INDOT contract R-43365-A bid tabulation
SLIDE CORRECTION, SMALL STRUCTURE AND DRAINS CONSTRUCTION. Let by Indiana DOT on July 8, 2026, Franklin, Seymour. 6 bids received; low bid $2,381,195 by Paul H Rohe Company Inc.
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 80
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Paul H Rohe Company Inc | $2,381,195 | Low |
| 2 | Beaty Construction Inc | $2,495,623 | +5.0% |
| 3 | Sunesis Construction Company | $2,545,607 | +7.0% |
| 4 | Force Construction Co Inc | $2,660,225 | +12% |
| 5 | Morphey Construction Inc. | $3,260,000 | +37% |
| 6 | Milestone Contractors LP | $3,285,600 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Paul H Rohe Company Inc | 2. Beaty Construction Inc | 3. Sunesis Construction Company | 4. Force Construction Co Inc | 5. Morphey Construction Inc. | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $29,763 | $107,000 | $20,154 | $32,543 | $34,250 | $20,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $78,790 | $124,324 | $68,113 | $132,000 | $163,000 | $168,500 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $68,215 | $49,729 | $25,395 | $40,650 | $65,200 | $804,943 |
| 0011 | Paved side ditch, remove (202-02272) | LFT | 121 | $28.00 | $20.00 | $13.00 | $31.00 | $20.00 | $20.50 |
| 0012 | Fence, farm field, remove (202-99187) | LFT | 534 | $4.00 | $4.00 | $7.00 | $8.30 | $5.00 | $17.85 |
| 0013 | Excavation, common (203-02000) | CYS | 3,450 | $46.00 | $50.00 | $46.00 | $47.00 | $45.00 | $59.00 |
| 0014 | Borrow (203-02070) | CYS | 15 | $140.00 | $91.00 | $0.01 | $88.00 | $100.00 | $80.00 |
| 0015 | Pier, drill in bedrock socket , HP 12 X 53 (203-02590) | LFT | 1,260 | $244.00 | $583.00 | $520.00 | $497.00 | $300.00 | $425.00 |
| 0016 | Pier, non-formed, drill above bedrock socket , HP 12 X 53 (203-02592) | LFT | 1,667 | $199.00 | $28.00 | $97.00 | $145.00 | $300.00 | $80.00 |
| 0017 | Pump around (205-11626) | EACH | 1 | $11,410 | $45,000 | $6,085.00 | $17,200 | $10,000 | $30,000 |
| 0018 | Stormwater management budget (205-12108) | DOL | 31,607 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $18,000 | $20,000 | $15,962 | $13,010 | $500.00 | $40,000 |
| 0020 | SWQCP preparation (205-12618) | LS | 1 | $1,900.00 | $6,200.00 | $3,718.00 | $3,637.00 | $2,500.00 | $1,900.00 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 859 | $46.00 | $50.00 | $67.00 | $48.00 | $50.00 | $67.00 |
| 0022 | B borrow (211-02050) | CYS | 25 | $105.00 | $150.00 | $160.00 | $60.00 | $65.00 | $149.00 |
| 0023 | Structure backfill, type 2 (211-09265) | CYS | 258 | $92.00 | $65.00 | $122.00 | $102.00 | $65.00 | $65.00 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 253 | $7.50 | $10.00 | $10.00 | $7.20 | $7.50 | $11.25 |
| 0025 | Compacted aggregate, no. 8 (301-12233) | CYS | 13 | $190.00 | $400.00 | $320.00 | $100.00 | $150.00 | $385.00 |
| 0026 | Compacted aggregate, no. 53 (303-01180) | TON | 371 | $60.00 | $80.00 | $60.00 | $45.00 | $50.00 | $77.50 |
| 0027 | Widening with HMA, type B (304-07493) | TON | 280 | $180.00 | $140.00 | $141.00 | $161.00 | $235.00 | $195.00 |
| 0028 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 774 | $4.00 | $5.00 | $6.00 | $9.30 | $7.00 | $18.50 |
| 0029 | Milling, asphalt, 2 in. (306-08036) | SYS | 1,783 | $3.00 | $5.00 | $4.00 | $5.90 | $7.00 | $9.30 |
| 0030 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 317 | $150.00 | $140.00 | $141.00 | $145.00 | $140.00 | $195.00 |
| 0031 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 32 | $220.00 | $140.00 | $141.00 | $145.00 | $140.00 | $325.00 |
| 0032 | QC/QA-HMA, 2, 58S, base, 25.0 MM (401-000046) | TON | 77 | $190.00 | $140.00 | $141.00 | $145.00 | $140.00 | $300.00 |
| 0033 | Joint adhesive (401-11526) | LFT | 2,822 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $2.00 |
| 0034 | Asphalt for tack coat (406-05520) | TON | 3 | $850.00 | $600.00 | $605.00 | $623.00 | $600.00 | $750.00 |
| 0035 | Guardrail, reset (601-06035) | LFT | 50 | $50.00 | $21.00 | $21.00 | $52.00 | $50.00 | $50.00 |
| 0036 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 713 | $22.00 | $24.00 | $24.00 | $23.00 | $22.00 | $22.00 |
| 0037 | Guardrail, MGS, long span, type 1 (601-12287) | EACH | 1 | $1,400.00 | $1,800.00 | $1,814.00 | $1,455.00 | $1,400.00 | $1,400.00 |
| 0038 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $950.00 | $1,000.00 | $1,008.00 | $987.00 | $950.00 | $950.00 |
| 0039 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $2,900.00 | $3,000.00 | $3,023.00 | $3,013.00 | $2,900.00 | $2,900.00 |
| 0040 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 920 | $3.60 | $11.00 | $6.00 | $1.60 | $7.00 | $1.55 |
| 0041 | Right-of-way marker (615-06490) | EACH | 12 | $200.00 | $185.00 | $186.00 | $208.00 | $200.00 | $200.00 |
| 0042 | Monument, type B (615-06505) | EACH | 6 | $900.00 | $1,375.00 | $1,386.00 | $935.00 | $900.00 | $900.00 |
| 0043 | Monument, type C (615-06510) | EACH | 2 | $600.00 | $850.00 | $857.00 | $623.00 | $600.00 | $600.00 |
| 0044 | Riprap, class 1 (616-05688) | TON | 43 | $110.00 | $120.00 | $136.00 | $90.00 | $145.00 | $245.00 |
| 0045 | Riprap, class 2 (616-05689) | TON | 113 | $112.00 | $120.00 | $117.00 | $130.00 | $150.00 | $150.00 |
| 0046 | Riprap, revetment (616-06405) | TON | 100 | $82.00 | $80.00 | $88.00 | $93.00 | $130.00 | $140.00 |
| 0047 | Riprap, grouted, 12 in. (616-06425) | SYS | 31 | $230.00 | $220.00 | $147.00 | $240.00 | $170.00 | $230.00 |
| 0048 | Riprap, grouted, 24 in. (616-11928) | SYS | 15 | $335.00 | $460.00 | $212.00 | $495.00 | $250.00 | $476.00 |
| 0049 | Geotextile for riprap, type 1A (616-12246) | SYS | 169 | $4.50 | $6.00 | $7.00 | $5.50 | $6.00 | $13.00 |
| 0050 | Geotextile for riprap, type 2A (616-12248) | SYS | 104 | $13.00 | $12.00 | $11.00 | $6.20 | $12.00 | $23.65 |
| 0051 | Geotextile for riprap, type 2B (616-12249) | SYS | 33 | $15.00 | $36.00 | $76.00 | $44.00 | $50.00 | $90.50 |
| 0052 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $1,000.00 | $400.00 | $403.00 | $416.00 | $400.00 | $400.00 |
| 0053 | Erosion control blanket (621-02770) | SYS | 2,549 | $1.75 | $1.75 | $3.00 | $1.80 | $5.00 | $1.75 |
| 0054 | Seed mixture, native (621-03909) | LBS | 29 | $150.00 | $110.00 | $111.00 | $114.00 | $110.00 | $110.00 |
| 0055 | Mulched seeding, type R (621-06559) | SYS | 278 | $10.00 | $10.00 | $18.00 | $10.40 | $17.00 | $10.00 |
| 0056 | Articulated concrete block (621-09815) | SYS | 274 | $235.00 | $300.00 | $261.00 | $295.00 | $300.00 | $270.00 |
| 0057 | Computer system equipment (628-11976) | EACH | 2 | $950.00 | $650.00 | $1,161.00 | $831.00 | $675.00 | $1,325.00 |
| 0058 | Field office, type D (628-12683) | MOS | 15 | $3,700.00 | $3,500.00 | $3,345.00 | $3,637.00 | $2,400.00 | $6,000.00 |
| 0059 | Topsoil processing and distribution (629-000149) | SYS | 2,885 | $7.80 | $15.00 | $3.00 | $12.00 | $5.00 | $17.45 |
| 0060 | Topsoil amendment budget (629-000150) | DOL | 5,770 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0061 | Concrete, A, substructure (702-51005) | CYS | 35 | $1,465.00 | $2,000.00 | $3,005.00 | $1,210.00 | $1,800.00 | $1,850.00 |
| 0062 | Pipe, type 1, circular, diameter 36 in. (715-05019) | LFT | 66 | $220.00 | $500.00 | $433.00 | $319.00 | $480.00 | $525.00 |
| 0063 | Drilled shaft, diameter 24 in. (728-11742) | LFT | 4,216 | $128.50 | $101.00 | $151.00 | $103.00 | $265.00 | $80.00 |
| 0064 | Road closure sign assembly (801-04308) | EACH | 5 | $350.00 | $252.00 | $406.00 | $364.00 | $402.63 | $350.00 |
| 0065 | Detour route marker assembly (801-06625) | EACH | 63 | $139.00 | $157.00 | $110.00 | $144.00 | $109.49 | $139.00 |
| 0066 | Construction sign, type A (801-06640) | EACH | 18 | $200.00 | $209.00 | $128.00 | $208.00 | $126.95 | $200.00 |
| 0067 | Maintaining traffic (801-06775) | LS | 1 | $27,314 | $45,832 | $3,558.00 | $276,860 | $13,366 | $160,078 |
| 0068 | Barricade, type III-A (801-07118) | LFT | 48 | $18.00 | $15.85 | $11.00 | $19.00 | $11.26 | $18.00 |
| 0069 | Barricade, type III-B (801-07119) | LFT | 54 | $18.00 | $15.85 | $11.00 | $19.00 | $11.26 | $18.00 |
| 0070 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 30 | $28.00 | $58.00 | $53.00 | $29.00 | $28.00 | $28.00 |
| 0071 | Sign, sheet, and supports, remove (802-07059) | EACH | 2 | $50.00 | $21.00 | $28.00 | $52.00 | $50.00 | $50.00 |
| 0072 | Sign, sheet, relocate (802-07060) | EACH | 3 | $140.00 | $300.00 | $95.00 | $145.00 | $140.00 | $140.00 |
| 0073 | Grooving for pavement markings (808-12032) | LFT | 1,840 | $1.00 | $1.08 | $4.00 | $1.00 | $4.20 | $1.00 |
| 0074 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 1,840 | $1.00 | $0.72 | $3.00 | $1.00 | $2.50 | $1.00 |
| 0075 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 1,645 | $1.00 | $0.68 | $3.00 | $1.00 | $2.50 | $1.00 |
| 0076 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 22 | $25.00 | $12.00 | $101.00 | $104.00 | $5.00 | $95.00 |
| 0077 | Snowplowable raised pavement marker (808-75998) | EACH | 22 | $100.00 | $68.00 | $166.00 | $104.00 | $165.00 | $100.00 |
| 0078 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 49 | $1.50 | $1.20 | $3.00 | $1.60 | $2.50 | $1.50 |
| 0079 | Pier, formed, drill above bedrock socket , HP 12 X 53 (203-02591) | LFT | 475 | $392.00 | $63.00 | $162.00 | $53.00 | $320.00 | $25.00 |
| 0080 | Drilled shaft, exploratory core (728-11672) | LFT | 100 | $180.00 | $125.00 | $233.00 | $281.00 | $150.00 | $270.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.