INDOT contract R-44376-A bid tabulation
SMALL STRUCTURE PIPE LINING AND REPLACEMENT. Let by Indiana DOT on July 8, 2026, Clinton, Crawfordsville. 6 bids received; low bid $1,417,000 by Morphey Construction Inc..
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 76
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morphey Construction Inc. | $1,417,000 | Low |
| 2 | William Charles Construction Company | $1,536,850 | +8.0% |
| 3 | Milestone Contractors LP | $1,579,475 | +11% |
| 4 | Superior Construction Co Inc | $1,599,650 | +13% |
| 5 | Rieth-Riley Construction Co., Inc. | $1,690,961 | +19% |
| 6 | E & B Paving LLC | $1,914,178 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morphey Construction Inc. | 2. William Charles Construction Company | 3. Milestone Contractors LP | 4. Superior Construction Co Inc | 5. Rieth-Riley Construction Co., Inc. | 6. E & B Paving LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $13,800 | $9,400.00 | $13,445 | $9,375.00 | $13,000 | $12,700 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $405.82 | $5,000.00 | $2,300.00 | $1,150.00 | $1,800.00 | $2,500.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $70,000 | $75,000 | $78,200 | $85,000 | $126,670 | $95,708 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $22,324 | $26,196 | $31,000 | $34,000 | $33,800 | $38,000 |
| 0013 | Present structure, remove, structure no. CV 421-012-133.62 (202-51330) | LS | 1 | $15,000 | $75,000 | $29,460 | $70,988 | $35,300 | $30,000 |
| 0014 | Pipe, remove (202-96133) | LFT | 109 | $50.00 | $41.00 | $14.00 | $45.00 | $12.00 | $27.00 |
| 0015 | Excavation, common (203-02000) | CYS | 461 | $80.00 | $70.00 | $60.00 | $60.00 | $80.00 | $100.00 |
| 0016 | Borrow (203-02070) | CYS | 113 | $60.00 | $52.00 | $1.00 | $49.00 | $50.00 | $100.00 |
| 0017 | Pump around (205-11626) | EACH | 3 | $12,000 | $40,000 | $7,100.00 | $15,000 | $3,200.00 | $22,000 |
| 0018 | Stormwater management budget (205-12108) | DOL | 30,900 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $750.00 | $10,000 | $7,800.00 | $72,000 | $5,500.00 | $11,500 |
| 0020 | SWQCP preparation (205-12618) | LS | 1 | $4,500.00 | $3,610.00 | $3,700.00 | $1,800.00 | $1,850.00 | $1,800.00 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 1,881 | $63.00 | $50.00 | $50.00 | $33.00 | $80.00 | $35.00 |
| 0022 | Structure backfill, type 2 (211-09265) | CYS | 83 | $120.00 | $100.00 | $125.00 | $66.00 | $144.00 | $184.00 |
| 0023 | Structure backfill, type 5 (211-09268) | CYS | 145 | $225.00 | $310.00 | $200.00 | $192.00 | $333.00 | $240.00 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,793 | $6.00 | $4.00 | $3.00 | $5.00 | $4.00 | $6.15 |
| 0025 | Compacted aggregate, no. 5 (301-12232) | CYS | 50 | $165.00 | $150.00 | $85.00 | $105.00 | $150.00 | $100.00 |
| 0026 | Compacted aggregate, no. 8 (301-12233) | CYS | 48 | $130.00 | $156.00 | $150.00 | $151.00 | $120.00 | $147.00 |
| 0027 | Compacted aggregate, no. 53 (301-12234) | CYS | 50 | $125.00 | $155.00 | $70.00 | $121.00 | $180.00 | $90.00 |
| 0028 | Compacted aggregate, no. 53 (303-01180) | TON | 290 | $60.00 | $70.00 | $70.00 | $44.00 | $62.00 | $75.00 |
| 0029 | Widening with HMA, type B (304-07493) | TON | 53 | $270.00 | $155.00 | $295.00 | $270.00 | $200.00 | $350.00 |
| 0030 | Milling, transition (306-08043) | SYS | 480 | $20.03 | $2.00 | $9.00 | $8.50 | $9.00 | $20.00 |
| 0031 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 171 | $130.00 | $166.00 | $200.00 | $130.00 | $166.00 | $130.00 |
| 0032 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 210 | $115.00 | $144.00 | $175.00 | $115.00 | $144.00 | $115.00 |
| 0033 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 511 | $118.00 | $111.00 | $135.00 | $118.00 | $111.00 | $118.00 |
| 0034 | Joint adhesive (401-11526) | LFT | 3,390 | $0.50 | $0.10 | $2.00 | $0.50 | $0.01 | $0.50 |
| 0035 | Asphalt for tack coat (406-05520) | TON | 1 | $600.00 | $11.00 | $10.00 | $600.00 | $11.00 | $599.99 |
| 0036 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 187.50 | $22.00 | $22.00 | $22.00 | $22.00 | $22.00 | $22.00 |
| 0037 | Guardrail, MGS, long span, type 2 (601-12288) | EACH | 2 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 0038 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,975.00 | $2,975.00 | $2,975.00 | $2,975.00 | $2,975.00 | $2,975.00 |
| 0039 | Fence, chain link, reset (603-06065) | LFT | 140 | $22.00 | $22.00 | $22.00 | $22.00 | $22.00 | $22.00 |
| 0040 | Right-of-way marker (615-06490) | EACH | 10 | $160.00 | $160.00 | $160.00 | $160.00 | $160.00 | $160.00 |
| 0041 | Monument, type B (615-06505) | EACH | 2 | $1,050.00 | $1,050.00 | $1,050.00 | $1,050.00 | $1,050.00 | $1,050.00 |
| 0042 | Riprap, class 1 (616-05688) | TON | 90 | $175.00 | $230.00 | $170.00 | $110.00 | $160.00 | $370.00 |
| 0043 | Riprap, revetment (616-06405) | TON | 170 | $150.00 | $160.00 | $115.00 | $94.00 | $100.00 | $135.00 |
| 0044 | Geotextile for riprap, type 2A (616-12248) | SYS | 469 | $4.00 | $3.00 | $2.00 | $7.00 | $4.00 | $9.65 |
| 0045 | Geotextile for riprap, type 2B (616-12249) | SYS | 152 | $5.00 | $9.00 | $10.00 | $12.00 | $9.00 | $18.00 |
| 0046 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $425.00 | $425.00 | $425.00 | $425.00 | $800.00 | $425.00 |
| 0047 | Seed mixture, native (621-03909) | LBS | 1 | $2,500.00 | $875.00 | $875.00 | $875.00 | $800.00 | $875.00 |
| 0048 | Mulched seeding, type R (621-06559) | SYS | 3,373 | $9.00 | $2.00 | $2.20 | $2.20 | $1.07 | $2.20 |
| 0049 | Sodding (621-06574) | SYS | 1,218 | $12.00 | $5.00 | $5.10 | $5.10 | $13.00 | $5.10 |
| 0050 | Computer system equipment (628-11976) | EACH | 2 | $800.00 | $2,000.00 | $1,750.00 | $500.00 | $800.00 | $650.00 |
| 0051 | Field office, type D (628-12683) | MOS | 15 | $2,400.00 | $3,000.00 | $8,500.00 | $3,650.00 | $7,600.00 | $3,750.00 |
| 0052 | Topsoil processing and distribution (629-000149) | SYS | 2,873 | $15.00 | $2.00 | $10.00 | $3.00 | $19.00 | $2.20 |
| 0053 | Topsoil amendment budget (629-000150) | DOL | 5,746 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0054 | Waterproofing membrane, type 3 (714-000087) | SFT | 1,481 | $6.00 | $9.00 | $4.50 | $8.00 | $9.00 | $5.20 |
| 0055 | Structure, coated reinforced concrete, box sections 17 FT X 4 FT (714-12972) | LFT | 47 | $3,500.00 | $4,020.00 | $4,300.00 | $5,000.00 | $2,900.00 | $3,500.00 |
| 0056 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 117 | $180.00 | $150.00 | $175.00 | $200.00 | $215.00 | $210.00 |
| 0057 | Pipe extension, circular, diameter 15 in. , RCP (715-05595) | LFT | 10 | $375.00 | $440.00 | $170.00 | $320.00 | $390.00 | $505.00 |
| 0058 | Concrete anchor, min. area 29.5 SFT (715-06939) | EACH | 1 | $10,400 | $11,016 | $19,300 | $11,000 | $3,000.00 | $15,500 |
| 0059 | HMA for structure installation, type B (715-08305) | TON | 14 | $240.00 | $690.00 | $750.00 | $353.20 | $270.00 | $570.00 |
| 0060 | Pipe installation, trenchless, 6 in. (716-07654) | LFT | 228 | $50.00 | $100.00 | $275.00 | $416.67 | $280.00 | $850.80 |
| 0061 | Pipe, drain tile terminal (719-05440) | LFT | 50 | $60.00 | $192.00 | $70.00 | $50.00 | $90.00 | $130.00 |
| 0062 | Pipe, drain tile terminal (719-05443) | LFT | 50 | $70.00 | $196.00 | $85.00 | $50.00 | $110.00 | $143.00 |
| 0063 | Manhole, type C2 (720-90984) | EACH | 3 | $5,500.00 | $8,360.00 | $6,500.00 | $8,500.00 | $8,500.00 | $12,000 |
| 0064 | Pipe liner, cured-in- place, min. area 26.8 SFT (725-12052) | LFT | 228.30 | $1,300.00 | $1,275.00 | $1,400.00 | $1,500.00 | $1,350.00 | $1,823.09 |
| 0065 | Road closure sign assembly (801-04308) | EACH | 6 | $250.00 | $295.00 | $249.00 | $250.00 | $265.00 | $265.00 |
| 0066 | Detour route marker assembly (801-06625) | EACH | 22 | $85.00 | $120.00 | $148.00 | $85.00 | $145.00 | $145.00 |
| 0067 | Construction sign, type A (801-06640) | EACH | 38 | $200.00 | $175.00 | $198.00 | $200.00 | $185.00 | $185.00 |
| 0068 | Flashing arrow sign (801-06710) | DAY | 90 | $25.00 | $20.00 | $15.00 | $25.00 | $21.00 | $21.00 |
| 0069 | Maintaining traffic (801-06775) | LS | 1 | $40,000 | $16,555 | $21,447 | $20,000 | $12,300 | $25,000 |
| 0070 | Barricade, type III-A (801-07118) | LFT | 48 | $18.00 | $16.00 | $15.51 | $18.00 | $12.00 | $12.00 |
| 0071 | Barricade, type III-B (801-07119) | LFT | 96 | $18.00 | $16.00 | $15.51 | $18.00 | $12.00 | $12.00 |
| 0072 | Truck mounted attenuator (801-12042) | DAY | 90 | $275.00 | $250.00 | $400.00 | $100.00 | $1,300.00 | $1,750.00 |
| 0073 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 22 | $35.00 | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 0074 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $200.00 | $300.00 | $300.00 | $300.00 | $300.00 | $300.00 |
| 0075 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 1,190 | $1.00 | $1.00 | $0.47 | $1.00 | $0.90 | $0.91 |
| 0076 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 1,190 | $1.00 | $1.00 | $0.47 | $1.00 | $0.90 | $0.89 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.