INDOT contract B-45531-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on July 8, 2026, Adams, Fort Wayne. 4 bids received; low bid $1,384,133 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 70
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $1,384,133 | Low |
| 2 | Miller Bros Construction Inc | $1,391,949 | +1.0% |
| 3 | Duncan Robertson Inc | $1,448,565 | +5.0% |
| 4 | R L McCoy Inc | $1,479,881 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Miller Bros Construction Inc | 3. Duncan Robertson Inc | 4. R L McCoy Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $20,500 | $7,110.00 | $17,500 | $18,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $69,207 | $69,597 | $72,500 | $73,900 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $13,841 | $9,499.96 | $27,500 | $14,700 |
| 0011 | Pavement removal (202-02240) | SYS | 143 | $57.00 | $55.25 | $60.00 | $50.00 |
| 0012 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $71,842 | $137,877 | $125,000 | $245,000 |
| 0013 | Excavation, common (203-02000) | CYS | 590 | $79.00 | $66.79 | $60.00 | $80.00 |
| 0014 | Stormwater management budget (205-12108) | DOL | 10,750 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $1,000.00 | $9,100.00 | $17,500 | $4,000.00 |
| 0016 | Excavation, foundation, unclassified (206-51230) | CYS | 90 | $177.00 | $130.00 | $275.00 | $105.00 |
| 0017 | Subgrade treatment, type II (207-08264) | SYS | 17 | $27.00 | $51.21 | $18.00 | $85.00 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 194 | $36.00 | $31.41 | $45.00 | $90.00 |
| 0019 | Aggregate for end bent backfill (211-06467) | CYS | 22 | $155.00 | $254.64 | $95.00 | $135.00 |
| 0020 | Geotextile for pavement, type 2B (214-12239) | SYS | 202 | $10.00 | $11.68 | $4.00 | $20.00 |
| 0021 | Compacted aggregate, no. 2 (301-12231) | CYS | 14 | $185.00 | $259.80 | $85.00 | $130.00 |
| 0022 | Compacted aggregate, no. 53 (301-12234) | CYS | 19 | $210.00 | $233.94 | $85.00 | $150.00 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 52 | $219.00 | $183.37 | $125.00 | $120.00 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 179 | $59.00 | $53.38 | $60.00 | $42.00 |
| 0025 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 467 | $8.00 | $5.98 | $12.00 | $7.00 |
| 0026 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 53 | $140.00 | $140.00 | $379.00 | $140.00 |
| 0027 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 23 | $165.00 | $165.00 | $413.00 | $165.00 |
| 0028 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 55 | $105.00 | $105.00 | $225.00 | $105.00 |
| 0029 | Joint adhesive (401-11526) | LFT | 362 | $0.78 | $0.78 | $1.10 | $0.78 |
| 0030 | Asphalt for tack coat (406-05521) | SYS | 1,440 | $0.39 | $0.39 | $0.30 | $0.39 |
| 0031 | Guardrail transition, type TGS-1 , modified (601-06374) | EACH | 4 | $750.00 | $975.00 | $825.00 | $750.00 |
| 0032 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,975.00 | $2,900.00 | $3,272.00 | $2,975.00 |
| 0033 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 25 | $25.00 | $38.00 | $27.00 | $25.00 |
| 0034 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 196 | $175.00 | $232.16 | $240.00 | $220.00 |
| 0035 | HMA for approaches, type B (610-07487) | TON | 3 | $450.00 | $450.00 | $1,056.00 | $450.00 |
| 0036 | Monument, type B (615-06505) | EACH | 2 | $1,025.00 | $997.00 | $1,127.00 | $1,025.00 |
| 0037 | Benchmark post (615-06530) | EACH | 1 | $1,150.00 | $1,150.00 | $50.00 | $1,100.00 |
| 0038 | Riprap, revetment (616-06405) | TON | 227 | $50.00 | $77.41 | $60.00 | $120.00 |
| 0039 | Geotextile for riprap, type 1A (616-12246) | SYS | 622 | $6.00 | $6.37 | $3.00 | $5.00 |
| 0040 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $550.00 | $550.00 | $605.00 | $550.00 |
| 0041 | Mulched seeding, type R (621-06559) | SYS | 235 | $6.98 | $6.98 | $7.70 | $6.98 |
| 0042 | Field office, type C (628-09403) | MOS | 6 | $2,800.00 | $4,542.46 | $2,500.00 | $4,000.00 |
| 0043 | Dynamic pile load test (701-06011) | EACH | 4 | $5,200.00 | $3,780.22 | $5,750.00 | $8,000.00 |
| 0044 | Test pile, dynamic, production (701-09557) | LFT | 261 | $98.00 | $120.04 | $65.00 | $51.00 |
| 0045 | Test pile, dynamic, restrike (701-09559) | EACH | 4 | $4,700.00 | $3,780.22 | $4,400.00 | $5,500.00 |
| 0046 | Pile shoe, HP 12 X 53 (701-09739) | EACH | 24 | $290.00 | $160.37 | $350.00 | $250.00 |
| 0047 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 1,077 | $144.00 | $169.09 | $65.00 | $98.00 |
| 0048 | Concrete, A, substructure (702-51005) | CYS | 26.70 | $2,500.00 | $1,584.45 | $2,050.00 | $2,725.00 |
| 0049 | Concrete, C, substructure (702-92857) | CYS | 28.60 | $1,700.00 | $1,699.72 | $1,650.00 | $1,300.00 |
| 0050 | Reinforcing bars (703-06028) | LBS | 5,250 | $3.75 | $1.59 | $1.75 | $2.50 |
| 0051 | Reinforcing bars, epoxy coated (703-06029) | LBS | 46,040 | $1.80 | $1.69 | $1.75 | $1.50 |
| 0052 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 32 | $48.00 | $64.68 | $65.00 | $56.00 |
| 0053 | Concrete, C, superstructure (704-51002) | CYS | 119.40 | $1,670.00 | $1,109.19 | $1,350.00 | $1,600.00 |
| 0054 | Railing, steel type TS-1 (706-06344) | LFT | 208 | $100.00 | $89.00 | $79.00 | $72.00 |
| 0055 | Structural member, concrete, box beam, 12 in. X 48 in. (707-09029) | LFT | 525 | $499.00 | $566.08 | $625.00 | $487.00 |
| 0056 | Welded steel wire reinforcement (708-51814) | SFT | 162 | $55.00 | $14.06 | $5.00 | $26.00 |
| 0057 | Surface seal (709-51821) | LS | 1 | $700.00 | $3,410.89 | $4,000.00 | $500.00 |
| 0058 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 122 | $31.00 | $12.57 | $15.00 | $26.00 |
| 0059 | Geotextile for underdrains, type 2A (718-12307) | SYS | 75 | $16.00 | $14.02 | $3.00 | $12.00 |
| 0060 | Longitudinal grooving (722-12732) | SYS | 766 | $4.20 | $4.24 | $7.00 | $6.00 |
| 0061 | Bearing assembly, elastomeric (726-92406) | EACH | 40 | $350.00 | $305.65 | $500.00 | $200.00 |
| 0062 | Road closure sign assembly (801-04308) | EACH | 4 | $325.00 | $248.00 | $273.00 | $248.00 |
| 0063 | Detour route marker assembly (801-06625) | EACH | 13 | $175.00 | $153.00 | $168.00 | $153.00 |
| 0064 | Construction sign, type A (801-06640) | EACH | 6 | $250.00 | $202.00 | $222.00 | $202.00 |
| 0065 | Construction sign, type B (801-06645) | EACH | 1 | $150.00 | $110.00 | $121.00 | $110.00 |
| 0066 | Maintaining traffic (801-06775) | LS | 1 | $4,426.17 | $2,537.91 | $50,000 | $1,000.00 |
| 0067 | Barricade, type III-A (801-07118) | LFT | 72 | $20.00 | $15.88 | $17.50 | $15.88 |
| 0068 | Barricade, type III-B (801-07119) | LFT | 48 | $20.00 | $15.88 | $17.50 | $15.88 |
| 0069 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 800 | $1.00 | $0.62 | $0.68 | $0.62 |
| 0070 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 800 | $1.00 | $0.62 | $0.68 | $0.62 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.