INDOT contract B-43605-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on September 2, 2026, Lawrence, Vincennes. 9 bids received; low bid $2,392,561 by CLR Inc.
- Owner
- Indiana DOT
- Letting
- 02 SEP 2026
- Pay items
- 97
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | CLR Inc | $2,392,561 | Low |
| 2 | Ragle, Inc. | $2,549,353 | +7.0% |
| 3 | Force Construction Co Inc | $2,712,790 | +13% |
| 4 | Duncan Robertson Inc | $2,734,143 | +14% |
| 5 | American Contracting & Services Inc | $2,772,090 | +16% |
| 6 | Milestone Contractors LP | $2,807,416 | +17% |
| 7 | Pontem Contractors Inc | $2,897,007 | +21% |
| 8 | Rieth-Riley Construction Co., Inc. | $2,995,612 | +25% |
| 9 | E & B Paving LLC | $3,365,000 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. CLR Inc | 2. Ragle, Inc. | 3. Force Construction Co Inc | 4. Duncan Robertson Inc | 5. American Contracting & Services Inc | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $54,000 | $50,000 | $25,320 | $30,000 | $30,000 | $32,800 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $121,000 | $126,000 | $135,000 | $125,000 | $138,604 | $140,500 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $24,215 | $65,000 | $22,500 | $25,000 | $27,721 | $58,000 |
| 0011 | Excavation, common (203-02000) | CYS | 2,650 | $15.00 | $22.00 | $30.80 | $15.00 | $30.00 | $32.00 |
| 0012 | Excavation, rock (203-02010) | CYS | 45 | $269.00 | $80.00 | $269.00 | $200.00 | $200.00 | $175.00 |
| 0013 | Borrow (203-02070) | CYS | 5,405 | $9.00 | $0.01 | $32.00 | $25.00 | $35.00 | $22.00 |
| 0014 | Excavation, waterway (203-51223) | CYS | 975 | $11.00 | $45.00 | $21.00 | $30.00 | $40.00 | $32.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 40,817 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $15,000 | $12,190 | $40,000 | $30,000 | $14,000 |
| 0017 | SWQCP preparation (205-12618) | LS | 1 | $1,400.00 | $3,000.00 | $2,597.00 | $4,500.00 | $10,000 | $1,800.00 |
| 0018 | Excavation, X (206-51215) | CYS | 90 | $100.00 | $160.00 | $202.00 | $200.00 | $200.00 | $175.00 |
| 0019 | Excavation, foundation, unclassified (206-51230) | CYS | 75 | $83.00 | $70.00 | $122.00 | $200.00 | $130.00 | $175.00 |
| 0020 | Cofferdam (206-51235) | LS | 1 | $24,000 | $50,000 | $59,520 | $15,000 | $30,000 | $21,000 |
| 0021 | Subgrade treatment, type II (207-08264) | SYS | 246 | $22.00 | $28.00 | $37.00 | $18.00 | $35.00 | $22.00 |
| 0022 | Subgrade treatment, type IC (207-09935) | SYS | 1,340 | $33.00 | $26.00 | $39.00 | $35.00 | $40.00 | $32.00 |
| 0023 | Aggregate for end bent backfill (211-06467) | CYS | 60 | $80.00 | $115.00 | $116.00 | $135.00 | $150.00 | $140.00 |
| 0024 | Structure backfill, type 2 (211-09265) | CYS | 43 | $96.00 | $60.00 | $131.00 | $135.00 | $80.00 | $70.00 |
| 0025 | Geotextile for pavement, type 2A (214-12238) | SYS | 3,455 | $3.00 | $3.25 | $3.20 | $3.00 | $3.25 | $3.00 |
| 0026 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,340 | $6.00 | $3.50 | $4.90 | $4.00 | $5.00 | $4.00 |
| 0027 | Compacted aggregate, no. 5 (301-12232) | CYS | 843 | $47.00 | $55.00 | $66.00 | $70.00 | $60.00 | $104.00 |
| 0028 | Compacted aggregate, no. 53 (301-12234) | CYS | 517 | $57.00 | $90.00 | $73.00 | $25.00 | $90.00 | $95.00 |
| 0029 | Subbase for PCCP (302-06464) | CYS | 18 | $285.00 | $115.00 | $215.00 | $200.00 | $150.00 | $140.00 |
| 0030 | Compacted aggregate, no. 53 (303-01180) | TON | 82 | $125.00 | $55.00 | $53.00 | $65.00 | $65.00 | $70.00 |
| 0031 | Milling, transition (306-08043) | SYS | 140 | $15.00 | $30.00 | $35.00 | $35.00 | $45.00 | $41.00 |
| 0032 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 111 | $186.00 | $186.00 | $193.00 | $205.00 | $186.00 | $186.00 |
| 0033 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 197 | $120.00 | $120.00 | $125.00 | $132.00 | $120.00 | $120.00 |
| 0034 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 432 | $154.00 | $120.00 | $125.00 | $132.00 | $120.00 | $120.00 |
| 0035 | Joint adhesive (401-11526) | LFT | 1,140 | $1.30 | $1.30 | $1.40 | $1.40 | $1.30 | $1.30 |
| 0036 | Asphalt for tack coat (406-05520) | TON | 1 | $750.00 | $750.00 | $779.00 | $825.00 | $750.00 | $750.00 |
| 0037 | Terminal joint, type HMA (503-12477) | LFT | 42 | $584.00 | $435.00 | $508.00 | $400.00 | $1,340.00 | $700.00 |
| 0038 | Guardrail end treatment, type I (601-06037) | EACH | 4 | $1,225.00 | $1,225.00 | $1,273.00 | $1,350.00 | $1,230.00 | $1,225.00 |
| 0039 | Guardrail transition, type TGS-1 (601-06374) | EACH | 4 | $1,050.00 | $950.00 | $987.00 | $1,045.00 | $950.00 | $950.00 |
| 0040 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 38 | $40.00 | $22.00 | $23.00 | $24.00 | $22.00 | $22.00 |
| 0041 | Curb, HMA (605-05523) | LFT | 53 | $74.00 | $74.00 | $77.00 | $81.50 | $74.00 | $74.00 |
| 0042 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 86 | $357.00 | $230.00 | $303.00 | $350.00 | $280.00 | $410.00 |
| 0043 | HMA for approaches, type B (610-07487) | TON | 56 | $140.00 | $140.00 | $145.00 | $154.00 | $140.00 | $140.00 |
| 0044 | Monument, type B (615-06505) | EACH | 6 | $350.00 | $975.00 | $1,013.00 | $1,072.00 | $975.00 | $975.00 |
| 0045 | Benchmark post (615-06530) | EACH | 1 | $350.00 | $625.00 | $649.00 | $688.00 | $625.00 | $625.00 |
| 0046 | Riprap, class 1 (616-05688) | TON | 1,005 | $41.00 | $50.00 | $94.00 | $65.00 | $85.00 | $95.00 |
| 0047 | Riprap, revetment (616-06405) | TON | 132 | $78.00 | $70.00 | $100.00 | $60.00 | $70.00 | $95.00 |
| 0048 | Geotextile for riprap, type 2B (616-12249) | SYS | 1,154 | $4.00 | $3.75 | $3.80 | $3.50 | $6.00 | $4.25 |
| 0049 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $500.00 | $1,000.00 | $1,039.00 | $1,650.00 | $1,500.00 | $1,000.00 |
| 0050 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $500.00 | $300.00 | $312.00 | $5.50 | $5.00 | $300.00 |
| 0051 | Seed mixture, type R (621-06553) | LBS | 214 | $10.00 | $14.00 | $15.00 | $6.60 | $6.00 | $14.00 |
| 0052 | Mulching material (621-06565) | TON | 3 | $640.00 | $550.00 | $571.00 | $605.00 | $550.00 | $550.00 |
| 0053 | Water (621-06567) | KGAL | 2 | $100.00 | $0.01 | $0.01 | $0.11 | $0.10 | $0.01 |
| 0054 | Topsoil (621-06570) | CYS | 10 | $100.00 | $100.00 | $312.00 | $200.00 | $200.00 | $100.00 |
| 0055 | Sodding (621-06574) | SYS | 143 | $10.50 | $35.00 | $31.00 | $31.00 | $28.00 | $30.00 |
| 0056 | Seed mixture, floodplain , modified (621-12612) | LBS | 21 | $155.00 | $200.00 | $208.00 | $770.00 | $700.00 | $200.00 |
| 0057 | Plant, deciduous shrub, 18 in. to 24 in. (622-05639) | EACH | 46 | $35.00 | $95.00 | $99.00 | $121.00 | $110.00 | $95.00 |
| 0058 | Plant, deciduous tree, single stem, 1.25 in. or under (622-05648) | EACH | 91 | $190.00 | $100.00 | $104.00 | $138.00 | $125.00 | $100.00 |
| 0059 | Sign, 'DO not mow or spray' (622-52436) | EACH | 16 | $95.00 | $120.00 | $125.00 | $105.00 | $95.00 | $120.00 |
| 0060 | Sign, 'DO not disturb' (622-98200) | EACH | 16 | $95.00 | $120.00 | $125.00 | $105.00 | $95.00 | $120.00 |
| 0061 | Herbicide treatment (624-92647) | ACRE | 1 | $4,000.00 | $2,000.00 | $2,078.00 | $5,500.00 | $5,000.00 | $2,000.00 |
| 0062 | Field office, type C (628-09403) | MOS | 14 | $1,000.00 | $2,150.00 | $3,293.00 | $2,500.00 | $4,000.00 | $3,000.00 |
| 0063 | Computer system equipment (628-11976) | EACH | 1 | $100.00 | $1,000.00 | $826.00 | $750.00 | $1,000.00 | $750.00 |
| 0064 | Computer system (628-11977) | EACH | 1 | $100.00 | $1,000.00 | $1,029.00 | $750.00 | $3,000.00 | $3,250.00 |
| 0065 | Cored hole in rock, diameter 24 in. (701-02938) | LFT | 127 | $856.00 | $875.00 | $475.00 | $750.00 | $800.00 | $620.00 |
| 0066 | Pile shoe, HP 12 X 53 (701-09739) | EACH | 11 | $200.00 | $125.00 | $113.00 | $250.00 | $200.00 | $120.00 |
| 0067 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 241 | $125.00 | $135.00 | $121.00 | $112.00 | $220.00 | $150.00 |
| 0068 | Concrete, A, substructure (702-51005) | CYS | 53.90 | $1,625.00 | $2,000.00 | $1,947.00 | $1,750.00 | $1,200.00 | $1,730.00 |
| 0069 | Concrete, B, footings (702-51015) | CYS | 54.60 | $1,000.00 | $950.00 | $543.00 | $700.00 | $1,000.00 | $990.00 |
| 0070 | Concrete, C, substructure (702-92857) | CYS | 41.80 | $1,350.00 | $1,200.00 | $1,326.00 | $1,400.00 | $1,300.00 | $1,430.00 |
| 0071 | Reinforcing bars (703-06028) | LBS | 18,859 | $1.95 | $1.80 | $1.80 | $1.50 | $1.65 | $1.60 |
| 0072 | Reinforcing bars, epoxy coated (703-06029) | LBS | 95,315 | $1.99 | $1.90 | $1.50 | $1.50 | $1.80 | $1.70 |
| 0073 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 20 | $35.00 | $50.00 | $72.00 | $68.00 | $50.00 | $62.00 |
| 0074 | Concrete, C, superstructure (704-51002) | CYS | 192.80 | $1,350.00 | $1,750.00 | $1,282.00 | $1,750.00 | $1,500.00 | $1,900.00 |
| 0075 | Railing, steel type TS-1 (706-06344) | LFT | 431 | $81.00 | $75.00 | $72.00 | $80.00 | $69.00 | $85.00 |
| 0076 | Structural member, concrete, I-beam, 45 in. X 16 in. (707-05984) | LFT | 823 | $620.00 | $600.00 | $435.00 | $650.00 | $580.00 | $506.00 |
| 0077 | Pipe, type 4, circular, diameter 10 in. (715-05051) | LFT | 50 | $20.00 | $60.00 | $108.00 | $30.00 | $60.00 | $80.00 |
| 0078 | Pipe, type 3, circular, diameter 18 in. (715-05171) | LFT | 53 | $59.00 | $60.00 | $95.00 | $70.00 | $80.00 | $110.00 |
| 0079 | Pipe, type 3, circular, diameter 24 in. (715-05173) | LFT | 73 | $108.00 | $90.00 | $124.00 | $150.00 | $120.00 | $150.00 |
| 0080 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 136 | $22.50 | $13.50 | $37.00 | $15.00 | $25.00 | $40.00 |
| 0081 | Video inspection for pipe (715-09064) | LFT | 250 | $10.00 | $2.00 | $16.00 | $18.00 | $10.00 | $20.00 |
| 0082 | Pipe end section, diameter 18 in. (715-46010) | EACH | 2 | $635.00 | $900.00 | $1,799.00 | $500.00 | $850.00 | $1,600.00 |
| 0083 | Pipe end section, diameter 24 in. (715-46020) | EACH | 2 | $870.00 | $1,500.00 | $2,123.00 | $700.00 | $980.00 | $2,000.00 |
| 0084 | Geotextile for underdrains, type 2A (718-12307) | SYS | 145 | $4.50 | $5.00 | $5.30 | $3.00 | $15.00 | $6.50 |
| 0085 | Inlet, type F7 (720-45035) | EACH | 1 | $3,115.00 | $4,000.00 | $2,605.00 | $3,500.00 | $7,000.00 | $5,000.00 |
| 0086 | Longitudinal grooving (722-12732) | SYS | 557 | $8.00 | $7.00 | $5.90 | $10.00 | $9.00 | $5.40 |
| 0087 | Bearing assembly, elastomeric (726-92406) | EACH | 24 | $2,310.00 | $1,850.00 | $1,590.00 | $1,900.00 | $2,100.00 | $1,600.00 |
| 0088 | Road closure sign assembly (801-04308) | EACH | 2 | $295.00 | $230.00 | $239.00 | $250.00 | $250.00 | $300.00 |
| 0089 | Detour route marker assembly (801-06625) | EACH | 26 | $105.00 | $135.00 | $140.00 | $148.00 | $100.00 | $120.00 |
| 0090 | Construction sign, type A (801-06640) | EACH | 12 | $144.00 | $185.00 | $192.00 | $204.00 | $210.00 | $190.00 |
| 0091 | Construction sign, type B (801-06645) | EACH | 3 | $112.00 | $100.00 | $104.00 | $110.00 | $185.00 | $110.00 |
| 0092 | Maintaining traffic (801-06775) | LS | 1 | $6,612.00 | $10,000 | $270,468 | $50,000 | $12,000 | $14,715 |
| 0093 | Barricade, type III-A (801-07118) | LFT | 48 | $16.00 | $16.42 | $17.00 | $18.00 | $20.00 | $15.00 |
| 0094 | Barricade, type III-B (801-07119) | LFT | 36 | $16.00 | $16.42 | $17.00 | $18.00 | $22.00 | $15.00 |
| 0095 | Line, multi-component, solid, white, 4 in. (808-10033) | LFT | 1,650 | $0.58 | $0.75 | $0.80 | $0.82 | $1.00 | $0.90 |
| 0096 | Line, multi-component, solid, yellow, 4 in. (808-10034) | LFT | 1,650 | $0.58 | $0.75 | $0.80 | $0.82 | $1.00 | $0.90 |
| 0097 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $60,000 | $80,000 | $67,550 | $150,000 | $55,000 | $168,988 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 2, 2026. Compiled by Mirage Metrics.