INDOT contract B-44619-A bid tabulation

BRIDGE REPLACEMENT. Let by Indiana DOT on October 7, 2026, Jay, Greenfield. 6 bids received; low bid $1,669,080 by Duncan Robertson Inc.

Owner
Indiana DOT
Letting
07 OCT 2026
Pay items
86
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Duncan Robertson Inc$1,669,080Low
2Milestone Contractors LP$1,727,799+4.0%
3Jutte Excavating II, Inc.$1,743,345+4.0%
4E & B Paving LLC$1,859,536+11%
5Beaty Construction Inc$1,961,960+18%
6Pontem Contractors Inc$2,095,256+26%
INDOT contract B-44619-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Duncan Robertson Inc2. Milestone Contractors LP3. Jutte Excavating II, Inc.4. E & B Paving LLC5. Beaty Construction Inc6. Pontem Contractors Inc
0001Construction engineering (105-06845)LS1$10,000$28,000$10,000$18,500$18,508$18,585
0002Inspection hole, deeper than 3 FT (107-09358)EACH2$2,000.00$2,000.00$200.00$1,200.00$3,650.00$490.00
0003Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, temporary traffic control devices and markings (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0010Mobilization and demobilization (110-01001)LS1$82,500$86,390$122,500$92,975$95,000$103,150
0011Clearing right-of-way (201-52370)LS1$47,500$51,834$30,000$55,786$32,500$40,000
0012Pavement removal (202-02240)SYS1,384$45.00$36.00$10.00$25.00$20.00$31.50
0013Paved side ditch, remove (202-02272)LFT35$10.00$46.00$30.00$12.00$20.00$60.00
0014Present structure, remove, structure no. 1 (202-51330)LS1$105,000$62,000$150,000$114,800$250,800$182,519
0015Excavation, common (203-02000)CYS1,435$30.00$55.00$20.10$55.00$50.00$92.00
0016Excavation, waterway (203-51223)CYS490$55.00$60.00$20.00$70.00$37.00$90.00
0017Pump around (205-11626)EACH1$5,000.00$14,000$5,000.00$22,500$25,000$75,000
0018Stormwater management budget (205-12108)DOL23,250$1.00$1.00$1.00$1.00$1.00$1.00
0019Stormwater management implementation (205-12616)LS1$20,000$2,300.00$20,000$42,000$6,200.00$3,588.00
0020SWQCP preparation (205-12618)LS1$2,250.00$1,500.00$20,000$2,000.00$3,400.00$48,625
0021Excavation, foundation, unclassified (206-51230)CYS160$55.00$56.00$77.50$82.00$43.00$69.00
0022Subgrade treatment, type IC (207-09935)SYS2,179$40.00$36.00$17.67$51.00$40.00$42.00
0023Aggregate for end bent backfill (211-06467)CYS39$120.00$142.00$60.00$195.00$235.00$98.00
0024Geotextile for pavement, type 2A (214-12238)SYS2,340$3.00$4.50$5.00$2.50$4.00$4.00
0025Geotextile for pavement, type 2B (214-12239)SYS2,338$6.00$4.50$5.00$4.00$2.50$4.50
0026Compacted aggregate, no. 8 (301-12233)CYS375$60.00$72.00$40.00$65.00$95.00$57.50
0027Compacted aggregate, no. 53 (301-12234)CYS190$55.00$76.00$47.38$60.00$95.00$101.00
0028Subbase for PCCP (302-06464)CYS40$150.00$276.00$50.00$178.00$150.00$217.00
0029Compacted aggregate, no. 53 (303-01180)TON271$60.00$60.00$31.18$52.00$65.00$57.00
0030Milling, transition (306-08043)SYS480$12.00$15.00$20.00$19.00$22.00$14.00
0031QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON197$158.00$144.00$144.00$225.00$145.00$151.50
0032QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON268$134.00$122.00$122.00$185.00$125.00$128.50
0033QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON662$119.00$108.00$108.00$140.00$110.00$113.50
0034Joint adhesive (401-11526)LFT3,804$0.27$0.25$0.25$0.25$0.25$0.50
0035Asphalt for tack coat (406-05520)TON1.10$1,200.00$1,100.00$1,100.00$0.01$1,100.00$1,155.00
0036Guardrail, remove (601-02241)LFT793$3.30$3.00$3.00$3.00$0.01$3.50
0037Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT175$22.00$20.00$20.00$20.00$31.00$21.00
0038Guardrail transition, MGS without curb (601-12292)EACH4$3,300.00$3,000.00$3,000.00$3,000.00$3,700.00$3,150.00
0039Guardrail end treatment, type OS (601-94689)EACH4$3,190.00$2,900.00$2,900.00$2,900.00$3,350.00$3,045.00
0040Barrier delineator (602-06729)EACH6$33.00$18.00$30.00$29.00$30.00$145.00
0041Milled HMA corrugations, sinusoidal (606-12400)LFT1,992$3.00$7.04$1.68$3.50$5.00$4.00
0042Paved side ditch, type H (607-06370)LFT291$150.00$172.00$100.00$195.00$210.00$91.00
0043Reinforced concrete bridge approach, 12 in. (609-06259)SYS157$225.00$170.00$181.00$210.00$205.00$256.00
0044Right-of-way marker (615-06490)EACH7$165.00$150.00$150.00$150.00$215.00$157.50
0045Monument, type B (615-06505)EACH2$1,092.00$993.00$993.00$993.00$2,000.00$1,043.00
0046Riprap, revetment (616-06405)TON551$50.00$53.00$40.00$64.00$85.00$80.00
0047Geotextile for riprap, type 1A (616-12246)SYS93$4.00$10.00$5.00$15.00$7.00$15.50
0048Geotextile for riprap, type 2A (616-12248)SYS809$4.00$4.50$5.00$4.15$5.00$4.50
0049Mobilization and demobilization for seeding (621-01004)EACH1$1,320.00$725.00$725.00$1,200.00$750.00$762.00
0050Mulched seeding, type R (621-06559)SYS5,210$2.20$1.60$1.60$2.00$1.75$2.00
0051Sodding (621-06574)SYS140$33.00$14.25$14.25$30.00$15.00$40.00
0052Sign, 'DO not spray' (621-52448)EACH2$143.00$125.00$125.00$250.00$125.00$131.50
0053Field office, type C (628-09403)MOS10$2,750.00$3,300.00$3,000.00$4,000.00$3,100.00$4,075.00
0054Topsoil processing and distribution (629-000149)SYS5,210$3.00$11.00$5.00$2.80$3.30$17.50
0055Topsoil amendment budget (629-000150)DOL10,420$1.00$1.00$1.00$1.00$1.00$1.00
0056Test pile, indicator, production (701-09558)LFT90$90.00$128.00$103.00$107.00$145.00$105.00
0057Test pile, indicator, restrike (701-09560)EACH2$2,000.00$2,000.00$1,000.00$7,000.00$2,000.00$1,518.00
0058Pile shoe, HP 12 X 53 (701-09739)EACH12$300.00$210.00$200.00$150.00$130.00$125.00
0059Pile, steel H, HP 12 X 53 (701-51195)LFT350$90.00$114.00$103.00$180.00$145.00$111.00
0060Grates, basins, and fittings, cast iron (702-12076)EACH4$4,000.00$2,300.00$2,000.00$2,500.00$2,400.00$2,257.00
0061Concrete, C, substructure (702-92857)CYS37.40$1,100.00$1,480.00$1,548.66$1,100.00$1,950.00$938.00
0062Reinforcing bars, epoxy coated (703-06029)LBS46,042$1.40$2.10$2.00$2.00$1.70$1.59
0063Threaded tie bar assembly, epoxy coated (703-97936)EACH36$55.00$44.00$50.00$40.00$55.00$55.50
0064Concrete, C, superstructure (704-51002)CYS115.30$1,225.00$1,225.00$1,600.00$1,350.00$1,175.00$1,350.00
0065Railing, concrete type FC (706-11600)CYS16.40$1,500.00$1,059.00$2,331.70$830.00$1,200.00$871.50
0066Concrete bridge railing transition, type TFC (706-11620)EACH4$2,000.00$3,000.00$2,800.00$2,000.00$4,800.00$2,100.00
0067Structural member, concrete, bulb-T beam, 42 in. X 49 in. (707-08158)LFT338$750.00$720.00$895.85$645.00$800.00$813.00
0068Surface seal (709-51821)LS1$1,800.00$500.00$15,000$1.00$1.00$2,625.00
0069Pipe, type 3, circular, diameter 15 in. (715-05169)LFT54$95.00$58.00$40.00$130.00$76.00$108.00
0070Pipe, end bent drain, diameter 6 in. (715-05407)LFT118$20.00$26.00$15.00$11.00$12.50$17.00
0071Pipe, roadway drain casting extension (715-10238)EACH4$1,250.00$2,000.00$1,500.00$750.00$1,500.00$1,206.00
0072Pipe end section, diameter 15 in. (715-46005)EACH2$600.00$600.00$400.00$650.00$775.00$934.00
0073Longitudinal grooving (722-12732)SYS449$10.00$9.60$14.00$9.00$7.00$15.50
0074Road closure sign assembly (801-04308)EACH5$262.00$238.00$262.00$238.00$240.00$275.50
0075Detour route marker assembly (801-06625)EACH59$153.00$139.00$136.00$139.00$140.00$143.00
0076Construction sign, type A (801-06640)EACH29$212.00$193.00$183.00$193.00$195.00$192.50
0077Maintaining traffic (801-06775)LS1$25,000$9,840.49$36,632$4,500.00$45,000$25,555
0078Barricade, type III-A (801-07118)LFT96$16.00$14.64$13.00$14.64$15.00$14.00
0079Barricade, type III-B (801-07119)LFT96$16.00$14.64$15.00$14.64$15.00$16.00
0080Portable changeable message sign (801-11642)EACH4$3,320.00$3,019.00$2,995.00$3,019.00$3,100.00$3,145.00
0081Sign post, square, type 1, reinforced anchor base (802-05701)LFT38$47.00$43.00$43.00$43.00$30.00$45.50
0082Sign, sheet, and supports, remove (802-07059)EACH1$116.00$106.00$106.00$106.00$105.00$111.50
0083Sign, sheet, with legend, 0.080 in. thickness (802-09838)SFT8$191.00$174.00$175.00$174.00$71.00$183.00
0084Line, multi-component, solid, white, 6 in. (808-10049)LFT1,580$1.00$0.88$2.00$0.88$0.90$2.50
0085Grooving for pavement markings (808-12032)LFT1,495$1.10$1.02$2.99$1.02$1.00$3.50
0086Line, multi-component, broken, yellow, 6 in. (808-12841)LFT198$1.10$1.01$2.00$1.01$1.00$2.50
INDOT contract B-44619-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy