5 Star Company Inc: INDOT bid record
5 Star Company Inc submitted 98 bids on Indiana DOT contracts in the data, from 12 JAN 2022 to 05 NOV 2026, and was the low bidder on 41 of them (42%). When it was not low, its total sat a median +19% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $30,785,952
- Latest bid
- 05 NOV 2026
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 16 | 7 | 44% |
| 2023 | 9 | 4 | 44% |
| 2024 | 24 | 11 | 46% |
| 2025 | 20 | 8 | 40% |
| 2026 | 29 | 11 | 38% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Seymour | 51 | 22 | 43% |
| Greenfield | 19 | 7 | 37% |
| Crawfordsville | 15 | 7 | 47% |
| Vincennes | 7 | 3 | 43% |
| Fort Wayne | 5 | 2 | 40% |
| LaPorte | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 96 | 96 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 96 | 96 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 89 | 89 (100%) | $1.00 | $1.00 |
| Stormwater management budget | 205-12108 | DOL | 83 | 83 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 82 | 82 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 77 | 77 (100%) | $1.00 | $1.00 |
| Quality adjustments, HMA | 109-08440 | DOL | 57 | 57 (100%) | $1.00 | $1.00 |
| Project estimate adjustment | 109-08463 | DOL | 46 | 46 (100%) | $1.00 | $1.00 |
| Payment adjustment, PG asphalt binder | 109-09489 | DOL | 44 | 44 (100%) | $1.00 | $1.00 |
| Pump around | 205-11626 | EACH | 65 | 34 (52%) | $5,500.00 | $14,000 |
| Milling, asphalt, 1 1/2 in. | 306-08034 | SYS | 45 | 34 (76%) | $9.00 | $10.00 |
| Excavation, common | 203-02000 | CYS | 60 | 26 (43%) | $45.00 | $63.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Morphey Construction Inc. | 73 | 14 of 73 |
| Milestone Contractors LP | 45 | 10 of 45 |
| Paul H Rohe Company Inc | 36 | 12 of 36 |
| Dave Omara Contractor Inc | 36 | 11 of 36 |
| Olco Inc | 33 | 15 of 33 |
| E & B Paving LLC | 33 | 9 of 33 |
| Force Construction Co Inc | 24 | 7 of 24 |
| Yarberry Companies Inc | 22 | 5 of 22 |
| Yardberry Landscape Company | 16 | 2 of 16 |
| Collom Excavating LLC | 15 | 8 of 15 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 NOV 2026 | R-44432-A | Seymour | SMALL STRUCTURE REPLACEMENT AND PIPE LINING | 1 of 4 | $1,124,038 | Low, 26% under the second |
| 05 NOV 2026 | R-46935-A | Greenfield | TREE REMOVAL AND TRIMMING | 1 of 6 | $361,453 | Low, 26% under the second |
| 05 NOV 2026 | B-46218-A | Seymour | SMALL STRUCTURE REPLACEMENT | 1 of 7 | $446,353 | Low, 5.0% under the second |
| 05 NOV 2026 | B-46893-A | Greenfield | TREE REMOVAL AND TRIMMING | 2 of 4 | $237,803 | +29% |
| 05 NOV 2026 | M-46855-A | LaPorte | TREE REMOVAL AND TRIMMING | 2 of 5 | $198,403 | +67% |
| 07 OCT 2026 | R-43755-A | Seymour | SIGHT DISTANCE IMPROVEMENT | 3 of 5 | $388,140 | +11% |
| 07 OCT 2026 | R-44462-A | Seymour | SMALL STRUCTURE REPLACEMENT, PIPE LINING AND DRAINS CONSTR | 2 of 5 | $1,866,856 | +12% |
| 07 OCT 2026 | R-44469-A | Seymour | SMALL STRUCTURE PIPE LINING | 4 of 4 | $446,393 | +21% |
| 07 OCT 2026 | B-44959-A | Seymour | SCOUR PROTECTION | 7 of 8 | $461,116 | +76% |
| 07 OCT 2026 | B-44972-A | Seymour | SCOUR PROTECTION | 3 of 7 | $210,847 | +6.0% |
| 02 SEP 2026 | R-44461-A | Seymour | SMALL STRUCTURE REPLACEMENT AND PIPE LINING | 1 of 9 | $1,566,293 | Low, 19% under the second |
| 02 SEP 2026 | R-45304-A | Seymour | SMALL STRUCTURE REPLACEMENT | 4 of 9 | $176,816 | +25% |
| 02 SEP 2026 | B-45599-A | Greenfield | SCOUR PROTECTION | 2 of 7 | $147,575 | +5.0% |
| 02 SEP 2026 | B-45612-A | Greenfield | SCOUR PROTECTION | 1 of 7 | $327,596 | Low, 4.0% under the second |
| 05 AUG 2026 | R-44862-A | Vincennes | SMALL STRUCTURE MAINTENANCE AND REPAIR | 3 of 9 | $327,226 | +7.0% |
| 05 AUG 2026 | B-44436-A | Seymour | SMALL STRUCTURE REPLACEMENT WITH BRIDGE | 6 of 10 | $648,888 | +14% |
| 08 JUL 2026 | R-43766-A | Seymour | SMALL STRUCTURES AND DRAINS | 1 of 7 | $2,591,012 | Low, 11% under the second |
| 08 JUL 2026 | R-45311-A | Seymour | SMALL STRUCTURE REPLACEMENT | 1 of 7 | $647,309 | Low, 34% under the second |
| 08 JUL 2026 | B-45347-A | Greenfield | SCOUR PROTECTION | 1 of 6 | $342,660 | Low, 15% under the second |
| 08 APR 2026 | B-44594-A | Fort Wayne | DEBRIS REMOVAL FROM CHANNEL, REPAIR OR REPLACE JOINTS | 4 of 4 | $943,407 | +56% |
| 11 MAR 2026 | R-44130-A | Greenfield | AUXILIARY LANE CONSTRUCTION | 11 of 11 | $1,156,311 | +52% |
| 11 FEB 2026 | B-44425-A | Crawfordsville | SCOUR PROTECTION | 3 of 5 | $1,383,222 | +98% |
| 11 FEB 2026 | B-44941-A | Crawfordsville | SCOUR PROTECTION | 4 of 6 | $564,978 | +20% |
| 11 FEB 2026 | B-44943-A | Crawfordsville | SCOUR PROTECTION | 4 of 5 | $961,989 | +63% |
| 14 JAN 2026 | R-44328-A | Crawfordsville | SMALL STRUCTURE MAINTENANCE AND REPAIR | 1 of 6 | $96,765 | Low, 7.0% under the second |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.