INDOT contract B-44483-A bid tabulation
BRIDGE REPLACEMENT AND THIN DECK OVERLAY. Let by Indiana DOT on October 7, 2026, Rush, Shelby, Greenfield. 6 bids received; low bid $1,179,781 by Duncan Robertson Inc.
- Owner
- Indiana DOT
- Letting
- 07 OCT 2026
- Pay items
- 85
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Duncan Robertson Inc | $1,179,781 | Low |
| 2 | Milestone Contractors LP | $1,281,800 | +9.0% |
| 3 | Force Construction Co Inc | $1,427,446 | +21% |
| 4 | Dave O'Mara Contractor Inc | $1,471,000 | +25% |
| 5 | American Contracting & Services Inc | $1,526,315 | +29% |
| 6 | Paul H Rohe Company Inc | $1,550,073 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Duncan Robertson Inc | 2. Milestone Contractors LP | 3. Force Construction Co Inc | 4. Dave O'Mara Contractor Inc | 5. American Contracting & Services Inc | 6. Paul H Rohe Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,000 | $14,000 | $9,833.00 | $13,500 | $15,000 | $12,200 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 4 | $1,500.00 | $855.00 | $898.00 | $800.00 | $950.00 | $1,130.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $55,000 | $64,000 | $71,000 | $73,550 | $76,316 | $104,140 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $20,000 | $35,700 | $22,660 | $29,420 | $30,526 | $38,940 |
| 0013 | Regulated asbestos containing materials, remove (202-03135) | SFT | 6 | $10.00 | $250.00 | $1,030.00 | $9,000.00 | $250.00 | $1,720.00 |
| 0014 | Regulated materials, dispose, type C (202-05547) | DRUM | 1 | $250.00 | $1,500.00 | $515.00 | $100.00 | $2,500.00 | $900.00 |
| 0015 | Regulated materials, transport, type C (202-05557) | DRUM | 1 | $250.00 | $1,500.00 | $1,030.00 | $100.00 | $2,500.00 | $900.00 |
| 0016 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $100,000 | $60,391 | $51,730 | $100.00 | $75,000 | $85,430 |
| 0017 | Pipe, remove (202-96133) | LFT | 31 | $20.00 | $40.00 | $71.00 | $115.00 | $65.00 | $280.00 |
| 0018 | Excavation, common (203-02000) | CYS | 535 | $40.00 | $55.00 | $58.00 | $44.00 | $175.00 | $126.00 |
| 0019 | Pump around (205-11626) | EACH | 1 | $5,000.00 | $31,500 | $12,980 | $19,000 | $25,000 | $15,000 |
| 0020 | Stormwater management budget (205-12108) | DOL | 14,214 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0021 | Stormwater management implementation (205-12616) | LS | 1 | $15,000 | $7,500.00 | $8,456.00 | $32,500 | $15,000 | $3,000.00 |
| 0022 | Excavation, foundation, unclassified (206-51230) | CYS | 243 | $40.00 | $64.00 | $43.00 | $60.00 | $70.00 | $80.00 |
| 0023 | Subgrade treatment, type II (207-08264) | SYS | 78 | $20.00 | $39.00 | $41.00 | $22.50 | $35.00 | $92.00 |
| 0024 | Subgrade treatment, type IC (207-09935) | SYS | 1,416 | $30.00 | $50.00 | $44.00 | $42.00 | $44.00 | $50.00 |
| 0025 | Structure backfill, type 2 (211-09265) | CYS | 9 | $125.00 | $82.00 | $138.00 | $128.00 | $120.00 | $220.00 |
| 0026 | Flowable backfill, removable (213-09270) | CYS | 82 | $300.00 | $220.00 | $280.00 | $400.00 | $250.00 | $300.00 |
| 0027 | Geogrid, type IB (214-11796) | SYS | 1,416 | $3.00 | $4.00 | $2.80 | $5.00 | $4.00 | $3.50 |
| 0028 | Geotextile for pavement, type 2B (214-12239) | SYS | 193 | $4.00 | $9.50 | $8.10 | $5.00 | $13.00 | $5.70 |
| 0029 | Subbase for PCCP (302-06464) | CYS | 49 | $150.00 | $180.00 | $157.00 | $120.00 | $145.00 | $210.00 |
| 0030 | Compacted aggregate, no. 53 (303-01180) | TON | 318 | $55.00 | $66.00 | $58.00 | $42.00 | $45.00 | $62.00 |
| 0031 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 329 | $18.00 | $41.00 | $19.00 | $10.91 | $20.00 | $19.00 |
| 0032 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 134 | $137.00 | $195.00 | $129.00 | $125.00 | $125.00 | $205.00 |
| 0033 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 180 | $137.00 | $125.00 | $129.00 | $125.00 | $125.00 | $150.00 |
| 0034 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 573 | $137.00 | $109.00 | $129.00 | $125.00 | $125.00 | $132.00 |
| 0035 | Joint adhesive (401-11526) | LFT | 1,989 | $0.11 | $2.00 | $0.10 | $0.10 | $0.10 | $1.25 |
| 0036 | Asphalt for tack coat (406-05521) | SYS | 4,290 | $0.11 | $0.30 | $0.10 | $0.10 | $0.10 | $0.45 |
| 0037 | Terminal joint, retrofit polymer modified asphalt (503-12480) | SFT | 173 | $95.00 | $85.95 | $89.00 | $86.00 | $225.00 | $85.95 |
| 0038 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $3,540.00 | $3,220.00 | $3,315.00 | $3,500.00 | $3,220.00 | $3,220.00 |
| 0039 | Guardrail terminal system, W-beam, curved, type 1 (601-01700) | EACH | 1 | $3,190.00 | $2,900.00 | $2,986.00 | $3,000.00 | $2,900.00 | $2,900.00 |
| 0040 | Guardrail, remove (601-02241) | LFT | 561 | $2.20 | $2.00 | $2.10 | $2.00 | $2.00 | $2.00 |
| 0041 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 88 | $25.00 | $23.00 | $24.00 | $24.00 | $23.00 | $23.00 |
| 0042 | Guardrail transition, MGS without curb (601-12292) | EACH | 3 | $3,410.00 | $3,100.00 | $3,192.00 | $3,400.00 | $3,100.00 | $3,100.00 |
| 0043 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,190.00 | $2,900.00 | $2,986.00 | $3,200.00 | $2,900.00 | $2,900.00 |
| 0044 | Barrier delineator (602-06729) | EACH | 4 | $30.00 | $29.00 | $60.00 | $25.00 | $100.00 | $29.00 |
| 0045 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 193 | $255.00 | $282.00 | $214.00 | $275.00 | $225.00 | $258.00 |
| 0046 | HMA for approaches, type B (610-07487) | TON | 22 | $137.00 | $110.00 | $129.00 | $125.00 | $125.00 | $300.00 |
| 0047 | Mailbox assembly, reset, double (611-08233) | EACH | 1 | $650.00 | $590.00 | $607.00 | $600.00 | $590.00 | $590.00 |
| 0048 | Right-of-way marker (615-06490) | EACH | 12 | $192.00 | $175.00 | $180.00 | $185.00 | $175.00 | $175.00 |
| 0049 | Monument, type B (615-06505) | EACH | 2 | $1,094.00 | $994.00 | $1,023.00 | $1,000.00 | $994.00 | $994.00 |
| 0050 | Benchmark post (615-06530) | EACH | 1 | $394.00 | $500.00 | $772.00 | $650.00 | $625.00 | $1,020.00 |
| 0051 | Riprap, class 1 (616-05688) | TON | 306 | $65.00 | $112.00 | $100.00 | $120.00 | $120.00 | $90.00 |
| 0052 | Riprap, revetment (616-06405) | TON | 115 | $60.00 | $118.00 | $85.00 | $100.00 | $115.00 | $135.00 |
| 0053 | Geotextile for riprap, type 1A (616-12246) | SYS | 598 | $3.50 | $3.50 | $4.20 | $5.00 | $7.00 | $4.50 |
| 0054 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $1,017.00 | $900.00 | $927.00 | $1,000.00 | $900.00 | $500.00 |
| 0055 | Mulched seeding, type R (621-06559) | SYS | 1,482 | $3.25 | $2.11 | $2.20 | $3.50 | $2.11 | $5.00 |
| 0056 | Sodding (621-06574) | SYS | 11 | $192.00 | $297.00 | $306.00 | $180.00 | $297.00 | $275.00 |
| 0057 | Field office, type C (628-09403) | MOS | 9 | $2,750.00 | $4,400.00 | $3,327.00 | $2,200.00 | $4,500.00 | $3,850.00 |
| 0058 | Dynamic pile load test (701-06011) | EACH | 2 | $2,750.00 | $3,400.00 | $3,258.00 | $4,200.00 | $6,000.00 | $1,250.00 |
| 0059 | Test pile, dynamic, production (701-09557) | LFT | 124 | $72.00 | $63.50 | $103.00 | $160.00 | $135.00 | $245.00 |
| 0060 | Test pile, dynamic, restrike (701-09559) | EACH | 2 | $2,000.00 | $3,400.00 | $3,258.00 | $3,200.00 | $6,000.00 | $3,875.00 |
| 0061 | Pile, steel pipe, 0.250 in., diameter 14 in. (701-09662) | LFT | 728 | $72.00 | $116.75 | $103.00 | $128.00 | $125.00 | $155.00 |
| 0062 | Conical pile tip, 14 in. (701-09679) | EACH | 16 | $1,000.00 | $480.00 | $416.00 | $525.00 | $1,000.00 | $870.00 |
| 0063 | Reinforcing bars, epoxy coated (703-06029) | LBS | 58,477 | $1.50 | $1.80 | $1.50 | $1.60 | $1.85 | $1.65 |
| 0064 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 43 | $60.00 | $53.00 | $55.00 | $60.00 | $60.00 | $190.00 |
| 0065 | Concrete, C, superstructure (704-51002) | CYS | 179.20 | $1,250.00 | $1,260.00 | $1,344.00 | $1,700.00 | $1,600.00 | $1,685.00 |
| 0066 | Railing, concrete type FC (706-11600) | CYS | 4.70 | $1,750.00 | $1,877.00 | $1,933.00 | $4,500.00 | $2,600.00 | $1,877.00 |
| 0067 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $2,250.00 | $2,100.00 | $2,162.00 | $6,500.00 | $3,000.00 | $2,100.00 |
| 0068 | Surface seal , structure no. 1 (709-51821) | LS | 1 | $2,800.00 | $0.01 | $1.00 | $2,900.00 | $1,100.00 | $2,677.76 |
| 0069 | Surface seal , structure no. 2 (709-51821) | LS | 1 | $2,800.00 | $2,586.59 | $2,663.00 | $2,900.00 | $2,900.00 | $2,586.59 |
| 0070 | Safety metal end section, 4:1, diameter 24 in. (715-03476) | EACH | 1 | $3,750.00 | $1,800.00 | $2,305.00 | $2,600.00 | $3,500.00 | $4,725.00 |
| 0071 | Pipe, type 3, circular, diameter 24 in. (715-05173) | LFT | 58 | $110.00 | $74.00 | $119.00 | $130.00 | $120.00 | $172.00 |
| 0072 | Pipe end section, diameter 24 in. (715-46020) | EACH | 1 | $800.00 | $1,125.00 | $3,159.00 | $1,500.00 | $1,130.00 | $5,085.00 |
| 0073 | Longitudinal grooving (722-12732) | SYS | 326 | $12.00 | $11.75 | $10.00 | $8.00 | $15.00 | $8.44 |
| 0074 | Bridge deck patching, partial depth (722-51852) | SFT | 329 | $2.75 | $2.50 | $2.60 | $2.75 | $40.00 | $2.50 |
| 0075 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 731 | $54.00 | $42.90 | $44.00 | $52.00 | $75.00 | $42.90 |
| 0076 | Road closure sign assembly (801-04308) | EACH | 9 | $165.00 | $255.00 | $263.00 | $500.00 | $255.00 | $150.00 |
| 0077 | Detour route marker assembly (801-06625) | EACH | 54 | $94.00 | $143.00 | $147.00 | $300.00 | $143.00 | $85.00 |
| 0078 | Construction sign, type A (801-06640) | EACH | 22 | $192.00 | $189.00 | $195.00 | $350.00 | $189.00 | $175.00 |
| 0079 | Maintaining traffic (801-06775) | LS | 1 | $30,000 | $9,000.00 | $237,000 | $80,143 | $20,000 | $19,540 |
| 0080 | Barricade, type III-A (801-07118) | LFT | 96 | $16.50 | $15.21 | $16.00 | $26.00 | $16.00 | $15.00 |
| 0081 | Barricade, type III-B (801-07119) | LFT | 96 | $16.50 | $15.21 | $16.00 | $26.00 | $16.00 | $15.00 |
| 0082 | Reference post (802-04893) | EACH | 1 | $500.00 | $358.00 | $369.00 | $375.00 | $358.00 | $358.00 |
| 0083 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 1,286 | $2.20 | $0.88 | $0.90 | $5.00 | $0.88 | $2.00 |
| 0084 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 416 | $2.20 | $0.88 | $0.90 | $5.00 | $0.88 | $2.00 |
| 0085 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 109 | $2.20 | $1.03 | $1.10 | $5.00 | $1.03 | $2.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.