SMALL STRUCTURES AND DRAINS. Let by Indiana DOT on July 8, 2026, Jefferson, Seymour. 7 bids received; low bid $2,591,012 by 5 Star Company Inc.
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 80
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 5 Star Company Inc | $2,591,012 | Low |
| 2 | Libs Paving Company Inc | $2,878,136 | +11% |
| 3 | Mac Construction & Excavating Inc | $2,897,000 | +12% |
| 4 | Dave O'Mara Contractor Inc | $3,358,000 | +30% |
| 5 | Paul H Rohe Company Inc | $3,426,063 | +32% |
| 6 | Milestone Contractors LP | $4,716,358 | +82% |
| 7 | E & B Paving LLC | $5,400,000 | +108% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 5 Star Company Inc | 2. Libs Paving Company Inc | 3. Mac Construction & Excavating Inc | 4. Dave O'Mara Contractor Inc | 5. Paul H Rohe Company Inc | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $38,500 | $15,000 | $56,070 | $40,000 | $26,400 | $31,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $201,560 | $100,000 | $130,000 | $163,000 | $72,550 | $240,000 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $22,000 | $25,000 | $75,000 | $97,000 | $46,940 | $120,000 |
| 0010 | Center curb, concrete, remove (202-02273) | SYS | 9 | $100.00 | $55.00 | $200.00 | $78.00 | $550.00 | $296.80 |
| 0011 | Curb and gutter, remove (202-02279) | LFT | 135 | $10.00 | $45.00 | $20.00 | $23.40 | $70.00 | $56.80 |
| 0012 | Slopewall, remove (202-51368) | SYS | 550 | $15.00 | $20.00 | $5.00 | $45.40 | $26.00 | $37.95 |
| 0013 | Pipe, remove (202-96133) | LFT | 2,077 | $10.00 | $60.00 | $30.00 | $26.00 | $46.00 | $45.00 |
| 0014 | Excavation, common (203-02000) | CYS | 570 | $58.00 | $60.00 | $95.00 | $72.85 | $40.00 | $119.00 |
| 0015 | Excavation, rock (203-02010) | CYS | 300 | $255.00 | $475.00 | $150.00 | $275.00 | $150.00 | $225.00 |
| 0016 | Pump around (205-11626) | EACH | 2 | $5,500.00 | $7,500.00 | $15,000 | $15,100 | $10,425 | $21,240 |
| 0017 | Stormwater management budget (205-12108) | DOL | 32,700 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $12,000 | $15,000 | $40,000 | $20,715 | $2,400.00 | $16,700 |
| 0019 | Subgrade treatment, type II (207-08264) | SYS | 3,961 | $34.00 | $35.00 | $26.00 | $24.25 | $37.00 | $34.50 |
| 0020 | B borrow (211-02050) | CYS | 730 | $45.00 | $115.00 | $80.00 | $74.00 | $97.00 | $102.80 |
| 0021 | Structure backfill, type 2 (211-09265) | CYS | 3,021 | $55.00 | $69.00 | $85.00 | $80.00 | $94.00 | $111.40 |
| 0022 | Geogrid, type IB (214-11796) | SYS | 3,961 | $3.80 | $1.50 | $4.00 | $5.50 | $5.00 | $4.65 |
| 0023 | Compacted aggregate, no. 8 (301-12233) | CYS | 14 | $60.00 | $995.00 | $320.00 | $173.00 | $220.00 | $1,440.00 |
| 0024 | HMA for temporary pavement, type C (402-10086) | TON | 1,309 | $150.00 | $240.00 | $125.00 | $100.00 | $150.00 | $169.70 |
| 0025 | Asphalt for tack coat (406-05520) | TON | 2 | $1,800.00 | $1,500.00 | $600.00 | $686.00 | $850.00 | $674.00 |
| 0026 | Guardrail, W-beam, shop curved, 6 FT 3 in. spacing (601-02103) | LFT | 68.75 | $45.00 | $40.00 | $40.00 | $52.00 | $38.00 | $41.70 |
| 0027 | Guardrail, remove (601-02241) | LFT | 1,452.50 | $10.00 | $9.50 | $9.50 | $0.57 | $11.00 | $12.05 |
| 0028 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,700.00 | $3,400.00 | $3,400.00 | $4,000.00 | $3,700.00 | $4,058.80 |
| 0029 | Guardrail end treatment, type MS (601-94690) | EACH | 11 | $6,500.00 | $6,000.00 | $6,000.00 | $15,400 | $6,650.00 | $7,295.00 |
| 0030 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 387.50 | $35.00 | $32.00 | $32.00 | $46.00 | $30.00 | $32.90 |
| 0031 | Guardrail, W-beam, double faced, 6 FT 3 in. spacing (601-99108) | LFT | 502.50 | $47.50 | $44.00 | $44.00 | $52.60 | $48.00 | $52.65 |
| 0032 | Curb and gutter, concrete (605-06140) | LFT | 135 | $25.00 | $65.00 | $72.00 | $72.00 | $100.00 | $91.00 |
| 0033 | Center curb, concrete, type C (605-06250) | SYS | 9 | $200.00 | $290.00 | $893.00 | $320.00 | $1,000.00 | $1,312.00 |
| 0034 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 564 | $8.50 | $16.00 | $16.38 | $2.30 | $13.00 | $17.95 |
| 0035 | Riprap, class 2 (616-05689) | TON | 25 | $95.00 | $550.00 | $250.00 | $126.00 | $240.00 | $982.00 |
| 0036 | Riprap, revetment (616-06405) | TON | 28 | $85.00 | $550.00 | $250.00 | $77.50 | $550.00 | $661.30 |
| 0037 | Geotextile for riprap, type 1A (616-12246) | SYS | 136 | $5.00 | $12.50 | $5.00 | $6.66 | $18.00 | $42.80 |
| 0038 | Slopewall, concrete, 4 in. (616-51367) | SYS | 575 | $75.00 | $90.00 | $20.00 | $106.00 | $72.00 | $124.25 |
| 0039 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $540.00 | $1,250.00 | $1,250.00 | $570.00 | $1,250.00 | $439.00 |
| 0040 | Mulched seeding, type R (621-06559) | SYS | 2,094 | $3.89 | $2.00 | $2.00 | $3.50 | $2.00 | $3.30 |
| 0041 | Computer system equipment (628-11976) | EACH | 4 | $400.00 | $1,000.00 | $750.00 | $1,715.00 | $950.00 | $3,120.00 |
| 0042 | Field office, type D (628-12683) | MOS | 12 | $2,150.00 | $4,500.00 | $5,200.00 | $2,860.00 | $3,550.00 | $4,370.00 |
| 0043 | Concrete, A, structures (702-44240) | CYS | 34 | $1,400.00 | $4,650.00 | $1,800.00 | $3,239.00 | $4,130.00 | $3,320.00 |
| 0044 | Concrete, B, footings (702-51015) | CYS | 24 | $1,400.00 | $250.00 | $1,800.00 | $1,544.00 | $3,510.00 | $2,420.00 |
| 0045 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 1,705 | $175.00 | $55.00 | $100.00 | $144.00 | $170.00 | $300.00 |
| 0046 | Pipe, type 1, circular, diameter 30 in. (715-05125) | LFT | 111 | $500.00 | $165.00 | $260.00 | $375.00 | $225.00 | $528.45 |
| 0047 | Pipe, type 1, circular, diameter 48 in. (715-05128) | LFT | 205 | $500.00 | $480.00 | $600.00 | $1,167.00 | $317.00 | $834.00 |
| 0048 | Pipe, type 1, deformed, min. area 8.8 SFT (715-08162) | LFT | 71 | $550.00 | $160.00 | $220.00 | $288.00 | $215.00 | $309.90 |
| 0049 | HMA for structure installation, type C (715-08306) | TON | 1,047 | $175.00 | $190.00 | $200.00 | $154.50 | $190.00 | $228.45 |
| 0050 | Video inspection for pipe (715-09064) | LFT | 2,097 | $2.76 | $2.00 | $2.00 | $4.00 | $3.37 | $2.15 |
| 0051 | Underdrain, patching (718-08308) | LFT | 314 | $20.00 | $95.00 | $40.00 | $78.75 | $160.00 | $273.70 |
| 0052 | Inlet reconstruct (720-04499) | EACH | 24 | $400.00 | $3,800.00 | $5,000.00 | $2,212.00 | $2,755.00 | $5,534.05 |
| 0053 | Temporary crossover, type B, refurbish (801-04153) | EACH | 1 | $22,000 | $6,000.00 | $12,000 | $11,440 | $7,675.00 | $72,640 |
| 0054 | Road closure sign assembly (801-04308) | EACH | 3 | $289.00 | $300.00 | $250.00 | $383.00 | $276.00 | $302.75 |
| 0055 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 79,255 | $2.03 | $1.80 | $1.75 | $2.46 | $1.89 | $2.05 |
| 0056 | Temporary pavement message marking, removable, lane indication arrow (801-06211) | EACH | 2 | $208.00 | $200.00 | $200.00 | $432.30 | $195.00 | $214.00 |
| 0057 | Construction sign, type A (801-06640) | EACH | 38 | $222.00 | $200.00 | $175.00 | $290.00 | $217.00 | $238.05 |
| 0058 | Flashing arrow sign (801-06710) | DAY | 120 | $18.00 | $15.00 | $15.00 | $28.60 | $16.00 | $17.55 |
| 0059 | Maintaining traffic (801-06775) | LS | 1 | $102,330 | $80,000 | $138,000 | $126,089 | $26,782 | $95,500 |
| 0060 | Barricade, type III-A (801-07118) | LFT | 156 | $19.00 | $18.00 | $16.00 | $17.10 | $16.26 | $17.85 |
| 0061 | Barricade, type III-B (801-07119) | LFT | 576 | $19.00 | $18.00 | $16.00 | $20.00 | $16.26 | $17.85 |
| 0062 | Temporary crossover drainage pipe (801-07606) | LFT | 560 | $23.00 | $100.00 | $100.00 | $137.00 | $70.00 | $122.75 |
| 0063 | Portable changeable message sign (801-11642) | EACH | 2 | $5,500.00 | $5,000.00 | $4,500.00 | $5,175.00 | $3,193.00 | $3,502.65 |
| 0064 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 11 | $400.00 | $400.00 | $300.00 | $406.00 | $383.65 | $420.85 |
| 0065 | Temporary crossover, type A (801-52818) | EACH | 3 | $15,500 | $22,000 | $30,000 | $43,025 | $62,340 | $118,908 |
| 0066 | Grooving for pavement markings (808-12032) | LFT | 761 | $2.25 | $2.00 | $2.00 | $2.30 | $2.17 | $2.40 |
| 0067 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 338 | $3.30 | $3.00 | $3.00 | $1.00 | $0.93 | $1.00 |
| 0068 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 338 | $3.30 | $3.00 | $3.00 | $1.00 | $0.93 | $1.00 |
| 0069 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 1 | $265.00 | $250.00 | $250.00 | $386.00 | $215.00 | $235.85 |
| 0070 | Line, thermoplastic, broken, white, 6 in. (808-96075) | LFT | 85 | $3.30 | $3.00 | $3.00 | $2.25 | $1.91 | $2.10 |
| 0071 | Atr station, 4 lane (809-05905) | EACH | 1 | $85,700 | $55,000 | $55,000 | $63,000 | $55,000 | $91,000 |
| 0072 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 1 | $550.00 | $750.00 | $2,000.00 | $2,220.00 | $1,500.00 | $2,500.00 |
| 0073 | Clearing and grubbing (201-01015) | LS | 1 | $18,000 | $7,000.00 | $65,000 | $60,000 | $20,835 | $19,307 |
| 0074 | Paved side ditch, remove (202-02272) | LFT | 110 | $5.00 | $75.00 | $60.00 | $69.00 | $55.00 | $259.35 |
| 0075 | Paved side ditch, type F (607-06360) | LFT | 100 | $25.00 | $135.00 | $200.00 | $137.00 | $185.00 | $640.95 |
| 0076 | Paved side ditch, type H (607-06370) | LFT | 10 | $100.00 | $275.00 | $375.00 | $216.00 | $400.00 | $879.25 |
| 0077 | Plant, deciduous tree, single stem, 1.25 in. to 2 in. (622-05649) | EACH | 5 | $822.00 | $635.00 | $635.00 | $915.00 | $635.00 | $630.75 |
| 0078 | Temporary shoring (702-04325) | LS | 1 | $22,900 | $37,000 | $45,000 | $104,200 | $477,575 | $280,350 |
| 0079 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $12,495 | $11,500 | $11,500 | $9,836.00 | $9,950.00 | $10,915 |
| 0080 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 500 | $36.00 | $80.00 | $50.00 | $105.30 | $55.00 | $143.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.