INDOT contract B-45612-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on September 2, 2026, Hancock, Henry, Rush, Greenfield. 7 bids received; low bid $327,596 by 5 Star Company Inc.
- Owner
- Indiana DOT
- Letting
- 02 SEP 2026
- Pay items
- 24
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 5 Star Company Inc | $327,596 | Low |
| 2 | Olco Inc | $341,130 | +4.0% |
| 3 | Morphey Construction Inc. | $345,188 | +5.0% |
| 4 | Milestone Contractors LP | $382,320 | +17% |
| 5 | Yarberry Companies Inc | $411,206 | +26% |
| 6 | Duncan Robertson Inc | $435,004 | +33% |
| 7 | Paul H Rohe Company Inc | $530,784 | +62% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 5 Star Company Inc | 2. Olco Inc | 3. Morphey Construction Inc. | 4. Milestone Contractors LP | 5. Yarberry Companies Inc | 6. Duncan Robertson Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $20,000 | $9,900.00 | $20,000 | $6,300.00 | $15,000 | $6,000.00 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $500.00 | $581.11 | $300.00 | $1,320.00 | $700.00 | $3,500.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $28,900 | $10,314 | $17,250 | $19,000 | $45,000 | $40,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $30,000 | $40,956 | $20,000 | $3,800.00 | $35,000 | $15,000 |
| 0011 | Stormwater management budget (205-12108) | DOL | 40,750 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Stormwater management implementation (205-12616) | LS | 1 | $2,500.00 | $4,650.53 | $2,200.00 | $18,000 | $6,000.00 | $85,000 |
| 0013 | Cofferdam , structure no. 1 (206-51235) | LS | 1 | $16,500 | $12,311 | $18,000 | $30,000 | $25,000 | $10,000 |
| 0014 | Cofferdam , structure no. 2 (206-51235) | LS | 1 | $16,000 | $24,623 | $18,000 | $30,000 | $25,000 | $10,000 |
| 0015 | Cofferdam , structure no. 3 (206-51235) | LS | 1 | $16,500 | $24,623 | $18,000 | $30,000 | $30,000 | $10,000 |
| 0016 | Grout for riprap (616-02281) | CYS | 65 | $400.00 | $515.43 | $368.00 | $520.00 | $400.00 | $1,000.00 |
| 0017 | Riprap, class 1 (616-05688) | TON | 194 | $121.00 | $150.74 | $120.00 | $195.00 | $200.00 | $50.00 |
| 0018 | Riprap, class 2 (616-05689) | TON | 352 | $121.00 | $150.74 | $120.00 | $235.00 | $200.00 | $50.00 |
| 0019 | Geotextile for riprap, type 1A (616-12246) | SYS | 306 | $4.00 | $6.24 | $7.00 | $8.00 | $10.00 | $4.00 |
| 0020 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $790.00 | $132.93 | $2,500.00 | $1,580.00 | $750.00 | $880.00 |
| 0021 | Mulched seeding, type R (621-06559) | SYS | 1,770 | $4.00 | $5.10 | $15.00 | $3.15 | $2.00 | $2.20 |
| 0022 | Construction sign, type A (801-06640) | EACH | 54 | $200.00 | $175.00 | $125.00 | $132.00 | $150.00 | $192.00 |
| 0023 | Construction sign, type B (801-06645) | EACH | 6 | $150.00 | $125.00 | $500.00 | $132.00 | $150.00 | $137.00 |
| 0024 | Maintaining traffic (801-06775) | LS | 1 | $41,000 | $34,492 | $55,000 | $26,791 | $35,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 2, 2026. Compiled by Mirage Metrics.