INDOT letting results, July 8, 2026
46 contracts let by Indiana DOT on July 8, 2026, $88,867,008 in low bids, a median of 4 bidders per contract.
- Owner
- Indiana DOT
- Contracts
- 46
- Low bids, total
- $88,867,008
- Data through
- 05 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| B-43243-B | BRIDGE MAINTENANCE AND REPAIR | Vincennes | 3 | Southern Road & Bridge, LLC | $12,676,734 | $14,343,964 | +13% | INDOT |
| B-44566-A | BRIDGE DECK REPLACEMENT | Greenfield | 4 | Beaty Construction Inc | $8,836,360 | $9,350,000 | +6.0% | INDOT |
| B-42442-A | BRIDGE REPLACEMENT | LaPorte | 4 | Dunnet Bay Construction Company | $8,117,156 | $8,262,151 | +2.0% | INDOT |
| R-44285-A | ROAD RECONSTRUCTION | Vincennes | 5 | Blankenberger Brothers Inc | $5,370,050 | $5,453,595 | +2.0% | INDOT |
| R-44162-A | HMA OVERLAY, MINOR STRUCTURAL | Greenfield | 3 | Milestone Contractors LP | $5,368,000 | $5,633,187 | +5.0% | INDOT |
| B-44515-A | BRIDGE REPLACEMENT AND DECK OVERLAY | Fort Wayne | 5 | Milestone Contractors LP | $4,235,938 | $4,427,416 | +5.0% | INDOT |
| R-45169-A | INTERSECTION IMPROVEMENT, MEDIAN U-TURN | Greenfield | 5 | Paul H Rohe Company Inc | $3,600,349 | $3,874,000 | +8.0% | INDOT |
| R-44663-A | HMA OVERLAY, PREVENTIVE MAINTENANCE | LaPorte | 2 | Rieth-Riley Construction Co., Inc. | $2,892,215 | $3,039,431 | +5.0% | INDOT |
| T-46131-A | CENTERLINE RUMBLE STRIPES INSTALLATION | Crawfordsville | 1 | Rieth-Riley Construction Co., Inc. | $2,735,500 | INDOT | ||
| R-45965-A | PAVEMENT PATCHING | Crawfordsville | 2 | Rieth-Riley Construction Co., Inc. | $2,607,010 | $2,980,280 | +14% | INDOT |
| R-43623-A | INTERSECTION IMPROVEMENT, ROUNDABOUT | Fort Wayne | 5 | Fleming Excavating Inc | $2,592,099 | $2,648,821 | +2.0% | INDOT |
| R-43766-A | SMALL STRUCTURES AND DRAINS | Seymour | 7 | 5 Star Company Inc | $2,591,012 | $2,878,136 | +11% | INDOT |
| R-43365-A | SLIDE CORRECTION, SMALL STRUCTURE AND DRAINS CONSTRUCTION | Seymour | 6 | Paul H Rohe Company Inc | $2,381,195 | $2,495,623 | +5.0% | INDOT |
| B-44484-A | BRIDGE DECK REPLACEMENT AND SMALL STRUCTURE PIPE LINING | Greenfield | 4 | Rieth-Riley Construction Co., Inc. | $1,909,729 | $1,983,610 | +4.0% | INDOT |
| R-43130-A | INTERSECTION IMPROVEMENT WITH ADDED TURN LANES AND SIGNALS | LaPorte | 2 | Rieth-Riley Construction Co., Inc. | $1,886,324 | $1,971,777 | +5.0% | INDOT |
| B-44244-A | BRIDGE REPLACEMENT | Crawfordsville | 7 | Duncan Robertson Inc | $1,745,859 | $2,021,219 | +16% | INDOT |
| R-44376-A | SMALL STRUCTURE PIPE LINING AND REPLACEMENT | Crawfordsville | 6 | Morphey Construction Inc. | $1,417,000 | $1,536,850 | +8.0% | INDOT |
| B-45531-A | BRIDGE REPLACEMENT | Fort Wayne | 4 | Milestone Contractors LP | $1,384,133 | $1,391,949 | +1.0% | INDOT |
| R-45569-A | HMA OVERLAY, PREVENTIVE MAINTENANCE | Fort Wayne | 2 | Rieth-Riley Construction Co., Inc. | $1,281,012 | $1,402,204 | +9.0% | INDOT |
| B-44339-A | BRIDGE REPLACEMENT | Fort Wayne | 6 | Milestone Contractors LP | $1,187,695 | $1,407,877 | +19% | INDOT |
| B-46217-A | BRIDGE DECK OVERLAY | Seymour | 8 | Dave O'Mara Contractor Inc | $1,153,939 | $1,342,508 | +16% | INDOT |
| R-43761-A | SLIDE CORRECTION | Seymour | 6 | Mac Construction & Excavating Inc | $1,097,342 | $1,263,937 | +15% | INDOT |
| B-44265-A | BRIDGE REPLACEMENT | Greenfield | 4 | Duncan Robertson Inc | $1,041,447 | $1,190,300 | +14% | INDOT |
| T-44690-A | TRAFFIC SIGNALS MODERNIZATION | Seymour | 3 | Midwestern Electric LLC | $1,008,671 | $1,204,601 | +19% | INDOT |
| B-44511-A | BRIDGE THIN DECK OVERLAY AND SMALL STRUCTURE REPLACEMENT | Vincennes | 5 | E & B Paving LLC | $995,950 | $996,197 | 0.0% | INDOT |
| R-44871-A | HMA OVERLAY AND SMALL STRUCTURE REPLACEMENT | Vincennes | 2 | E & B Paving LLC | $962,369 | $1,030,222 | +7.0% | INDOT |
| R-46544-A | PAVEMENT PATCHING | Seymour | 2 | E & B Paving LLC | $957,582 | $1,158,299 | +21% | INDOT |
| B-42338-A | BRIDGE DECK OVERLAY | Greenfield | 5 | Milestone Contractors LP | $738,823 | $796,000 | +8.0% | INDOT |
| R-45311-A | SMALL STRUCTURE REPLACEMENT | Seymour | 7 | 5 Star Company Inc | $647,309 | $867,107 | +34% | INDOT |
| R-46536-A | HMA OVERLAY, PREVENTIVE MAINTENANCE | Fort Wayne | 3 | E & B Paving LLC | $644,488 | $745,025 | +16% | INDOT |
| R-46493-A | SMALL STRUCTURES AND DRAINS CONSTRUCTION | Fort Wayne | 5 | Fleming Excavating Inc | $450,353 | $520,600 | +16% | INDOT |
| B-43938-A | BRIDGE COATING | Greenfield | 5 | Eagle Painting & Maintenance Company Inc | $417,021 | $425,000 | +2.0% | INDOT |
| B-44418-A | SCOUR PROTECTION | Seymour | 3 | Mac Construction & Excavating Inc | $417,000 | $477,655 | +15% | INDOT |
| T-46006-A | LIGHTING AND SIGN INSTALLATION | Greenfield | 8 | His Constructors Inc | $387,176 | $389,934 | +1.0% | INDOT |
| T-46037-A | TRAFFIC SIGNALS | LaPorte | 4 | Midwestern Electric LLC | $384,145 | $406,910 | +6.0% | INDOT |
| T-41617-A | TRAFFIC SIGNALS MODERNIZATION | Crawfordsville | 2 | Hawk Enterprises Inc | $367,000 | $391,570 | +7.0% | INDOT |
| T-45933-A | NEW FLASHER INSTALLATION | Seymour | 4 | Midwestern Electric LLC | $363,908 | $417,628 | +15% | INDOT |
| B-45347-A | SCOUR PROTECTION | Greenfield | 6 | 5 Star Company Inc | $342,660 | $395,500 | +15% | INDOT |
| T-45932-A | TRAFFIC SIGNALS | Seymour | 4 | Midwestern Electric LLC | $318,133 | $334,910 | +5.0% | INDOT |
| T-45920-A | UN-SIGNALIZED INTERSECTION SIGN AND MARKING VISIBILITY | Vincennes | 2 | Michiana Contracting Inc | $296,910 | $347,679 | +17% | INDOT |
| TM-46080-A | TRAFFIC SIGNAL MAINTENANCE | Greenfield | 3 | His Constructors Inc | $272,092 | $350,754 | +29% | INDOT |
| R-44802-A | HMA OVERLAY, PREVENTIVE MAINTENANCE | Greenfield | 3 | Paul H Rohe Company Inc | $257,068 | $262,000 | +2.0% | INDOT |
| T-45974-A | SIGNING | Fort Wayne | 8 | Hamm Contracting LLC | $218,258 | $220,910 | +1.0% | INDOT |
| T-46141-A | RAISED PAVEMENT MARKINGS, REFURBISHED | Greenfield | 4 | K & S Markers, Inc. | $147,426 | $151,913 | +3.0% | INDOT |
| R-45915-A | RAISED PAVEMENT MARKINGS, NEW | Crawfordsville | 5 | America'S Parking Remarking, LLC | $119,845 | $150,774 | +26% | INDOT |
| T-45902-A | PAVEMENT MARKINGS | Fort Wayne | 4 | Ce Hughes Milling Inc | $44,724 | $62,366 | +39% | INDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than INDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.