INDOT contract B-44484-A bid tabulation
BRIDGE DECK REPLACEMENT AND SMALL STRUCTURE PIPE LINING. Let by Indiana DOT on July 8, 2026, Wayne, Greenfield. 4 bids received; low bid $1,909,729 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 100
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $1,909,729 | Low |
| 2 | Milestone Contractors LP | $1,983,610 | +4.0% |
| 3 | Beaty Construction Inc | $2,010,600 | +5.0% |
| 4 | Duncan Robertson Inc | $2,405,677 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Milestone Contractors LP | 3. Beaty Construction Inc | 4. Duncan Robertson Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,200 | $22,500 | $12,000 | $15,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $152,778 | $99,000 | $95,000 | $115,000 |
| 0011 | Clearing and grubbing (201-01015) | LS | 1 | $2,690.43 | $6,500.00 | $6,000.00 | $22,500 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $19,097 | $19,000 | $3,000.00 | $22,500 |
| 0013 | Structures and obstructions, remove (202-01000) | LS | 1 | $546.19 | $9,800.00 | $6,000.00 | $22,500 |
| 0014 | Pavement removal (202-02240) | SYS | 127 | $109.99 | $55.00 | $61.00 | $60.00 |
| 0015 | Paved side ditch, remove (202-02272) | LFT | 180 | $17.68 | $10.00 | $21.50 | $15.00 |
| 0016 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $192,475 | $125,236 | $150,000 | $275,000 |
| 0017 | Curb and gutter turnout, remove (202-92953) | SYS | 47 | $23.30 | $14.00 | $21.00 | $15.00 |
| 0018 | Fence, farm field, remove (202-99187) | LFT | 188 | $7.00 | $7.50 | $10.00 | $7.70 |
| 0019 | Excavation, common (203-02000) | CYS | 385 | $80.01 | $85.00 | $39.00 | $70.00 |
| 0020 | Borrow (203-02070) | CYS | 60 | $0.01 | $4.00 | $35.00 | $50.00 |
| 0021 | Pump around (205-11626) | EACH | 1 | $22,887 | $29,000 | $22,000 | $17,500 |
| 0022 | Stormwater management budget (205-12108) | DOL | 13,465 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0023 | Stormwater management implementation (205-12616) | LS | 1 | $6,252.43 | $5,000.00 | $6,800.00 | $20,000 |
| 0024 | Excavation, wet (206-51220) | CYS | 94 | $131.36 | $95.00 | $250.00 | $100.00 |
| 0025 | Subgrade treatment, type IC (207-09935) | SYS | 846 | $34.16 | $60.00 | $36.00 | $45.00 |
| 0026 | Aggregate for end bent backfill (211-06467) | CYS | 52 | $216.22 | $185.00 | $134.00 | $110.00 |
| 0027 | Structure backfill, type 2 (211-09265) | CYS | 174 | $113.56 | $135.00 | $130.00 | $110.00 |
| 0028 | Flowable backfill, removable (213-09270) | CYS | 20 | $458.18 | $340.00 | $360.00 | $300.00 |
| 0029 | Geotextile for pavement, type 2B (214-12239) | SYS | 822 | $2.98 | $7.00 | $8.00 | $4.00 |
| 0030 | Subbase for PCCP (302-06464) | CYS | 74 | $138.18 | $200.00 | $147.00 | $125.00 |
| 0031 | Compacted aggregate, no. 53 (303-01180) | TON | 380 | $78.00 | $57.00 | $66.00 | $65.00 |
| 0032 | HMA patching, partial depth, type B (304-12624) | TON | 3 | $1,497.65 | $713.00 | $180.00 | $198.00 |
| 0033 | Milling, transition (306-08043) | SYS | 534 | $14.33 | $8.00 | $13.00 | $15.00 |
| 0034 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 82 | $177.00 | $250.00 | $180.00 | $198.00 |
| 0035 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 62 | $180.21 | $320.00 | $180.00 | $198.00 |
| 0036 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 272 | $124.67 | $160.00 | $180.00 | $198.00 |
| 0037 | Joint adhesive (401-11526) | LFT | 720 | $0.90 | $2.50 | $1.00 | $1.10 |
| 0038 | Asphalt for tack coat (406-05521) | SYS | 1,814 | $0.01 | $0.50 | $0.50 | $0.55 |
| 0039 | Terminal joint, type HMA (503-12477) | LFT | 96 | $383.59 | $375.00 | $367.00 | $425.00 |
| 0040 | Guardrail, remove (601-02241) | LFT | 520 | $5.00 | $5.20 | $0.10 | $5.50 |
| 0041 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 38 | $22.00 | $23.00 | $22.00 | $24.00 |
| 0042 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,275.00 | $3,450.00 | $3,500.00 | $3,602.00 |
| 0043 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,975.00 | $3,125.00 | $2,500.00 | $3,272.00 |
| 0044 | Barrier delineator (602-06729) | EACH | 12 | $54.49 | $32.00 | $18.00 | $25.00 |
| 0045 | Fence, farm field, 47 in. (603-06040) | LFT | 290 | $18.00 | $19.00 | $26.00 | $20.00 |
| 0046 | Temporary fence (603-97461) | LFT | 108 | $19.00 | $20.00 | $17.00 | $21.00 |
| 0047 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 292 | $172.04 | $175.00 | $174.00 | $275.00 |
| 0048 | Monument, type B (615-06505) | EACH | 2 | $1,075.00 | $1,150.00 | $1,500.00 | $1,182.00 |
| 0049 | Riprap, class 1 (616-05688) | TON | 92 | $124.59 | $210.00 | $88.00 | $100.00 |
| 0050 | Riprap, revetment (616-06405) | TON | 174 | $108.24 | $160.00 | $99.00 | $55.00 |
| 0051 | Geotextile for riprap, type 1A (616-12246) | SYS | 212 | $2.54 | $11.00 | $5.00 | $2.50 |
| 0052 | Geotextile for riprap, type 2B (616-12249) | SYS | 166 | $8.05 | $18.00 | $7.00 | $4.00 |
| 0053 | Inspection hole (616-93772) | EACH | 4 | $1,315.89 | $850.00 | $115.00 | $500.00 |
| 0054 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $25,000 | $17,900 | $25,000 | $22,000 |
| 0055 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $450.00 | $1,050.00 | $450.00 | $1,100.00 |
| 0056 | Clean steel bridge, top flanges, type QP-2, bridge no. 1 (619-12506) | LS | 1 | $19,000 | $19,000 | $19,000 | $16,500 |
| 0057 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $6,900.00 | $10,500 | $6,900.00 | $11,000 |
| 0058 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $1,000.00 | $262.00 | $250.00 | $275.00 |
| 0059 | Mulched seeding, type R (621-06559) | SYS | 1,572 | $2.00 | $5.00 | $4.75 | $5.25 |
| 0060 | Water (621-06567) | KGAL | 2 | $0.01 | $0.25 | $0.10 | $0.22 |
| 0061 | Topsoil (621-06570) | CYS | 3 | $1,083.99 | $425.00 | $525.00 | $150.00 |
| 0062 | Sodding (621-06574) | SYS | 95 | $50.00 | $52.50 | $50.00 | $55.00 |
| 0063 | Field office, type C (628-09403) | MOS | 12 | $3,400.00 | $4,000.00 | $4,500.00 | $2,500.00 |
| 0064 | Computer system equipment (628-11976) | EACH | 1 | $1,089.80 | $100.00 | $1,200.00 | $1,000.00 |
| 0065 | Concrete, A, substructure (702-51005) | CYS | 17.40 | $3,806.76 | $2,975.00 | $2,600.00 | $2,750.00 |
| 0066 | Concrete, B, footings (702-51015) | CYS | 19.40 | $1,530.31 | $1,650.00 | $800.00 | $1,250.00 |
| 0067 | Field drilled hole in concrete (702-51863) | EACH | 574 | $41.53 | $16.00 | $29.00 | $15.00 |
| 0068 | Concrete, C, substructure (702-92857) | CYS | 13 | $3,093.52 | $2,450.00 | $1,700.00 | $2,250.00 |
| 0069 | Reinforcing bars (703-06028) | LBS | 3,380 | $1.93 | $1.60 | $1.57 | $2.00 |
| 0070 | Reinforcing bars, epoxy coated (703-06029) | LBS | 81,685 | $1.46 | $1.70 | $1.53 | $2.00 |
| 0071 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 52 | $59.15 | $50.00 | $38.00 | $65.00 |
| 0072 | Concrete, C, superstructure (704-51002) | CYS | 224 | $1,128.18 | $1,425.00 | $1,280.00 | $1,650.00 |
| 0073 | Railing, concrete type FC (706-11600) | CYS | 29.70 | $600.00 | $775.00 | $740.00 | $1,250.00 |
| 0074 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $1,550.00 | $3,050.00 | $1,800.00 | $3,250.00 |
| 0075 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $4,578.10 | $6,300.00 | $2,500.00 | $6,000.00 |
| 0076 | Surface seal , CV 001-089- 71.85 (709-51821) | LS | 1 | $939.80 | $3,150.00 | $800.00 | $1,600.00 |
| 0077 | Patching concrete structures , bridge no. 1 (710-09158) | SFT | 200 | $80.00 | $11.00 | $80.00 | $100.00 |
| 0078 | Drilled hole (711-51864) | EACH | 42 | $100.00 | $40.00 | $92.00 | $50.00 |
| 0079 | Jacking and supporting steel beams , bridge no. 1 (711-95291) | LS | 1 | $8,415.80 | $22,500 | $22,000 | $35,000 |
| 0080 | Stud shear connectors , bridge no. 1 (711-96800) | EACH | 1,974 | $4.19 | $4.50 | $6.00 | $4.60 |
| 0081 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 150 | $16.87 | $28.00 | $15.00 | $15.00 |
| 0082 | Geotextile for underdrains, type 1A (718-12305) | SYS | 104 | $2.01 | $16.00 | $4.00 | $2.00 |
| 0083 | Longitudinal grooving (722-12732) | SYS | 1,112 | $4.08 | $3.75 | $4.00 | $6.00 |
| 0084 | Pipe liner, cured-in- place, min. area 30.1 SFT (725-12054) | LFT | 163 | $1,864.40 | $2,020.00 | $2,600.00 | $2,750.00 |
| 0085 | Bearing assembly, elastomeric (726-92406) | EACH | 14 | $1,527.20 | $2,100.00 | $1,700.00 | $3,000.00 |
| 0086 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 1 | $100.00 | $162.00 | $100.00 | $88.00 |
| 0087 | Epoxy injection, crack preparation (727-90308) | LFT | 30 | $80.38 | $131.00 | $80.38 | $104.00 |
| 0088 | Epoxy injection, furnishing equipment , bridge no. 1 (727-93560) | LS | 1 | $2,500.00 | $1,015.00 | $2,500.00 | $1,005.00 |
| 0089 | Road closure sign assembly (801-04308) | EACH | 8 | $396.24 | $267.00 | $254.00 | $280.00 |
| 0090 | Detour route marker assembly (801-06625) | EACH | 22 | $110.36 | $160.00 | $152.00 | $167.00 |
| 0091 | Construction sign, type A (801-06640) | EACH | 26 | $213.94 | $220.00 | $209.00 | $230.00 |
| 0092 | Construction sign, type B (801-06645) | EACH | 10 | $152.15 | $111.00 | $106.00 | $116.00 |
| 0093 | Maintaining traffic (801-06775) | LS | 1 | $8,856.66 | $17,500 | $93,166 | $50,000 |
| 0094 | Barricade, type III-A (801-07118) | LFT | 120 | $11.28 | $16.00 | $15.25 | $17.00 |
| 0095 | Barricade, type III-B (801-07119) | LFT | 48 | $11.28 | $16.00 | $15.25 | $17.00 |
| 0096 | Reference post (802-04893) | EACH | 1 | $350.00 | $368.00 | $500.00 | $385.00 |
| 0097 | Sign, sheet, and supports, remove (802-07059) | EACH | 5 | $125.00 | $131.00 | $63.00 | $137.00 |
| 0098 | Sign, ground mounted, reset (802-91122) | EACH | 3 | $375.00 | $400.00 | $300.00 | $412.00 |
| 0099 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 786 | $1.50 | $1.00 | $0.88 | $0.97 |
| 0100 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 786 | $1.50 | $1.00 | $0.88 | $0.97 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.