5,000.00 |
| 0079 | Barricade, type III-A (801-07118) | LFT | 48 | $15.58 | $15.58 | $16.00 | $20.00 | $16.00 | $17.00 |
| 0080 | Barricade, type III-B (801-07119) | LFT | 48 | $15.58 | $15.58 | $16.00 | $20.00 | $16.00 | $17.00 |
| 0081 | Sign, sheet, remove (802-04089) | EACH | 6 | $90.00 | $90.00 | $90.00 | $90.00 | $61.00 | $95.00 |
| 0082 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 12 | $65.00 | $65.00 | $65.00 | $65.00 | $32.00 | $100.00 |
| 0083 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $100.00 | $100.00 | $100.00 | $100.00 | $316.00 | $105.00 |
| 0084 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 2,000 | $0.81 | $0.81 | $1.00 | $2.65 | $0.85 | $1.00 |
| 0085 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 780 | $0.81 | $0.81 | $1.00 | $2.65 | $0.85 | $1.00 |
| 0086 | Grooving for pavement markings (808-12032) | LFT | 2,667 | $0.88 | $0.88 | $1.00 | $2.85 | $0.90 | $1.00 |
| 0087 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 250 | $1.07 | $1.07 | $1.00 | $2.65 | $1.10 | $1.10 |
| 0088 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 18 | $36.71 | $9.69 | $35.00 | $1.00 | $37.00 | $39.00 |
| 0089 | Snowplowable raised pavement marker (808-75998) | EACH | 8 | $265.00 | $265.00 | $265.00 | $500.00 | $265.00 | $280.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of March 11, 2026. Compiled by Mirage Metrics.