INDOT contract R-44432-A bid tabulation
SMALL STRUCTURE REPLACEMENT AND PIPE LINING. Let by Indiana DOT on November 5, 2026, Decatur, Seymour. 4 bids received; low bid $1,124,038 by 5 Star Company Inc.
- Owner
- Indiana DOT
- Letting
- 05 NOV 2026
- Pay items
- 65
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 5 Star Company Inc | $1,124,038 | Low |
| 2 | Paul H Rohe Company Inc | $1,412,829 | +26% |
| 3 | Milestone Contractors LP | $1,447,961 | +29% |
| 4 | Morphey Construction Inc. | $1,514,600 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 5 Star Company Inc | 2. Paul H Rohe Company Inc | 3. Milestone Contractors LP | 4. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $18,500 | $10,900 | $47,000 | $20,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 4 | $550.00 | $1,400.00 | $2,603.50 | $1,000.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $65,500 | $60,365 | $75,000 | $75,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $10,000 | $23,780 | $100,000 | $20,000 |
| 0011 | Pipe abandon and grout fill (202-02637) | LFT | 75 | $349.00 | $380.00 | $316.70 | $500.00 |
| 0012 | Present structure, remove portions, structure no. , CV 003-016- 61.68, headwalls (202-51328) | LS | 1 | $14,250 | $14,890 | $15,000 | $15,000 |
| 0013 | Excavation, common (203-02000) | CYS | 307 | $40.00 | $150.00 | $52.60 | $70.00 |
| 0014 | Borrow (203-02070) | CYS | 27 | $46.00 | $180.00 | $131.10 | $40.00 |
| 0015 | Pump around (205-11626) | EACH | 4 | $3,500.00 | $20,350 | $17,010 | $20,000 |
| 0016 | Stormwater management budget (205-12108) | DOL | 41,624 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $2,900.00 | $3,000.00 | $15,604 | $3,500.00 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 72 | $61.00 | $118.00 | $71.20 | $65.00 |
| 0019 | Structure backfill, type 2 (211-09265) | CYS | 240 | $71.00 | $120.00 | $75.30 | $120.00 |
| 0020 | Structure backfill, type 5 (211-09268) | CYS | 46 | $169.00 | $360.00 | $274.00 | $300.00 |
| 0021 | Geotextile for pavement, type 2B (214-12239) | SYS | 72 | $4.00 | $9.00 | $29.00 | $30.00 |
| 0022 | Compacted aggregate, no. 2 (301-12231) | CYS | 8 | $45.00 | $260.00 | $190.95 | $180.00 |
| 0023 | Compacted aggregate, no. 8 (301-12233) | CYS | 15 | $45.00 | $280.00 | $498.30 | $200.00 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 3 | $45.00 | $150.00 | $290.00 | $70.00 |
| 0025 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 374 | $11.00 | $12.00 | $15.55 | $25.00 |
| 0026 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 37 | $185.00 | $340.00 | $304.45 | $425.00 |
| 0027 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 9 | $190.00 | $400.00 | $481.00 | $415.00 |
| 0028 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 21 | $149.00 | $390.00 | $245.75 | $410.00 |
| 0029 | Joint adhesive (401-11526) | LFT | 160 | $1.00 | $4.00 | $13.00 | $3.00 |
| 0030 | Asphalt for tack coat (406-05521) | SYS | 560 | $1.00 | $1.00 | $0.25 | $0.80 |
| 0031 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 140 | $45.00 | $40.00 | $87.20 | $25.00 |
| 0032 | Right-of-way marker (615-06490) | EACH | 9 | $490.00 | $455.00 | $497.00 | $455.00 |
| 0033 | Monument, type B (615-06505) | EACH | 2 | $2,200.00 | $2,000.00 | $2,180.00 | $2,000.00 |
| 0034 | Riprap, class 1 (616-05688) | TON | 36 | $115.00 | $165.00 | $140.45 | $250.00 |
| 0035 | Riprap, class 2 (616-05689) | TON | 78 | $115.00 | $158.00 | $134.85 | $220.00 |
| 0036 | Riprap, revetment (616-06405) | TON | 174 | $85.00 | $120.00 | $69.10 | $230.00 |
| 0037 | Geotextile for riprap, type 1A (616-12246) | SYS | 424 | $4.00 | $6.00 | $4.75 | $4.00 |
| 0038 | Geotextile for riprap, type 2A (616-12248) | SYS | 130 | $4.50 | $6.00 | $17.10 | $10.00 |
| 0039 | Mobilization and demobilization for seeding (621-01004) | EACH | 6 | $500.00 | $200.00 | $218.45 | $200.00 |
| 0040 | Erosion control blanket (621-02770) | SYS | 734 | $5.00 | $1.60 | $1.90 | $9.00 |
| 0041 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $500.00 | $600.00 | $5.45 | $5.00 |
| 0042 | Mulched seeding, type R (621-06559) | SYS | 5,795 | $2.90 | $1.15 | $2.70 | $9.00 |
| 0043 | Sodding (621-06574) | SYS | 30 | $35.00 | $11.00 | $114.65 | $130.00 |
| 0044 | Field office, type D (628-12683) | MOS | 12 | $2,450.00 | $3,800.00 | $4,147.00 | $2,400.00 |
| 0045 | Concrete, B, footings (702-51015) | CYS | 30 | $2,100.00 | $1,750.00 | $1,130.00 | $1,500.00 |
| 0046 | Concrete, A (702-90915) | CYS | 8 | $2,100.00 | $5,515.00 | $3,387.00 | $5,000.00 |
| 0047 | Reinforcing bars, epoxy coated (703-06029) | LBS | 7,526 | $4.00 | $3.40 | $2.40 | $3.50 |
| 0048 | Pipe, type 1, circular, diameter 48 in. (715-05128) | LFT | 49 | $800.00 | $290.00 | $306.20 | $575.00 |
| 0049 | Pipe installation, trenchless, 60 in. (716-07727) | LFT | 72 | $3,000.00 | $3,590.00 | $2,976.00 | $3,200.00 |
| 0050 | Perpetuation, existing pipe (725-10245) | EACH | 6 | $560.00 | $2,020.00 | $1,630.00 | $1,800.00 |
| 0051 | Pipe liner, cured-in- place, 60 in. (725-11288) | LFT | 180 | $1,133.00 | $1,095.00 | $1,115.00 | $1,315.00 |
| 0052 | Pipe liner, cured-in- place, min. area 14.7 SFT (725-12063) | LFT | 210 | $115.00 | $992.00 | $1,015.00 | $1,205.00 |
| 0053 | Road closure sign assembly (801-04308) | EACH | 4 | $78.00 | $75.00 | $244.00 | $75.00 |
| 0054 | Detour route marker assembly (801-06625) | EACH | 35 | $69.00 | $65.00 | $139.80 | $65.00 |
| 0055 | Construction sign, type A (801-06640) | EACH | 62 | $160.00 | $150.00 | $184.60 | $150.00 |
| 0056 | Construction sign, type B (801-06645) | EACH | 6 | $58.00 | $50.00 | $114.70 | $50.00 |
| 0057 | Maintaining traffic (801-06775) | LS | 1 | $152,650 | $58,920 | $74,995 | $42,003 |
| 0058 | Barricade, type III-A (801-07118) | LFT | 48 | $9.00 | $7.00 | $16.70 | $7.00 |
| 0059 | Barricade, type III-B (801-07119) | LFT | 48 | $9.00 | $7.00 | $16.70 | $7.00 |
| 0060 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 280 | $5.00 | $4.00 | $1.50 | $4.00 |
| 0061 | Grooving for pavement markings (808-12032) | LFT | 455 | $4.00 | $3.00 | $3.25 | $3.00 |
| 0062 | Line, thermoplastic, broken, yellow, 4 in. (808-75240) | LFT | 35 | $5.00 | $4.00 | $1.80 | $4.00 |
| 0063 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 140 | $5.00 | $4.00 | $1.50 | $4.00 |
| 0064 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 4 | $26.00 | $110.00 | $390.00 | $6.00 |
| 0065 | Snowplowable raised pavement marker (808-75998) | EACH | 4 | $300.00 | $250.00 | $136.50 | $250.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of November 5, 2026. Compiled by Mirage Metrics.