INDOT contract B-43610-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on December 10, 2025, Wabash, Fort Wayne. 8 bids received; low bid $2,625,854 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 10 DEC 2025
- Pay items
- 83
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $2,625,854 | Low |
| 2 | Beaty Construction Inc | $2,650,264 | +1.0% |
| 3 | Pontem Contractors Inc | $2,801,759 | +7.0% |
| 4 | E & B Paving LLC | $2,835,500 | +8.0% |
| 5 | R L McCoy Inc | $3,081,194 | +17% |
| 6 | Duncan Robertson Inc | $3,264,241 | +24% |
| 7 | Icc Group Inc | $3,436,000 | +31% |
| 8 | Rieth-Riley Construction Co., Inc. | $4,473,853 | +70% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Beaty Construction Inc | 3. Pontem Contractors Inc | 4. E & B Paving LLC | 5. R L McCoy Inc | 6. Duncan Robertson Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $33,000 | $18,033 | $25,000 | $40,000 | $26,000 | $17,500 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $129,274 | $125,000 | $139,000 | $280,000 | $154,000 | $160,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $39,000 | $44,175 | $55,500 | $56,000 | $61,600 | $65,000 |
| 0011 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $116,150 | $67,875 | $180,981 | $397,626 | $300,000 | $175,000 |
| 0012 | Excavation, common (203-02000) | CYS | 270 | $163.95 | $65.00 | $251.86 | $200.00 | $50.00 | $35.00 |
| 0013 | Borrow (203-02070) | CYS | 7,735 | $14.27 | $20.00 | $25.76 | $20.00 | $29.00 | $30.00 |
| 0014 | Excavation, waterway (203-51223) | CYS | 135 | $111.00 | $40.00 | $71.74 | $80.00 | $80.00 | $25.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 27,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $3,600.00 | $12,500 | $50,270 | $50,000 | $20,000 | $30,000 |
| 0017 | SWQCP preparation (205-12618) | LS | 1 | $3,600.00 | $4,000.00 | $5,745.59 | $5,000.00 | $3,200.00 | $2,500.00 |
| 0018 | Excavation, foundation, unclassified (206-51230) | CYS | 415 | $75.00 | $35.00 | $62.20 | $80.00 | $75.00 | $25.00 |
| 0019 | Subgrade treatment, type II (207-08264) | SYS | 54 | $15.65 | $44.00 | $32.87 | $15.65 | $40.00 | $20.00 |
| 0020 | Subgrade treatment, type III (207-08266) | SYS | 1,385 | $12.00 | $2.50 | $4.18 | $12.00 | $6.00 | $8.00 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 2,591 | $25.98 | $30.00 | $36.30 | $25.98 | $44.00 | $40.00 |
| 0022 | B borrow (211-02050) | CYS | 460 | $88.00 | $55.00 | $95.70 | $20.00 | $60.00 | $90.00 |
| 0023 | Aggregate for end bent backfill (211-06467) | CYS | 46 | $160.00 | $175.00 | $92.44 | $100.00 | $200.00 | $145.00 |
| 0024 | Structure backfill, type 3 (211-09266) | CYS | 1,005 | $80.00 | $55.00 | $91.03 | $25.00 | $110.00 | $120.00 |
| 0025 | Geotextile for pavement, type 2B (214-12239) | SYS | 2,263 | $5.00 | $5.00 | $5.50 | $5.00 | $8.00 | $5.50 |
| 0026 | Compacted aggregate, no. 53 (301-12234) | CYS | 137 | $57.50 | $90.00 | $102.91 | $57.50 | $112.00 | $110.00 |
| 0027 | Subbase for PCCP (302-06464) | CYS | 64 | $175.00 | $155.00 | $104.72 | $120.00 | $200.00 | $190.00 |
| 0028 | Compacted aggregate, no. 53 (303-01180) | TON | 490 | $40.75 | $60.00 | $53.13 | $40.75 | $55.00 | $75.00 |
| 0029 | Milling, transition (306-08043) | SYS | 223 | $20.00 | $45.00 | $36.50 | $20.00 | $18.00 | $45.00 |
| 0030 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 171 | $220.00 | $150.00 | $242.00 | $220.00 | $150.00 | $165.00 |
| 0031 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 285 | $125.00 | $125.00 | $137.50 | $125.00 | $125.00 | $137.00 |
| 0032 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 697 | $90.00 | $100.00 | $99.00 | $90.00 | $98.00 | $108.00 |
| 0033 | Joint adhesive (401-11526) | LFT | 3,425 | $0.50 | $0.35 | $0.55 | $0.50 | $0.32 | $0.35 |
| 0034 | HMA for temporary pavement, type B (402-10084) | TON | 169 | $250.00 | $170.00 | $307.01 | $200.00 | $240.00 | $220.00 |
| 0035 | Asphalt for tack coat (406-05521) | SYS | 4,129 | $2.60 | $0.55 | $2.86 | $2.60 | $0.53 | $0.58 |
| 0036 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 50 | $20.00 | $23.00 | $25.30 | $20.00 | $20.00 | $22.00 |
| 0037 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,325.00 | $3,525.00 | $3,877.50 | $3,325.00 | $3,325.00 | $3,657.00 |
| 0038 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,950.00 | $2,500.00 | $275.00 | $2,950.00 | $2,950.00 | $3,245.00 |
| 0039 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 238 | $185.00 | $180.00 | $194.48 | $150.00 | $275.00 | $300.00 |
| 0040 | HMA for approaches, type B (610-07487) | TON | 5 | $350.00 | $450.00 | $385.00 | $350.00 | $450.00 | $495.00 |
| 0041 | Monument, type B (615-06505) | EACH | 2 | $1,050.00 | $1,925.00 | $2,117.50 | $1,050.00 | $1,050.00 | $1,155.00 |
| 0042 | Benchmark post (615-06530) | EACH | 1 | $2,137.57 | $2,000.00 | $1,100.00 | $800.00 | $800.00 | $1,100.00 |
| 0043 | Riprap, revetment (616-06405) | TON | 803 | $56.00 | $77.25 | $87.67 | $85.00 | $80.00 | $65.00 |
| 0044 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,067 | $3.96 | $3.50 | $4.51 | $5.00 | $4.00 | $4.00 |
| 0045 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $425.00 | $425.00 | $467.50 | $500.00 | $425.00 | $467.00 |
| 0046 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $800.00 | $800.00 | $880.00 | $1,450.00 | $800.00 | $880.00 |
| 0047 | Mulched seeding, type R (621-06559) | SYS | 3,616 | $2.45 | $2.50 | $2.70 | $3.25 | $2.45 | $2.70 |
| 0048 | Mulching material (621-06565) | TON | 2 | $510.00 | $510.00 | $561.00 | $900.00 | $510.00 | $561.00 |
| 0049 | Sodding (621-06574) | SYS | 172 | $12.95 | $13.00 | $28.64 | $29.00 | $12.95 | $14.00 |
| 0050 | Seed mixture, floodplain (621-12612) | LBS | 3 | $438.00 | $440.00 | $481.80 | $390.00 | $438.00 | $481.00 |
| 0051 | Field office, type C (628-09403) | MOS | 18 | $4,659.95 | $2,800.00 | $3,339.14 | $2,500.00 | $2,850.00 | $2,500.00 |
| 0052 | Computer system equipment (628-11976) | EACH | 1 | $1,007.48 | $850.00 | $824.93 | $500.00 | $850.00 | $1,000.00 |
| 0053 | Test pile, dynamic, production (701-09557) | LFT | 175 | $150.00 | $125.00 | $137.24 | $75.00 | $107.00 | $75.00 |
| 0054 | Test pile, dynamic, restrike (701-09559) | EACH | 2 | $6,200.00 | $6,000.00 | $5,104.50 | $5,000.00 | $8,000.00 | $10,000 |
| 0055 | Conical pile tip, 14 in. (701-09679) | EACH | 16 | $513.00 | $500.00 | $419.91 | $600.00 | $450.00 | $650.00 |
| 0056 | Pile, steel pipe, 0.5 in., diameter 14 in. (701-09826) | LFT | 1,085 | $117.00 | $125.00 | $90.68 | $72.00 | $112.00 | $75.00 |
| 0057 | Concrete, C, substructure (702-92857) | CYS | 41 | $1,200.00 | $1,650.00 | $856.13 | $1,500.00 | $1,200.00 | $1,500.00 |
| 0058 | Reinforcing bars, epoxy coated (703-06029) | LBS | 70,626 | $1.90 | $1.55 | $1.50 | $1.50 | $1.45 | $1.75 |
| 0059 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 468 | $53.00 | $58.00 | $53.63 | $20.00 | $62.00 | $65.00 |
| 0060 | Concrete, C, superstructure (704-51002) | CYS | 148.90 | $1,500.00 | $1,600.00 | $1,200.03 | $1,320.00 | $1,500.00 | $1,600.00 |
| 0061 | Railing, concrete type FC (706-11600) | CYS | 17.80 | $1,100.00 | $1,850.00 | $1,672.00 | $1,520.00 | $1,520.00 | $1,100.00 |
| 0062 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $3,000.00 | $4,800.00 | $2,750.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0063 | Structural member, concrete, bulb-T beam, 36 in. X 49 in. (707-09865) | LFT | 458 | $610.00 | $643.00 | $630.84 | $750.00 | $710.00 | $1,100.00 |
| 0064 | Surface seal (709-51821) | LS | 1 | $1,200.00 | $1.00 | $5,500.00 | $1.00 | $500.00 | $2,200.00 |
| 0065 | Temporary causeway (713-04331) | LS | 1 | $110,000 | $177,000 | $70,370 | $75,000 | $120,000 | $250,000 |
| 0066 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 120 | $171.00 | $16.75 | $24.57 | $10.00 | $38.00 | $15.00 |
| 0067 | Geotextile for underdrains, type 2B (718-12308) | SYS | 106 | $11.00 | $9.00 | $12.24 | $5.00 | $11.00 | $4.00 |
| 0068 | Longitudinal grooving (722-12732) | SYS | 633 | $1.00 | $10.00 | $19.38 | $4.00 | $16.00 | $8.00 |
| 0069 | Temporary wire-facing (735-10241) | SFT | 3,376 | $40.00 | $24.15 | $23.42 | $10.00 | $30.00 | $25.00 |
| 0070 | Temporary wall erection (735-10242) | SFT | 3,376 | $12.00 | $15.00 | $16.72 | $7.00 | $23.00 | $25.00 |
| 0071 | Temporary pavement marking, 4 in. (801-06203) | LFT | 4,200 | $0.40 | $1.00 | $1.10 | $0.20 | $0.40 | $0.44 |
| 0072 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 4,100 | $1.35 | $1.00 | $1.76 | $0.80 | $1.35 | $1.50 |
| 0073 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $10.00 | $16.00 | $17.60 | $11.04 | $10.00 | $11.00 |
| 0074 | Construction sign, type A (801-06640) | EACH | 10 | $200.00 | $200.00 | $220.00 | $221.00 | $200.00 | $220.00 |
| 0075 | Construction sign, type B (801-06645) | EACH | 2 | $100.00 | $140.73 | $132.00 | $111.00 | $100.00 | $110.00 |
| 0076 | Maintaining traffic (801-06775) | LS | 1 | $9,500.00 | $48,000 | $30,540 | $50,000 | $8,300.00 | $40,000 |
| 0077 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $6,800.00 | $8,650.00 | $9,515.00 | $3,000.00 | $6,800.00 | $9,020.00 |
| 0078 | Barricade, type III-A (801-07118) | LFT | 72 | $20.00 | $17.00 | $18.70 | $25.00 | $20.00 | $22.00 |
| 0079 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 690 | $62.00 | $100.00 | $45.74 | $40.00 | $100.00 | $60.00 |
| 0080 | Fixed temporary signal (801-12082) | LS | 1 | $83,510 | $104,000 | $118,226 | $65,000 | $104,000 | $96,500 |
| 0081 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 2 | $500.00 | $1,325.00 | $1,444.30 | $800.00 | $500.00 | $550.00 |
| 0082 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 2,000 | $0.60 | $1.00 | $1.10 | $0.38 | $0.60 | $0.66 |
| 0083 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 2,000 | $0.60 | $1.00 | $1.10 | $0.38 | $0.60 | $0.66 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.