INDOT contract B-44941-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on February 11, 2026, Vigo, Crawfordsville. 6 bids received; low bid $470,571 by CLR Inc.
- Owner
- Indiana DOT
- Letting
- 11 FEB 2026
- Pay items
- 45
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | CLR Inc | $470,571 | Low |
| 2 | William Charles Construction Company | $510,568 | +8.0% |
| 3 | Morphey Construction Inc. | $520,000 | +11% |
| 4 | 5 Star Company Inc | $564,978 | +20% |
| 5 | Yarberry Companies Inc | $608,551 | +29% |
| 6 | Rieth-Riley Construction Co., Inc. | $1,190,174 | +153% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. CLR Inc | 2. William Charles Construction Company | 3. Morphey Construction Inc. | 4. 5 Star Company Inc | 5. Yarberry Companies Inc | 6. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $26,000 | $10,000 | $5,000.00 | $35,000 | $35,000 | $6,500.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $23,500 | $60,000 | $26,000 | $84,000 | $30,000 | $81,850 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $9,400.00 | $30,000 | $10,400 | $20,000 | $35,000 | $39,313 |
| 0010 | Debris, remove, structure no. 3 (201-90788) | LS | 1 | $500.00 | $15,000 | $10,000 | $6,500.00 | $10,000 | $47,482 |
| 0011 | Excavation, waterway (203-51223) | CYS | 161 | $175.00 | $110.00 | $150.00 | $195.00 | $150.00 | $323.76 |
| 0012 | Pump around (205-11626) | EACH | 1 | $5,000.00 | $30,000 | $10,000 | $5,500.00 | $20,000 | $19,821 |
| 0013 | Stormwater management budget (205-12108) | DOL | 17,402 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0014 | Stormwater management implementation (205-12616) | LS | 1 | $1,800.00 | $15,000 | $2,100.00 | $5,000.00 | $15,000 | $20,036 |
| 0015 | Cofferdam (206-51235) | LS | 1 | $28,000 | $30,000 | $30,000 | $45,000 | $35,000 | $65,104 |
| 0016 | Compacted aggregate, no. 53 (303-01180) | TON | 8 | $225.00 | $300.00 | $200.00 | $90.00 | $200.00 | $403.88 |
| 0017 | Guardrail, reset (601-06035) | LFT | 180 | $30.00 | $30.00 | $30.00 | $50.00 | $55.00 | $30.00 |
| 0018 | Grout for riprap (616-02281) | CYS | 41 | $655.00 | $550.00 | $500.00 | $290.00 | $450.00 | $403.19 |
| 0019 | Riprap, revetment (616-06405) | TON | 1,322 | $140.00 | $97.00 | $140.00 | $100.00 | $160.00 | $479.47 |
| 0020 | Geotextile for riprap, type 1A (616-12246) | SYS | 514 | $10.00 | $5.00 | $5.00 | $4.00 | $12.00 | $6.90 |
| 0021 | Geotextile for riprap, type 3 (616-12251) | SYS | 1,183 | $6.00 | $4.00 | $5.00 | $5.00 | $10.00 | $5.90 |
| 0022 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $300.00 | $800.00 | $800.00 | $1,250.00 | $750.00 | $800.00 |
| 0023 | Mulched seeding, type U (621-06560) | SYS | 2,449 | $1.90 | $2.25 | $9.00 | $3.00 | $2.00 | $2.25 |
| 0024 | Field office, type C (628-09403) | MOS | 10 | $1,000.00 | $3,360.00 | $3,200.00 | $1,500.00 | $2,500.00 | $5,948.24 |
| 0025 | Computer system equipment (628-11976) | EACH | 1 | $100.00 | $2,500.00 | $800.00 | $500.00 | $2,000.00 | $1,201.66 |
| 0026 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 40 | $37.00 | $80.00 | $150.00 | $50.00 | $50.00 | $86.35 |
| 0027 | Construction sign, type C (801-03290) | EACH | 4 | $200.00 | $250.00 | $200.00 | $210.00 | $920.00 | $250.00 |
| 0028 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 1,320 | $2.00 | $1.60 | $2.00 | $2.20 | $3.00 | $1.60 |
| 0029 | Temporary pavement message marking, removable, lane indication arrow (801-06211) | EACH | 3 | $100.00 | $160.00 | $100.00 | $105.00 | $120.00 | $160.00 |
| 0030 | Temporary pavement message marking, removable, (only) (801-06212) | EACH | 2 | $200.00 | $190.00 | $200.00 | $205.00 | $230.00 | $190.00 |
| 0031 | Construction sign, type A (801-06640) | EACH | 37 | $150.00 | $180.00 | $150.00 | $155.00 | $175.00 | $180.00 |
| 0032 | Construction sign, type B (801-06645) | EACH | 6 | $75.00 | $110.00 | $75.00 | $80.00 | $100.00 | $110.00 |
| 0033 | Flashing arrow sign (801-06710) | DAY | 14 | $200.00 | $20.00 | $30.00 | $35.00 | $50.00 | $20.00 |
| 0034 | Maintaining traffic (801-06775) | LS | 1 | $39,916 | $30,000 | $67,536 | $85,500 | $55,000 | $27,032 |
| 0035 | Barricade, type III-A (801-07118) | LFT | 24 | $12.00 | $16.00 | $10.00 | $15.00 | $13.00 | $16.00 |
| 0036 | Temporary traffic barrier, type 2 (801-08401) | LFT | 120 | $85.00 | $75.00 | $100.00 | $145.00 | $50.00 | $117.30 |
| 0037 | Truck mounted attenuator (801-12042) | DAY | 14 | $750.00 | $700.00 | $200.00 | $210.00 | $240.00 | $2,448.41 |
| 0038 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 8 | $250.00 | $820.00 | $250.00 | $260.00 | $300.00 | $820.00 |
| 0039 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 2 | $590.00 | $1,050.00 | $500.00 | $520.00 | $575.00 | $1,050.00 |
| 0040 | Temporary pavement marking, removable, 10 in. (801-12956) | LFT | 550 | $3.50 | $3.00 | $3.50 | $4.00 | $6.00 | $3.00 |
| 0041 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $700.00 | $600.00 | $600.00 | $550.00 | $400.00 | $600.00 |
| 0042 | Line, remove (808-06716) | LFT | 165 | $2.35 | $1.00 | $2.00 | $2.10 | $3.00 | $1.00 |
| 0043 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 200 | $3.00 | $1.00 | $3.00 | $3.10 | $5.00 | $1.00 |
| 0044 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 200 | $3.00 | $1.00 | $3.00 | $3.10 | $5.00 | $1.00 |
| 0045 | Line, thermoplastic, broken, white, 6 in. (808-96075) | LFT | 215 | $3.00 | $1.50 | $3.00 | $3.10 | $5.00 | $1.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 11, 2026. Compiled by Mirage Metrics.