INDOT contract R-42755-A bid tabulation
NEW ROAD CONSTRUCTION. Let by Indiana DOT on January 14, 2026, Hancock, Greenfield. 10 bids received; low bid $3,368,000 by Calumet Civil Contractors Inc.
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 111
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Calumet Civil Contractors Inc | $3,368,000 | Low |
| 2 | E & B Paving LLC | $3,369,026 | 0.0% |
| 3 | His Constructors Inc | $3,385,689 | +1.0% |
| 4 | Rieth-Riley Construction Co., Inc. | $3,579,959 | +6.0% |
| 5 | 3D Company Inc | $3,712,023 | +10% |
| 6 | Gradex Inc | $3,794,672 | +13% |
| 7 | Milestone Contractors LP | $3,878,555 | +15% |
| 8 | Morphey Construction Inc. | $3,979,000 | +18% |
| 9 | Millennium Contractors LLC | $4,167,235 | +24% |
| 10 | William Charles Construction Company | $4,233,404 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Calumet Civil Contractors Inc | 2. E & B Paving LLC | 3. His Constructors Inc | 4. Rieth-Riley Construction Co., Inc. | 5. 3D Company Inc | 6. Gradex Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $38,000 | $56,573 | $72,000 | $31,500 | $81,192 | $294,315 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $146,204 | $158,342 | $152,000 | $66,432 | $267,962 | $189,734 |
| 0012 | Scalping (201-01025) | ACRE | 3 | $8,003.07 | $2,715.00 | $21,000 | $6,793.15 | $9,700.00 | $6,732.24 |
| 0013 | Clearing right-of-way (201-52370) | LS | 1 | $20,200 | $50,800 | $36,000 | $29,587 | $75,690 | $151,787 |
| 0014 | Pavement removal (202-02240) | SYS | 33 | $25.00 | $24.50 | $43.00 | $37.02 | $52.18 | $99.12 |
| 0015 | Curb, concrete, remove (202-02278) | LFT | 588 | $14.00 | $16.50 | $10.00 | $15.87 | $11.93 | $11.65 |
| 0016 | Inlet, remove (202-91385) | EACH | 3 | $500.00 | $410.00 | $930.00 | $566.13 | $1,355.00 | $530.10 |
| 0017 | Pipe, remove (202-96133) | LFT | 457 | $18.00 | $14.80 | $27.00 | $32.81 | $27.20 | $19.34 |
| 0018 | Fence, farm field, remove (202-99187) | LFT | 556 | $6.00 | $6.00 | $6.50 | $6.48 | $6.00 | $8.65 |
| 0019 | Excavation, common (203-02000) | CYS | 24,845 | $22.00 | $28.70 | $19.00 | $32.11 | $29.95 | $24.36 |
| 0020 | Stormwater management budget (205-12108) | DOL | 18,920 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0021 | Stormwater management implementation (205-12616) | LS | 1 | $27,500 | $25,954 | $42,000 | $5,327.78 | $36,735 | $72,747 |
| 0022 | SWQCP preparation (205-12618) | LS | 1 | $2,500.00 | $2,500.00 | $1,500.00 | $49,210 | $3,273.00 | $5,000.00 |
| 0023 | Subgrade treatment, type II (207-08264) | SYS | 116 | $23.50 | $35.00 | $34.00 | $25.75 | $25.75 | $27.91 |
| 0024 | Subgrade treatment, type ibc (207-12635) | SYS | 21,982 | $12.50 | $11.30 | $13.50 | $11.13 | $12.00 | $12.85 |
| 0025 | Structure backfill, type 1 (211-09264) | CYS | 401 | $60.00 | $80.50 | $99.00 | $52.43 | $85.52 | $46.43 |
| 0026 | Drying soils for embankment (217-11917) | TON | 199 | $262.25 | $262.25 | $320.00 | $262.25 | $313.35 | $297.34 |
| 0027 | Compacted aggregate, no. 53 (301-12234) | CYS | 132 | $130.00 | $90.00 | $97.00 | $87.94 | $96.94 | $38.35 |
| 0028 | Dense graded subbase (302-07455) | CYS | 8 | $150.00 | $97.00 | $134.00 | $120.35 | $122.50 | $38.28 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 2,104 | $45.00 | $32.00 | $42.00 | $42.83 | $39.77 | $39.31 |
| 0030 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 2,426 | $95.00 | $85.00 | $91.00 | $99.99 | $93.50 | $85.34 |
| 0031 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 5,559 | $92.00 | $80.00 | $86.00 | $95.61 | $88.00 | $80.32 |
| 0032 | Joint adhesive (401-11526) | LFT | 9,712 | $0.45 | $0.24 | $0.30 | $0.54 | $0.27 | $0.24 |
| 0033 | Asphalt for tack coat (406-05520) | TON | 18 | $0.01 | $0.01 | $0.05 | $0.01 | $0.02 | $0.01 |
| 0034 | QC/QA-HMA, 4, 58E, surface, 9.5 MM - SMA (410-000073) | TON | 1,945 | $165.00 | $140.00 | $150.00 | $151.66 | $154.00 | $140.57 |
| 0035 | Void reducing asphalt membrane for SMA (410-12466) | LFT | 9,712 | $3.30 | $2.60 | $3.50 | $3.30 | $3.81 | $3.30 |
| 0036 | PCCP, 7 in. (502-11564) | SYS | 926 | $113.00 | $83.00 | $89.00 | $95.01 | $91.30 | $83.34 |
| 0037 | D-1 contraction joint (503-05240) | LFT | 838 | $18.00 | $10.00 | $11.00 | $14.81 | $11.00 | $10.04 |
| 0038 | Guardrail terminal system, W-beam, curved, type 6 (601-01839) | EACH | 1 | $3,050.00 | $3,050.00 | $3,270.00 | $2,878.00 | $3,355.00 | $2,510.00 |
| 0039 | Guardrail terminal system, W-beam, curved, type 9 (601-05586) | EACH | 2 | $3,250.00 | $3,250.00 | $3,485.00 | $3,079.00 | $3,575.00 | $3,000.00 |
| 0040 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,744 | $22.00 | $22.00 | $24.00 | $20.00 | $24.20 | $20.00 |
| 0041 | Guardrail height transition, MGS (601-12289) | EACH | 3 | $950.00 | $950.00 | $1,020.00 | $950.00 | $1,045.00 | $975.00 |
| 0042 | Guardrail, MGS W-beam, cable terminal anchor (601-12294) | EACH | 3 | $1,050.00 | $1,050.00 | $1,125.00 | $975.00 | $1,155.00 | $1,200.00 |
| 0043 | Curb, integral concrete (605-06090) | LFT | 63 | $36.00 | $59.00 | $63.00 | $60.84 | $64.90 | $59.24 |
| 0044 | Curb, integral concrete, type B (605-06095) | LFT | 879 | $36.00 | $44.00 | $47.00 | $33.63 | $48.40 | $44.18 |
| 0045 | Curb, integral concrete, type B , modified (605-06095) | LFT | 233 | $36.00 | $30.00 | $43.00 | $29.13 | $44.00 | $40.16 |
| 0046 | Curb, concrete , modified (605-06120) | LFT | 80 | $36.00 | $27.00 | $29.00 | $37.82 | $29.70 | $27.11 |
| 0047 | Curb and gutter, concrete , modified (605-06140) | LFT | 1,292 | $26.00 | $28.00 | $30.00 | $31.20 | $30.80 | $28.11 |
| 0048 | Center curb, concrete, type D (605-06255) | SYS | 17 | $400.00 | $461.00 | $495.00 | $308.70 | $508.00 | $462.87 |
| 0049 | Milled PCCP corrugations, conventional (606-11064) | LFT | 377 | $0.70 | $0.29 | $6.50 | $3.32 | $2.92 | $2.06 |
| 0050 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 5,624 | $0.70 | $0.29 | $1.60 | $3.33 | $0.93 | $2.06 |
| 0051 | PCCP for approaches, 6 in. (610-08446) | SYS | 46 | $78.00 | $70.00 | $77.00 | $91.51 | $79.20 | $72.29 |
| 0052 | Mailbox assembly, reset, single (611-08232) | EACH | 4 | $375.00 | $375.00 | $400.00 | $294.00 | $412.50 | $250.00 |
| 0053 | Right-of-way marker (615-06490) | EACH | 55 | $200.00 | $200.00 | $215.00 | $169.00 | $220.00 | $176.00 |
| 0054 | Monument, type B (615-06505) | EACH | 10 | $850.00 | $850.00 | $910.00 | $971.00 | $935.00 | $1,150.00 |
| 0055 | Monument, type C (615-06510) | EACH | 2 | $400.00 | $400.00 | $430.00 | $897.00 | $440.00 | $750.00 |
| 0056 | Riprap, class 1 (616-05688) | TON | 34 | $80.00 | $85.55 | $173.00 | $92.33 | $124.71 | $156.60 |
| 0057 | Riprap, revetment (616-06405) | TON | 48 | $80.00 | $109.00 | $82.00 | $98.48 | $93.61 | $109.56 |
| 0058 | Geotextile for riprap, type 1A (616-12246) | SYS | 154 | $4.00 | $11.50 | $7.50 | $9.87 | $6.85 | $9.12 |
| 0059 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $500.00 | $500.00 | $535.00 | $500.00 | $690.00 | $500.00 |
| 0060 | Erosion control blanket (621-02770) | SYS | 9,303 | $1.50 | $1.50 | $1.60 | $1.50 | $1.71 | $1.50 |
| 0061 | Seed mixture, type R (621-06553) | LBS | 1,618 | $7.00 | $7.00 | $7.50 | $7.00 | $7.84 | $7.00 |
| 0062 | Mulching material (621-06565) | TON | 16 | $510.00 | $510.00 | $545.00 | $510.00 | $842.35 | $510.00 |
| 0063 | Water (621-06567) | KGAL | 4 | $1.00 | $1.00 | $1.05 | $1.00 | $110.00 | $1.00 |
| 0064 | Sodding (621-06574) | SYS | 783 | $6.50 | $6.50 | $7.00 | $6.50 | $7.28 | $12.11 |
| 0065 | Field office, type A (628-09401) | MOS | 12 | $3,250.00 | $3,150.00 | $3,246.00 | $3,143.77 | $3,465.00 | $3,250.00 |
| 0066 | Topsoil processing and distribution (629-000149) | SYS | 39,454 | $1.75 | $4.15 | $2.00 | $5.72 | $2.28 | $3.14 |
| 0067 | Topsoil amendment budget (629-000150) | DOL | 78,908 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0068 | Pipe, type 2, circular, diameter 15 in. (715-05032) | LFT | 247 | $90.00 | $74.30 | $88.00 | $71.01 | $53.47 | $39.82 |
| 0069 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 96 | $90.00 | $92.00 | $104.00 | $62.41 | $63.47 | $47.55 |
| 0070 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 97 | $128.00 | $120.00 | $144.00 | $103.79 | $90.86 | $73.31 |
| 0071 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 56 | $90.00 | $76.25 | $88.00 | $58.93 | $73.80 | $43.75 |
| 0072 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 29 | $90.00 | $101.00 | $156.00 | $77.42 | $78.65 | $47.55 |
| 0073 | Pipe, type 3, circular, diameter 18 in. (715-05171) | LFT | 50 | $100.00 | $90.50 | $114.00 | $77.75 | $94.16 | $53.09 |
| 0074 | Pipe, type 3, circular, diameter 30 in. (715-05175) | LFT | 50 | $175.00 | $144.00 | $178.00 | $131.40 | $144.50 | $100.32 |
| 0075 | Pipe, type 1, deformed, min. area 6.4 SFT (715-05237) | LFT | 67 | $330.00 | $252.00 | $388.00 | $269.42 | $281.15 | $222.21 |
| 0076 | Pipe extension, circular, diameter 15 in. , CCP (715-05595) | LFT | 12 | $90.00 | $105.00 | $188.00 | $259.69 | $131.74 | $100.39 |
| 0077 | Pipe extension, circular, diameter 15 in. , VCP (715-05595) | LFT | 3 | $90.00 | $210.00 | $670.00 | $367.28 | $297.40 | $265.36 |
| 0078 | Video inspection for pipe (715-09064) | LFT | 879 | $3.70 | $3.70 | $4.00 | $1.65 | $4.07 | $1.66 |
| 0079 | Pipe end section, diameter 6 in. (715-11665) | EACH | 6 | $1,000.00 | $570.00 | $1,491.46 | $441.52 | $613.39 | $776.81 |
| 0080 | Pipe, type 3, circular, diameter 6 in. (715-12405) | LFT | 172 | $25.00 | $38.00 | $45.90 | $31.41 | $34.70 | $25.09 |
| 0081 | Pipe end section, diameter 12 in. (715-46000) | EACH | 2 | $1,600.00 | $1,295.00 | $2,052.27 | $1,194.61 | $725.00 | $1,489.82 |
| 0082 | Pipe end section, diameter 15 in. (715-46005) | EACH | 6 | $1,600.00 | $1,300.00 | $2,141.15 | $1,196.43 | $1,050.00 | $1,553.50 |
| 0083 | Pipe end section, diameter 18 in. (715-46010) | EACH | 2 | $1,700.00 | $1,433.00 | $2,245.00 | $1,362.65 | $1,230.00 | $1,647.50 |
| 0084 | Pipe end section, diameter 24 in. (715-46020) | EACH | 3 | $1,800.00 | $1,915.00 | $2,550.00 | $1,690.20 | $1,628.00 | $2,239.24 |
| 0085 | Pipe end section, diameter 30 in. (715-46030) | EACH | 2 | $1,900.00 | $2,151.00 | $2,920.00 | $2,445.78 | $2,000.00 | $2,570.66 |
| 0086 | Pipe end section, min. area 6.4 SFT (715-46095) | EACH | 2 | $2,500.00 | $2,960.00 | $4,870.00 | $2,969.24 | $2,538.00 | $3,061.85 |
| 0087 | Inlet, type E7 (720-45030) | EACH | 1 | $3,200.00 | $3,198.00 | $2,650.00 | $2,955.33 | $3,900.00 | $1,766.60 |
| 0088 | Inlet, type F7 (720-45035) | EACH | 1 | $3,200.00 | $3,264.00 | $2,650.00 | $2,894.37 | $3,900.00 | $1,766.60 |
| 0089 | Inlet, type G7 (720-45040) | EACH | 1 | $3,200.00 | $4,201.00 | $2,780.00 | $3,053.02 | $4,065.00 | $1,766.60 |
| 0090 | Manhole, type C7 (720-94432) | EACH | 2 | $6,000.00 | $4,556.00 | $4,865.00 | $4,564.23 | $4,585.00 | $2,639.61 |
| 0091 | Road closure sign assembly (801-04308) | EACH | 6 | $225.00 | $211.00 | $240.00 | $225.00 | $248.00 | $211.00 |
| 0092 | Detour route marker assembly (801-06625) | EACH | 22 | $75.00 | $150.00 | $80.00 | $75.00 | $83.00 | $150.00 |
| 0093 | Construction sign, type A (801-06640) | EACH | 12 | $115.00 | $308.00 | $123.00 | $115.00 | $127.00 | $308.00 |
| 0094 | Construction sign, type B (801-06645) | EACH | 6 | $80.00 | $61.00 | $86.00 | $80.00 | $88.00 | $61.00 |
| 0095 | Maintaining traffic (801-06775) | LS | 1 | $93,000 | $18,000 | $48,000 | $9,489.62 | $13,995 | $132,814 |
| 0096 | Barricade, type III-A (801-07118) | LFT | 147 | $18.00 | $10.00 | $19.00 | $18.00 | $19.80 | $10.00 |
| 0097 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 324 | $30.00 | $25.00 | $16.00 | $30.00 | $33.00 | $30.00 |
| 0098 | Sign post, square, type 2, reinforced anchor base (802-05702) | LFT | 71 | $28.00 | $26.00 | $17.00 | $28.00 | $30.80 | $28.00 |
| 0099 | Sign, sheet, and supports, remove (802-07059) | EACH | 3 | $50.00 | $250.00 | $44.00 | $50.00 | $55.00 | $50.00 |
| 0100 | Sign, sheet, relocate (802-07060) | EACH | 3 | $250.00 | $500.00 | $45.00 | $250.00 | $275.00 | $250.00 |
| 0101 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 121 | $30.00 | $20.00 | $23.00 | $30.00 | $33.00 | $30.00 |
| 0102 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 98 | $32.00 | $22.00 | $18.00 | $32.00 | $35.20 | $32.00 |
| 0103 | Lighting foundation, conventional pole, concrete, with grounding (807-12791) | EACH | 8 | $3,000.00 | $2,800.00 | $2,415.00 | $3,000.00 | $3,300.00 | $3,000.00 |
| 0104 | Light pole, 30 FT E.M.H., 5 FT mast arm, breakaway base (807-85480) | EACH | 8 | $13,500 | $14,870 | $15,150 | $13,500 | $14,850 | $13,500 |
| 0105 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 8,285 | $0.70 | $0.59 | $1.00 | $0.70 | $0.77 | $0.59 |
| 0106 | Retro-reflectivity testing (808-09381) | LS | 1 | $2,500.00 | $2,455.00 | $2,680.00 | $2,500.00 | $2,750.00 | $2,455.00 |
| 0107 | Transverse marking, thermoplastic, yield line, white, 24 in. (808-10118) | LFT | 112 | $8.50 | $21.07 | $9.00 | $8.50 | $9.35 | $21.07 |
| 0108 | Line, thermoplastic, dotted, white, 4 in. (808-11482) | LFT | 53 | $0.70 | $3.33 | $1.00 | $0.70 | $0.77 | $3.33 |
| 0109 | Grooving for pavement markings (808-12032) | LFT | 17,507 | $0.55 | $0.62 | $0.60 | $0.55 | $0.61 | $0.62 |
| 0110 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 9,169 | $0.70 | $0.59 | $1.00 | $0.70 | $0.77 | $0.59 |
| 0111 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 12 | $170.00 | $184.00 | $182.00 | $170.00 | $187.00 | $184.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.