INDOT contract B-44269-A bid tabulation
BRIDGE REHABILITATION OR REPAIR. Let by Indiana DOT on September 2, 2026, Delaware, Greenfield. 6 bids received; low bid $1,703,674 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 02 SEP 2026
- Pay items
- 106
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $1,703,674 | Low |
| 2 | Pontem Contractors Inc | $1,842,830 | +8.0% |
| 3 | Duncan Robertson Inc | $1,851,009 | +9.0% |
| 4 | Milestone Contractors LP | $1,870,893 | +10% |
| 5 | Beaty Construction Inc | $1,887,234 | +11% |
| 6 | Superior Construction Co Inc | $2,087,000 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Pontem Contractors Inc | 3. Duncan Robertson Inc | 4. Milestone Contractors LP | 5. Beaty Construction Inc | 6. Superior Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,000 | $15,000 | $17,500 | $14,500 | $15,000 | $25,605 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $85,184 | $92,000 | $92,500 | $92,500 | $95,000 | $107,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $33,615 | $59,500 | $37,000 | $37,000 | $35,000 | $42,000 |
| 0011 | Pavement removal (202-02240) | SYS | 418 | $15.00 | $30.00 | $50.00 | $48.00 | $42.00 | $40.00 |
| 0012 | Curb and gutter, remove (202-02279) | LFT | 348 | $10.00 | $15.00 | $0.01 | $15.00 | $10.00 | $10.00 |
| 0013 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $200,000 | $263,040 | $225,000 | $206,625 | $257,000 | $338,954 |
| 0014 | Bridge railing, remove (202-62420) | LFT | 392 | $1.00 | $40.00 | $5.00 | $79.00 | $4.00 | $25.00 |
| 0015 | Inlet, remove (202-91385) | EACH | 3 | $1.00 | $600.00 | $500.00 | $635.00 | $365.00 | $500.00 |
| 0016 | Pipe, remove (202-96133) | LFT | 120 | $1.00 | $25.00 | $20.00 | $15.00 | $23.00 | $20.00 |
| 0017 | Excavation, common (203-02000) | CYS | 120 | $250.00 | $68.50 | $100.00 | $110.00 | $125.00 | $42.50 |
| 0018 | Linear grading (203-08607) | LFT | 710 | $3.00 | $7.00 | $4.00 | $6.00 | $4.00 | $2.00 |
| 0019 | Stormwater management budget (205-12108) | DOL | 17,636 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $7,000.00 | $22,500 | $12,500 | $16,500 | $15,000 |
| 0021 | Cofferdam (206-51235) | LS | 1 | $15,000 | $100,000 | $5,000.00 | $35,000 | $82,000 | $32,500 |
| 0022 | Subgrade treatment, type III (207-08266) | SYS | 100 | $10.00 | $26.00 | $10.00 | $25.00 | $12.00 | $11.00 |
| 0023 | Subgrade treatment, type IC (207-09935) | SYS | 776 | $50.00 | $44.50 | $65.00 | $72.00 | $50.00 | $25.00 |
| 0024 | Aggregate for end bent backfill (211-06467) | CYS | 27 | $180.00 | $90.00 | $125.00 | $200.00 | $195.00 | $125.00 |
| 0025 | Drilled hole for flowable backfill (213-08068) | EACH | 8 | $200.00 | $435.00 | $500.00 | $100.00 | $55.00 | $250.00 |
| 0026 | Flowable backfill, non- removable (213-09269) | CYS | 10 | $1,000.00 | $235.50 | $1,200.00 | $520.00 | $375.00 | $500.00 |
| 0027 | Geotextile for pavement, type 2B (214-12239) | SYS | 628 | $5.00 | $6.50 | $4.00 | $8.00 | $7.00 | $3.00 |
| 0028 | Compacted aggregate, no. 53 (301-12234) | CYS | 75 | $125.00 | $94.00 | $115.00 | $160.00 | $148.00 | $100.00 |
| 0029 | Subbase for PCCP (302-06464) | CYS | 72 | $125.00 | $195.00 | $135.00 | $225.00 | $165.00 | $60.00 |
| 0030 | Compacted aggregate, no. 53 (303-01180) | TON | 60 | $75.00 | $54.00 | $70.00 | $180.00 | $120.00 | $120.00 |
| 0031 | Compacted aggregate, no. 73 (303-07449) | TON | 22 | $75.00 | $54.00 | $70.00 | $90.00 | $102.00 | $60.00 |
| 0032 | Widening with HMA, type B (304-07493) | TON | 49 | $229.00 | $325.00 | $209.00 | $280.00 | $199.05 | $199.05 |
| 0033 | Milling, transition (306-08043) | SYS | 856 | $10.00 | $7.50 | $10.00 | $10.00 | $8.00 | $2.00 |
| 0034 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 105 | $236.00 | $179.00 | $187.00 | $225.00 | $170.02 | $170.02 |
| 0035 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 43 | $335.00 | $260.00 | $272.00 | $310.00 | $247.26 | $247.26 |
| 0036 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 185 | $162.00 | $161.50 | $168.00 | $165.00 | $153.57 | $153.57 |
| 0037 | Joint adhesive (401-11526) | LFT | 1,306 | $0.35 | $1.00 | $0.66 | $2.00 | $0.60 | $0.60 |
| 0038 | Asphalt for tack coat (406-05521) | SYS | 1,773 | $0.35 | $1.00 | $0.77 | $0.50 | $0.69 | $0.69 |
| 0039 | Terminal joint, type HMA (503-12477) | LFT | 68 | $220.00 | $320.00 | $300.00 | $400.00 | $500.00 | $255.00 |
| 0040 | Guardrail transition, type TGB (601-01522) | EACH | 2 | $2,785.00 | $3,202.50 | $4,345.00 | $3,200.00 | $2,785.00 | $3,050.00 |
| 0041 | Guardrail terminal system, W-beam, curved, type 5 (601-01848) | EACH | 1 | $2,400.00 | $2,677.50 | $2,805.00 | $2,680.00 | $2,400.00 | $2,550.00 |
| 0042 | Guardrail, W-beam, shop curved, 6 FT 3 in. spacing (601-02103) | LFT | 25 | $37.00 | $29.50 | $31.00 | $30.00 | $37.00 | $28.00 |
| 0043 | Guardrail, remove (601-02241) | LFT | 200 | $19.00 | $7.50 | $6.00 | $7.50 | $19.00 | $7.00 |
| 0044 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 138 | $22.00 | $22.50 | $23.00 | $22.00 | $22.00 | $21.00 |
| 0045 | Guardrail transition, MGS without curb (601-12292) | EACH | 2 | $3,200.00 | $3,334.00 | $3,495.00 | $3,350.00 | $3,200.00 | $3,175.00 |
| 0046 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $2,300.00 | $3,097.50 | $3,245.00 | $3,100.00 | $2,300.00 | $2,950.00 |
| 0047 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 38 | $24.00 | $23.50 | $24.00 | $23.00 | $24.00 | $22.00 |
| 0048 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 247 | $150.00 | $252.00 | $275.00 | $195.00 | $150.00 | $128.50 |
| 0049 | Monument, type B (615-06505) | EACH | 2 | $1,250.00 | $976.50 | $1,023.00 | $975.00 | $1,250.00 | $1,175.00 |
| 0050 | Benchmark post (615-06530) | EACH | 1 | $500.00 | $420.00 | $500.00 | $425.00 | $800.00 | $850.00 |
| 0051 | Riprap, revetment (616-06405) | TON | 188 | $300.00 | $71.00 | $75.00 | $150.00 | $125.00 | $175.00 |
| 0052 | Geotextile for riprap, type 1A (616-12246) | SYS | 309 | $5.00 | $6.00 | $3.00 | $10.00 | $4.00 | $12.00 |
| 0053 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $16,000 | $16,800 | $17,600 | $17,000 | $16,000 | $16,000 |
| 0054 | Clean steel bridge, QP-2, bridge no. 1 (619-11052) | LS | 1 | $99,000 | $103,950 | $110,000 | $104,000 | $99,000 | $99,000 |
| 0055 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $6,000.00 | $6,300.00 | $6,600.00 | $6,250.00 | $6,000.00 | $6,000.00 |
| 0056 | Clean steel bridge, top flanges, type QP-2, bridge no. 1 (619-12506) | LS | 1 | $17,500 | $18,375 | $19,250 | $18,250 | $17,500 | $17,500 |
| 0057 | Coat steel bridge, bridge no. 1 (619-51859) | LS | 1 | $39,500 | $41,475 | $43,450 | $41,400 | $39,500 | $39,500 |
| 0058 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $6,000.00 | $6,300.00 | $6,600.00 | $6,250.00 | $77,500 | $6,000.00 |
| 0059 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $650.00 | $682.50 | $715.00 | $1,600.00 | $650.00 | $650.00 |
| 0060 | Mulched seeding, type R (621-06559) | SYS | 395 | $3.85 | $4.50 | $4.25 | $5.50 | $3.85 | $3.85 |
| 0061 | Sodding (621-06574) | SYS | 113 | $23.00 | $59.50 | $26.50 | $37.00 | $23.00 | $23.00 |
| 0062 | Seed mixture, floodplain (621-12612) | LBS | 5 | $298.00 | $313.00 | $330.00 | $211.00 | $298.00 | $298.00 |
| 0063 | Sign, 'DO not spray' (621-52448) | EACH | 4 | $125.00 | $131.50 | $137.50 | $116.00 | $125.00 | $125.00 |
| 0064 | Field office, type A (628-09401) | MOS | 9 | $3,250.00 | $3,145.00 | $2,500.00 | $3,800.00 | $3,500.00 | $2,650.00 |
| 0065 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 4 | $2,000.00 | $2,200.00 | $3,500.00 | $5,000.00 | $1,800.00 | $1,200.00 |
| 0066 | Concrete, A, substructure (702-51005) | CYS | 22.70 | $500.00 | $1,277.00 | $1,250.00 | $2,300.00 | $1,200.00 | $1,975.00 |
| 0067 | Field drilled hole in concrete (702-51863) | EACH | 176 | $5.00 | $20.00 | $12.00 | $21.00 | $28.00 | $25.00 |
| 0068 | Reinforcing bars, epoxy coated (703-06029) | LBS | 87,185 | $1.25 | $1.55 | $2.00 | $1.85 | $1.62 | $1.45 |
| 0069 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 48 | $10.00 | $61.50 | $65.00 | $52.00 | $60.00 | $52.75 |
| 0070 | Concrete, C, superstructure (704-51002) | CYS | 204.70 | $1,700.00 | $1,120.00 | $1,750.00 | $1,475.00 | $1,200.00 | $1,450.00 |
| 0071 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 4 | $4,500.00 | $5,400.00 | $2,250.00 | $5,500.00 | $5,000.00 | $3,250.00 |
| 0072 | Railing, steel type PF-1 (706-11404) | LFT | 408 | $83.51 | $81.00 | $85.00 | $80.00 | $84.00 | $77.00 |
| 0073 | Railing, concrete type PF-1 (706-11602) | CYS | 24 | $1,500.00 | $1,585.00 | $1,400.00 | $1,125.00 | $2,400.00 | $1,957.00 |
| 0074 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $0.01 | $12,075 | $6,000.00 | $4,900.00 | $1.00 | $0.01 |
| 0075 | Patching concrete structures (710-09158) | SFT | 50 | $85.00 | $197.00 | $250.00 | $225.00 | $85.00 | $214.00 |
| 0076 | Structural steel (711-51038) | LS | 1 | $32,000 | $15,400 | $9,800.00 | $21,000 | $15,000 | $195,000 |
| 0077 | Drilled hole (711-51864) | EACH | 124 | $86.00 | $90.50 | $95.00 | $91.00 | $86.00 | $150.00 |
| 0078 | Jacking and supporting steel beams , bridge no. 1 (711-95291) | LS | 1 | $11,800 | $21,910 | $12,980 | $12,500 | $20,000 | $75,000 |
| 0079 | Stud shear connectors (711-96800) | EACH | 5,850 | $4.15 | $4.50 | $4.60 | $4.50 | $4.15 | $4.50 |
| 0080 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 48 | $20.00 | $34.50 | $15.00 | $25.00 | $17.00 | $15.00 |
| 0081 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 100 | $20.00 | $17.00 | $18.00 | $26.00 | $22.00 | $16.00 |
| 0082 | Pipe extension, circular, diameter 6 in. , thermosetting (715-06566) | LFT | 14 | $20.00 | $445.00 | $300.00 | $41.00 | $270.00 | $220.00 |
| 0083 | Outlet protector, type 3 (718-06531) | EACH | 1 | $1,750.00 | $975.00 | $2,500.00 | $640.00 | $730.00 | $1,300.00 |
| 0084 | Geotextile for underdrains, type 1A (718-12305) | SYS | 86 | $5.00 | $3.50 | $4.00 | $15.00 | $6.00 | $12.00 |
| 0085 | Longitudinal grooving (722-12732) | SYS | 976 | $3.50 | $12.50 | $6.00 | $4.00 | $3.39 | $3.39 |
| 0086 | Bearing assembly, elastomeric (726-92406) | EACH | 12 | $5,000.00 | $3,275.00 | $2,250.00 | $3,100.00 | $2,500.00 | $3,250.00 |
| 0087 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 25 | $25.00 | $10.50 | $11.00 | $11.00 | $25.00 | $10.00 |
| 0088 | Epoxy injection, crack preparation (727-90308) | LFT | 100 | $59.91 | $75.50 | $79.00 | $115.00 | $59.91 | $109.00 |
| 0089 | Epoxy injection, furnishing equipment (727-93560) | LS | 1 | $2,500.00 | $787.50 | $825.00 | $1,014.00 | $2,500.00 | $965.00 |
| 0090 | Road closure sign assembly (801-04308) | EACH | 3 | $212.00 | $223.00 | $233.00 | $223.00 | $265.00 | $212.00 |
| 0091 | Detour route marker assembly (801-06625) | EACH | 24 | $143.00 | $151.00 | $157.00 | $150.00 | $150.00 | $143.00 |
| 0092 | Construction sign, type A (801-06640) | EACH | 26 | $188.00 | $198.00 | $207.00 | $198.00 | $165.00 | $188.00 |
| 0093 | Maintaining traffic (801-06775) | LS | 1 | $10,000 | $25,000 | $25,000 | $3,500.00 | $50,000 | $37,500 |
| 0094 | Barricade, type III-A (801-07118) | LFT | 48 | $15.32 | $16.50 | $17.00 | $17.00 | $20.00 | $15.32 |
| 0095 | Barricade, type III-B (801-07119) | LFT | 24 | $15.32 | $16.50 | $17.00 | $17.00 | $24.00 | $15.32 |
| 0096 | Sign, ground mounted, reset (802-91122) | EACH | 4 | $150.00 | $157.50 | $165.00 | $155.00 | $300.00 | $150.00 |
| 0097 | Conduit, steel, galvanized, 2 in. (805-01844) | LFT | 30 | $45.00 | $47.50 | $50.00 | $48.00 | $45.00 | $35.00 |
| 0098 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 91 | $1.50 | $2.00 | $1.65 | $2.00 | $1.50 | $0.75 |
| 0099 | Signal cable, detector lead-in, copper, 2C/16 gauge (805-78510) | LFT | 5 | $2.00 | $2.50 | $2.20 | $2.50 | $2.00 | $5.00 |
| 0100 | Signal detector housing (805-78785) | EACH | 1 | $3,000.00 | $3,150.00 | $8,250.00 | $3,200.00 | $3,000.00 | $2,500.00 |
| 0101 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 80 | $15.50 | $16.50 | $17.00 | $17.00 | $15.50 | $15.00 |
| 0102 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 995 | $0.71 | $1.00 | $0.78 | $1.00 | $4.57 | $0.71 |
| 0103 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 505 | $0.71 | $1.00 | $0.78 | $1.00 | $4.57 | $0.71 |
| 0104 | Grooving for pavement markings (808-12032) | LFT | 756 | $1.36 | $1.50 | $1.50 | $1.50 | $1.00 | $1.36 |
| 0105 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 109 | $0.93 | $1.00 | $1.00 | $1.00 | $4.57 | $0.93 |
| 0106 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 4 | $1.00 | $55.00 | $400.00 | $65.00 | $400.00 | $5.38 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 2, 2026. Compiled by Mirage Metrics.