Duncan Robertson Inc: INDOT bid record
Duncan Robertson Inc submitted 86 bids on Indiana DOT contracts in the data, from 12 JAN 2022 to 05 NOV 2026, and was the low bidder on 41 of them (48%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $67,103,202
- Latest bid
- 05 NOV 2026
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 8 | 2 | 25% |
| 2023 | 14 | 11 | 79% |
| 2024 | 17 | 8 | 47% |
| 2025 | 24 | 12 | 50% |
| 2026 | 23 | 8 | 35% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Greenfield | 36 | 18 | 50% |
| Crawfordsville | 18 | 9 | 50% |
| Fort Wayne | 14 | 6 | 43% |
| Seymour | 12 | 6 | 50% |
| LaPorte | 4 | 1 | 25% |
| Vincennes | 2 | 1 | 50% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 85 | 85 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 85 | 85 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 85 | 85 (100%) | $1.00 | $1.00 |
| Stormwater management budget | 205-12108 | DOL | 83 | 83 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 82 | 82 (100%) | $1.00 | $1.00 |
| Quality adjustments, HMA | 109-08440 | DOL | 81 | 81 (100%) | $1.00 | $1.00 |
| Payment adjustment, PG asphalt binder | 109-09489 | DOL | 72 | 72 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 63 | 63 (100%) | $1.00 | $1.00 |
| Excavation, common | 203-02000 | CYS | 82 | 48 (59%) | $40.00 | $63.00 |
| Riprap, revetment | 616-06405 | TON | 73 | 38 (52%) | $60.00 | $100.00 |
| Concrete, C, superstructure | 704-51002 | CYS | 76 | 28 (37%) | $1,300.00 | $1,481.84 |
| Geotextile for pavement, type 2B | 214-12239 | SYS | 72 | 28 (39%) | $6.00 | $5.90 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Milestone Contractors LP | 78 | 28 of 78 |
| Beaty Construction Inc | 43 | 11 of 43 |
| Pontem Contractors Inc | 38 | 9 of 38 |
| E & B Paving LLC | 31 | 12 of 31 |
| His Constructors Inc | 26 | 10 of 26 |
| Force Construction Co Inc | 25 | 8 of 25 |
| Rieth-Riley Construction Co., Inc. | 23 | 6 of 23 |
| R L McCoy Inc | 14 | 6 of 14 |
| Icc Group Inc | 12 | 4 of 12 |
| Paul H Rohe Company Inc | 10 | 1 of 10 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 NOV 2026 | B-44266-A | Greenfield | BRIDGE REPLACEMENT | 2 of 2 | $1,225,178 | +3.0% |
| 05 NOV 2026 | B-44268-A | Greenfield | BRIDGE REHABILITATION OR REPAIR | 1 of 5 | $640,057 | Low, 6.0% under the second |
| 05 NOV 2026 | B-45063-A | Fort Wayne | BRIDGE REPLACEMENT | 5 of 6 | $2,207,345 | +17% |
| 07 OCT 2026 | B-43637-A | Seymour | BRIDGE REPLACEMENT | 1 of 8 | $1,712,490 | Low, 1.0% under the second |
| 07 OCT 2026 | B-44483-A | Greenfield | BRIDGE REPLACEMENT AND THIN DECK OVERLAY | 1 of 6 | $1,179,781 | Low, 9.0% under the second |
| 07 OCT 2026 | B-44619-A | Greenfield | BRIDGE REPLACEMENT | 1 of 6 | $1,669,080 | Low, 4.0% under the second |
| 07 OCT 2026 | B-44620-A | Greenfield | BRIDGE REPLACEMENT | 4 of 7 | $2,235,629 | +16% |
| 02 SEP 2026 | B-43605-A | Vincennes | BRIDGE REPLACEMENT | 4 of 9 | $2,734,143 | +14% |
| 02 SEP 2026 | B-43771-A | Seymour | BRIDGE AND SMALL STRUCTURE REPLACEMENT | 1 of 6 | $3,036,459 | Low, 2.0% under the second |
| 02 SEP 2026 | B-44104-A | LaPorte | BRIDGE REPLACEMENT | 2 of 4 | $3,027,174 | +2.0% |
| 02 SEP 2026 | B-44269-A | Greenfield | BRIDGE REHABILITATION OR REPAIR | 3 of 6 | $1,851,009 | +9.0% |
| 02 SEP 2026 | B-45068-A | Crawfordsville | BRIDGE DECK OVERLAY | 4 of 4 | $1,292,610 | +9.0% |
| 02 SEP 2026 | B-45599-A | Greenfield | SCOUR PROTECTION | 6 of 7 | $229,908 | +64% |
| 02 SEP 2026 | B-45612-A | Greenfield | SCOUR PROTECTION | 6 of 7 | $435,004 | +33% |
| 05 AUG 2026 | B-45349-A | Greenfield | BRIDGE DECK OVERLAY | 2 of 3 | $522,268 | +5.0% |
| 05 AUG 2026 | B-45351-A | Greenfield | SMALL STRUCTURE REPLACEMENT | 7 of 8 | $731,235 | +33% |
| 08 JUL 2026 | B-42338-A | Greenfield | BRIDGE DECK OVERLAY | 5 of 5 | $842,955 | +14% |
| 08 JUL 2026 | B-44244-A | Crawfordsville | BRIDGE REPLACEMENT | 1 of 7 | $1,745,859 | Low, 16% under the second |
| 08 JUL 2026 | B-44265-A | Greenfield | BRIDGE REPLACEMENT | 1 of 4 | $1,041,447 | Low, 14% under the second |
| 08 JUL 2026 | B-44484-A | Greenfield | BRIDGE DECK REPLACEMENT AND SMALL STRUCTURE PIPE LINING | 4 of 4 | $2,405,677 | +26% |
| 08 JUL 2026 | B-45531-A | Fort Wayne | BRIDGE REPLACEMENT | 3 of 4 | $1,448,565 | +5.0% |
| 08 JUL 2026 | B-46217-A | Seymour | BRIDGE DECK OVERLAY | 7 of 8 | $1,671,453 | +45% |
| 14 JAN 2026 | B-43650-A | Seymour | BRIDGE REPLACEMENT | 1 of 5 | $1,013,487 | Low, 3.0% under the second |
| 10 DEC 2025 | B-43610-A | Fort Wayne | BRIDGE REPLACEMENT | 6 of 8 | $3,264,241 | +24% |
| 10 DEC 2025 | B-44247-A | Crawfordsville | BRIDGE REPLACEMENT | 1 of 7 | $1,436,400 | Low, 3.0% under the second |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.