INDOT contract R-44462-A bid tabulation
SMALL STRUCTURE REPLACEMENT, PIPE LINING AND DRAINS CONSTR. Let by Indiana DOT on October 7, 2026, Ripley, Seymour. 5 bids received; low bid $1,673,000 by Dave O'Mara Contractor Inc.
- Owner
- Indiana DOT
- Letting
- 07 OCT 2026
- Pay items
- 90
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dave O'Mara Contractor Inc | $1,673,000 | Low |
| 2 | 5 Star Company Inc | $1,866,856 | +12% |
| 3 | Morphey Construction Inc. | $1,921,000 | +15% |
| 4 | Milestone Contractors LP | $2,288,879 | +37% |
| 5 | Paul H Rohe Company Inc | $2,293,594 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dave O'Mara Contractor Inc | 2. 5 Star Company Inc | 3. Morphey Construction Inc. | 4. Milestone Contractors LP | 5. Paul H Rohe Company Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $16,000 | $35,000 | $20,000 | $35,000 | $14,600 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $1,000.00 | $350.00 | $341.94 | $1,690.00 | $1,110.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Mobilization and demobilization (110-01001) | LS | 1 | $83,000 | $88,000 | $96,050 | $112,500 | $107,505 |
| 0013 | Clearing right-of-way (201-52370) | LS | 1 | $33,400 | $24,500 | $21,000 | $100,000 | $23,440 |
| 0014 | Pavement removal (202-02240) | SYS | 374 | $18.00 | $40.00 | $60.00 | $66.80 | $29.00 |
| 0015 | Present structure, remove, structure no. , CV 046-069-141.28 (202-51330) | LS | 1 | $25,000 | $17,500 | $13,575 | $150,000 | $39,320 |
| 0016 | Present structure, remove, structure no. , CV 129-069-32.98 (202-51330) | LS | 1 | $25,000 | $4,500.00 | $4,400.00 | $35,000 | $14,980 |
| 0017 | Excavation, common (203-02000) | CYS | 575 | $49.00 | $48.00 | $72.00 | $123.00 | $134.00 |
| 0018 | Excavation, rock (203-02010) | CYS | 3 | $949.00 | $300.00 | $2,500.00 | $1,840.00 | $1,500.00 |
| 0019 | Pump around (205-11626) | EACH | 5 | $3,000.00 | $4,850.00 | $7,500.00 | $19,000 | $9,880.00 |
| 0020 | Stormwater management budget (205-12108) | DOL | 14,793 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0021 | Stormwater management implementation (205-12616) | LS | 1 | $13,420 | $5,000.00 | $965.00 | $10,200 | $4,200.00 |
| 0022 | Excavation, foundation, unclassified (206-51230) | CYS | 46 | $472.00 | $60.00 | $125.00 | $94.00 | $110.00 |
| 0023 | Subgrade treatment, type IC (207-09935) | SYS | 1,405 | $42.00 | $35.00 | $60.00 | $59.80 | $62.00 |
| 0024 | Structure backfill, type 2 (211-09265) | CYS | 355 | $95.00 | $80.00 | $112.00 | $86.20 | $130.00 |
| 0025 | Structure backfill, type 5 (211-09268) | CYS | 373 | $250.00 | $209.00 | $240.00 | $340.00 | $280.00 |
| 0026 | Geotextile for pavement, type 2A (214-12238) | SYS | 76 | $12.00 | $4.00 | $7.00 | $21.40 | $18.00 |
| 0027 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,078 | $7.00 | $4.00 | $5.00 | $6.85 | $8.50 |
| 0028 | Compacted aggregate, no. 8 (301-12233) | CYS | 78 | $127.00 | $65.00 | $180.00 | $220.00 | $200.00 |
| 0029 | Compacted aggregate, no. 53 (301-12234) | CYS | 4 | $63.00 | $56.00 | $190.00 | $720.00 | $220.00 |
| 0030 | Compacted aggregate, no. 53 (303-01180) | TON | 214 | $50.00 | $45.00 | $67.00 | $88.20 | $90.00 |
| 0031 | Widening with HMA, type B (304-07493) | TON | 102 | $118.00 | $200.00 | $445.00 | $155.00 | $215.00 |
| 0032 | HMA patching, full depth, type B (304-12623) | TON | 16 | $383.00 | $200.00 | $400.00 | $570.00 | $280.00 |
| 0033 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 2,328 | $9.00 | $15.00 | $1.50 | $16.90 | $7.50 |
| 0034 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 198 | $184.00 | $200.00 | $245.00 | $300.00 | $245.00 |
| 0035 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 106 | $184.00 | $200.00 | $260.00 | $360.00 | $250.00 |
| 0036 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 102 | $154.00 | $185.00 | $290.00 | $250.00 | $252.00 |
| 0037 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 59 | $154.00 | $185.00 | $295.00 | $260.00 | $280.00 |
| 0038 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 435 | $140.00 | $180.00 | $205.00 | $230.00 | $200.00 |
| 0039 | Joint adhesive (401-11526) | LFT | 2,098 | $7.00 | $1.00 | $2.00 | $2.55 | $1.40 |
| 0040 | Asphalt for tack coat (406-05521) | SYS | 4,820 | $0.29 | $1.00 | $1.10 | $0.20 | $0.55 |
| 0041 | Guardrail, remove (601-02241) | LFT | 278 | $18.00 | $10.00 | $18.00 | $5.00 | $5.00 |
| 0042 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 125 | $40.00 | $30.00 | $36.00 | $28.00 | $28.00 |
| 0043 | Guardrail, MGS, long span, type 2 (601-12288) | EACH | 2 | $2,400.00 | $1,500.00 | $2,400.00 | $1,400.00 | $1,400.00 |
| 0044 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $3,100.00 | $3,200.00 | $2,950.00 | $3,150.00 | $3,150.00 |
| 0045 | Curb, island concrete (605-02493) | SYS | 14 | $325.00 | $450.00 | $500.00 | $570.00 | $370.00 |
| 0046 | Curb, concrete (605-06120) | LFT | 71 | $73.00 | $50.00 | $75.00 | $200.00 | $95.00 |
| 0047 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 161 | $14.00 | $65.00 | $32.00 | $6.43 | $16.50 |
| 0048 | Monument, type B (615-06505) | EACH | 6 | $1,125.00 | $1,000.00 | $1,085.00 | $925.00 | $925.00 |
| 0049 | Riprap, class 1 (616-05688) | TON | 126 | $83.00 | $105.00 | $170.00 | $95.80 | $150.00 |
| 0050 | Riprap, revetment (616-06405) | TON | 134 | $72.00 | $100.00 | $160.00 | $94.00 | $105.00 |
| 0051 | Geotextile for riprap, type 1A (616-12246) | SYS | 340 | $6.00 | $4.00 | $6.00 | $8.35 | $4.18 |
| 0052 | Geotextile for riprap, type 2A (616-12248) | SYS | 353 | $6.00 | $4.00 | $6.00 | $8.60 | $5.00 |
| 0053 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $900.00 | $750.00 | $1,200.00 | $1,100.00 | $1,100.00 |
| 0054 | Mulched seeding, type R (621-06559) | SYS | 4,394 | $3.40 | $3.00 | $12.00 | $0.75 | $0.75 |
| 0055 | Field office, type D (628-12683) | MOS | 14 | $2,250.00 | $2,500.00 | $2,400.00 | $3,980.00 | $3,900.00 |
| 0056 | Temporary shoring , CV 129-069-32.98 (702-04325) | LS | 1 | $19,000 | $31,000 | $15,000 | $34,200 | $133,435 |
| 0057 | Concrete, A, substructure (702-51005) | CYS | 3.70 | $1,800.00 | $1,200.00 | $3,550.00 | $9,600.00 | $7,415.00 |
| 0058 | Concrete, B, footings (702-51015) | CYS | 4.40 | $1,225.00 | $1,200.00 | $700.00 | $1.00 | $7,060.00 |
| 0059 | Reinforcing bars, epoxy coated (703-06029) | LBS | 932 | $5.00 | $2.00 | $6.00 | $1.00 | $6.62 |
| 0060 | Waterproofing membrane, type 2 (714-000086) | SFT | 4,808 | $4.50 | $5.00 | $5.00 | $2.30 | $3.57 |
| 0061 | Structure, coated reinforced concrete, box sections, 13 FT X 8 FT (714-000143) | LFT | 67 | $3,158.00 | $3,800.00 | $4,200.00 | $2,900.00 | $5,020.00 |
| 0062 | Structure, reinforced concrete, box sections, 4 FT X 3 FT (714-11192) | LFT | 109 | $740.00 | $540.00 | $1,000.00 | $680.00 | $720.00 |
| 0063 | Pipe, type 1, circular, diameter 36 in. (715-05019) | LFT | 100 | $299.00 | $900.00 | $400.00 | $420.00 | $740.00 |
| 0064 | Pipe end section, diameter 36 in. (715-46040) | EACH | 2 | $3,197.00 | $3,100.00 | $6,500.00 | $4,500.00 | $3,175.00 |
| 0065 | Pipe liner, cured-in- place, 51 in. (725-11421) | LFT | 184 | $842.00 | $1,200.00 | $765.00 | $790.00 | $884.00 |
| 0066 | Road closure sign assembly (801-04308) | EACH | 6 | $257.00 | $159.00 | $234.00 | $234.00 | $234.00 |
| 0067 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 26,675 | $2.00 | $1.96 | $2.00 | $1.97 | $1.97 |
| 0068 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 76 | $12.00 | $11.00 | $10.89 | $10.89 | $10.89 |
| 0069 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 43 | $10.00 | $11.00 | $9.36 | $9.36 | $9.36 |
| 0070 | Detour route marker assembly (801-06625) | EACH | 69 | $136.00 | $80.00 | $124.00 | $124.00 | $124.00 |
| 0071 | Construction sign, type A (801-06640) | EACH | 49 | $207.00 | $164.00 | $188.00 | $188.00 | $188.00 |
| 0072 | Construction sign, type B (801-06645) | EACH | 4 | $121.00 | $81.00 | $110.00 | $110.00 | $110.00 |
| 0073 | Maintaining traffic (801-06775) | LS | 1 | $78,879 | $94,600 | $49,333 | $79,999 | $49,700 |
| 0074 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $8,179.00 | $6,500.00 | $7,435.00 | $5,750.01 | $5,750.00 |
| 0075 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $9,735.00 | $7,250.00 | $8,850.00 | $6,750.01 | $6,750.00 |
| 0076 | Barricade, type III-A (801-07118) | LFT | 72 | $14.83 | $11.00 | $13.48 | $13.48 | $13.48 |
| 0077 | Barricade, type III-B (801-07119) | LFT | 253 | $14.83 | $11.00 | $13.48 | $13.48 | $13.48 |
| 0078 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,105 | $45.00 | $56.00 | $44.00 | $80.40 | $42.00 |
| 0079 | Portable changeable message sign (801-11642) | EACH | 2 | $3,319.00 | $4,400.00 | $3,000.00 | $3,017.00 | $3,017.00 |
| 0080 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 26 | $42.00 | $31.00 | $15.00 | $28.00 | $28.00 |
| 0081 | Sign, sheet assembly, relocate (802-07058) | EACH | 2 | $209.00 | $300.00 | $180.00 | $275.00 | $275.00 |
| 0082 | Sign, ground mounted, reset (802-91122) | EACH | 1 | $450.00 | $420.00 | $160.00 | $375.00 | $375.00 |
| 0083 | Line, remove (808-06716) | LFT | 21,301 | $0.60 | $0.76 | $0.53 | $0.53 | $0.53 |
| 0084 | Retro-reflectivity testing (808-09381) | LS | 1 | $5,000.00 | $6,500.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 0085 | Grooving for pavement markings (808-12032) | LFT | 5,162 | $1.00 | $1.65 | $0.88 | $0.88 | $0.88 |
| 0086 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 9,156 | $1.00 | $1.90 | $0.91 | $0.91 | $0.91 |
| 0087 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 5,043 | $1.00 | $1.90 | $0.91 | $0.91 | $0.91 |
| 0088 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 109 | $13.50 | $20.00 | $12.27 | $12.27 | $12.27 |
| 0089 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 882 | $1.15 | $2.50 | $1.07 | $1.07 | $1.07 |
| 0090 | Temporary shoring (702-04325) | LS | 1 | $19,000 | $41,500 | $24,000 | $24,200 | $133,435 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.