INDOT contract R-45169-A bid tabulation
INTERSECTION IMPROVEMENT, MEDIAN U-TURN. Let by Indiana DOT on July 8, 2026, Hancock, Greenfield. 5 bids received; low bid $3,600,349 by Paul H Rohe Company Inc.
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 115
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Paul H Rohe Company Inc | $3,600,349 | Low |
| 2 | Milestone Contractors LP | $3,874,000 | +8.0% |
| 3 | Dave O'Mara Contractor Inc | $3,972,000 | +10% |
| 4 | Rieth-Riley Construction Co., Inc. | $4,137,622 | +15% |
| 5 | Morphey Construction Inc. | $4,878,151 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Paul H Rohe Company Inc | 2. Milestone Contractors LP | 3. Dave O'Mara Contractor Inc | 4. Rieth-Riley Construction Co., Inc. | 5. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $23,100 | $24,315 | $30,000 | $26,600 | $50,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 20 | $1,030.00 | $680.00 | $887.00 | $1,704.04 | $1,000.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Mobilization and demobilization (110-01001) | LS | 1 | $102,820 | $55,757 | $183,600 | $129,854 | $245,000 |
| 0013 | Clearing right-of-way (201-52370) | LS | 1 | $38,553 | $5,000.00 | $73,440 | $34,532 | $98,000 |
| 0014 | Conduit, remove (202-01845) | LFT | 1,505 | $5.20 | $4.45 | $4.25 | $5.20 | $8.00 |
| 0015 | Pavement removal (202-02240) | SYS | 2,455 | $19.00 | $40.00 | $24.00 | $34.67 | $40.00 |
| 0016 | Catch basin, remove (202-02928) | EACH | 3 | $2,980.00 | $1,100.00 | $337.00 | $985.00 | $1,500.00 |
| 0017 | Sign, remove (202-74035) | EACH | 6 | $161.00 | $160.00 | $60.00 | $161.00 | $100.00 |
| 0018 | Detector housing, remove (202-90277) | EACH | 6 | $775.00 | $775.00 | $500.00 | $775.00 | $50.00 |
| 0019 | Manhole, remove (202-93047) | EACH | 3 | $3,800.00 | $715.00 | $836.00 | $1,325.36 | $1,500.00 |
| 0020 | Concrete foundation, remove (202-96022) | EACH | 8 | $2,300.00 | $730.00 | $700.00 | $1,800.00 | $2,000.00 |
| 0021 | Pipe, remove (202-96133) | LFT | 170 | $89.00 | $50.00 | $59.00 | $63.94 | $50.00 |
| 0022 | Excavation, common (203-02000) | CYS | 2,365 | $34.00 | $70.00 | $42.00 | $66.48 | $100.00 |
| 0023 | Pump around (205-11626) | EACH | 1 | $48,900 | $27,300 | $13,627 | $19,550 | $50,000 |
| 0024 | Stormwater management budget (205-12108) | DOL | 44,725 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0025 | Stormwater management implementation (205-12616) | LS | 1 | $11,100 | $11,000 | $23,275 | $16,563 | $5,000.00 |
| 0026 | SWQCP preparation (205-12618) | LS | 1 | $2,350.00 | $2,000.00 | $3,000.00 | $2,900.00 | $5,000.00 |
| 0027 | Subgrade treatment, type II (207-08264) | SYS | 573 | $32.00 | $38.00 | $28.00 | $79.15 | $40.00 |
| 0028 | Subgrade treatment, type ibc (207-12635) | SYS | 9,757 | $15.30 | $26.00 | $17.50 | $12.89 | $20.00 |
| 0029 | Structure backfill, type 1 (211-09264) | CYS | 735 | $76.00 | $86.00 | $77.00 | $103.02 | $60.00 |
| 0030 | Structure backfill, type 5 (211-09268) | CYS | 133 | $246.00 | $333.00 | $231.00 | $326.34 | $250.00 |
| 0032 | Geogrid, type IB (214-11796) | SYS | 20 | $15.00 | $24.00 | $16.00 | $30.80 | $30.00 |
| 0033 | Chemical modification, soils, cement (215-12637) | SYS | 9,757 | $10.35 | $12.00 | $17.50 | $12.89 | $15.00 |
| 0034 | Compacted aggregate, no. 8 (301-12233) | CYS | 148 | $180.00 | $137.00 | $157.00 | $242.12 | $150.00 |
| 0035 | Compacted aggregate, no. 53 (301-12234) | CYS | 14 | $190.00 | $267.00 | $108.00 | $121.89 | $160.00 |
| 0036 | Compacted aggregate, no. 73 (303-07449) | TON | 697 | $54.00 | $62.00 | $74.00 | $77.41 | $100.00 |
| 0037 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 5,679 | $4.00 | $5.00 | $3.92 | $5.14 | $5.00 |
| 0038 | Milling, profile (306-11872) | SYS | 3,881 | $6.00 | $7.00 | $7.35 | $8.46 | $5.00 |
| 0039 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 1,807 | $160.00 | $157.00 | $115.00 | $192.61 | $150.00 |
| 0040 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 2,123 | $122.00 | $129.00 | $104.00 | $174.18 | $125.00 |
| 0041 | QC/QA-HMA, 3, 58H, base, 25.0 MM (401-000050) | TON | 4,301 | $115.00 | $125.00 | $87.00 | $159.23 | $100.00 |
| 0042 | Joint adhesive (401-11526) | LFT | 19,800 | $0.55 | $1.00 | $1.00 | $0.79 | $1.00 |
| 0043 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 9,900 | $4.50 | $5.00 | $4.64 | $2.75 | $2.75 |
| 0045 | Asphalt for tack coat (406-05520) | TON | 11 | $850.00 | $890.00 | $522.00 | $0.01 | $0.01 |
| 0046 | PCCP, 8 in. (502-06999) | SYS | 80 | $103.25 | $130.00 | $241.00 | $154.87 | $220.00 |
| 0047 | Guardrail, remove (601-02241) | LFT | 413 | $4.00 | $4.20 | $5.00 | $4.00 | $5.00 |
| 0048 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 50 | $21.00 | $22.00 | $64.00 | $21.00 | $58.00 |
| 0049 | Guardrail transition, MGS with curb (601-12291) | EACH | 1 | $3,325.00 | $3,500.00 | $3,850.00 | $3,325.00 | $3,500.00 |
| 0050 | Guardrail end treatment, type MS (601-94690) | EACH | 1 | $5,375.00 | $5,650.00 | $6,000.00 | $5,375.00 | $5,500.00 |
| 0051 | Curb, island concrete (605-02493) | SYS | 535 | $48.79 | $77.00 | $114.00 | $164.63 | $200.00 |
| 0052 | Curb and gutter, concrete, type B (605-06145) | LFT | 1,373 | $49.15 | $55.00 | $51.00 | $62.25 | $100.00 |
| 0053 | Center curb, concrete, type B (605-06205) | LFT | 803 | $72.26 | $65.50 | $49.00 | $95.57 | $120.00 |
| 0054 | HMA for approaches, type B (610-07487) | TON | 31 | $200.00 | $251.00 | $480.00 | $299.46 | $400.00 |
| 0055 | Mailbox assembly, reset, single (611-08232) | EACH | 2 | $200.00 | $210.00 | $275.00 | $200.00 | $250.00 |
| 0056 | Right-of-way marker (615-06490) | EACH | 9 | $165.00 | $173.00 | $198.00 | $165.00 | $180.00 |
| 0057 | Monument, type C (615-06510) | EACH | 2 | $500.00 | $527.00 | $1,025.00 | $500.00 | $1,025.00 |
| 0058 | Riprap, revetment (616-06405) | TON | 176 | $85.00 | $118.00 | $78.00 | $168.15 | $200.00 |
| 0059 | Geotextile for riprap, type 1A (616-12246) | SYS | 534 | $5.00 | $6.00 | $6.00 | $6.32 | $7.00 |
| 0060 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $500.00 | $275.00 | $750.00 | $250.00 | $250.00 |
| 0061 | Mulched seeding, type R (621-06559) | SYS | 6,048 | $1.25 | $1.00 | $0.85 | $0.75 | $10.00 |
| 0062 | Sodding (621-06574) | SYS | 350 | $13.50 | $8.50 | $14.00 | $8.00 | $20.00 |
| 0063 | Field office, type C (628-09403) | MOS | 12 | $3,650.00 | $3,790.00 | $2,483.00 | $5,119.62 | $4,000.00 |
| 0064 | Topsoil processing and distribution (629-000149) | SYS | 6,397 | $9.60 | $7.75 | $6.25 | $7.46 | $10.00 |
| 0065 | Topsoil amendment budget (629-000150) | DOL | 12,794 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0066 | Structure, reinforced concrete, box sections, 8 FT X 3 FT (714-11096) | LFT | 215 | $1,290.00 | $1,319.00 | $1,158.00 | $1,274.71 | $1,000.00 |
| 0067 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 305 | $145.00 | $140.00 | $132.00 | $186.25 | $100.00 |
| 0069 | Inlet, type N12 (720-45065) | EACH | 2 | $9,580.00 | $7,750.00 | $5,525.00 | $8,322.52 | $125.00 |
| 0071 | Catch basin, type E7, modified (720-45335) | EACH | 1 | $6,260.00 | $3,410.00 | $3,291.00 | $5,434.13 | $9,000.00 |
| 0072 | Road closure sign assembly (801-04308) | EACH | 4 | $259.00 | $206.00 | $285.00 | $196.00 | $200.00 |
| 0073 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 11,988 | $1.94 | $1.50 | $2.00 | $1.50 | $1.50 |
| 0074 | Detour route marker assembly (801-06625) | EACH | 30 | $155.00 | $130.00 | $170.00 | $123.00 | $123.00 |
| 0075 | Construction sign, type A (801-06640) | EACH | 87 | $209.00 | $168.50 | $229.00 | $160.00 | $160.00 |
| 0076 | Construction sign, type B (801-06645) | EACH | 32 | $105.00 | $75.00 | $115.00 | $71.00 | $71.00 |
| 0077 | Flashing arrow sign (801-06710) | DAY | 180 | $15.00 | $12.00 | $15.00 | $11.00 | $11.00 |
| 0078 | Maintaining traffic (801-06775) | LS | 1 | $71,110 | $194,453 | $569,580 | $46,449 | $684,049 |
| 0079 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $8,600.00 | $9,050.00 | $10,179 | $8,600.00 | $8,600.00 |
| 0080 | Barricade, type III-A (801-07118) | LFT | 72 | $15.85 | $10.50 | $17.00 | $10.00 | $10.00 |
| 0081 | Temporary traffic barrier, type 2 (801-08401) | LFT | 3,862 | $52.00 | $43.00 | $38.55 | $47.60 | $30.00 |
| 0082 | Law enforcement officer (801-12324) | HRS | 200 | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 0083 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 189 | $25.50 | $26.00 | $30.00 | $25.50 | $17.00 |
| 0084 | Sign post, square, type 2, reinforced anchor base (802-05702) | LFT | 452 | $26.00 | $27.00 | $30.00 | $26.00 | $15.50 |
| 0085 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 109 | $37.50 | $38.00 | $30.00 | $37.50 | $25.00 |
| 0086 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 347 | $37.50 | $38.00 | $30.00 | $37.50 | $23.00 |
| 0087 | Sign, sheet, with legend, 0.125 in. thickness (802-09842) | SFT | 36 | $34.00 | $34.00 | $35.00 | $34.00 | $21.00 |
| 0088 | Sign, ground mounted, reset (802-91122) | EACH | 10 | $476.00 | $475.00 | $300.00 | $476.00 | $305.00 |
| 0089 | Delineator post, flexible, type I (804-11920) | EACH | 6 | $212.65 | $527.00 | $175.00 | $500.00 | $65.00 |
| 0090 | Delineator post, flexible, type II (804-11921) | EACH | 12 | $212.65 | $632.00 | $175.00 | $600.00 | $125.00 |
| 0091 | Traffic signal equipment, remove (805-01300) | EACH | 1 | $3,220.00 | $3,300.00 | $3,750.00 | $3,220.00 | $4,000.00 |
| 0092 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 450 | $13.00 | $14.00 | $36.00 | $13.00 | $41.00 |
| 0093 | Handhole, lighting (807-02191) | EACH | 11 | $1,720.00 | $1,750.00 | $1,980.00 | $1,720.00 | $2,750.00 |
| 0094 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 3,221 | $14.50 | $15.00 | $25.00 | $14.50 | $43.00 |
| 0095 | Luminaire, low lumen roadway (807-12202) | EACH | 16 | $734.00 | $737.00 | $700.00 | $734.00 | $1,500.00 |
| 0096 | Lighting foundation, conventional pole, concrete, with grounding (807-12791) | EACH | 16 | $2,290.00 | $2,350.00 | $2,750.00 | $2,290.00 | $2,000.00 |
| 0097 | Light pole, 40 FT E.M.H., 15 FT mast arm, breakaway base (807-85762) | EACH | 16 | $5,100.00 | $5,210.00 | $5,445.00 | $5,100.00 | $6,000.00 |
| 0098 | Line, remove (808-06716) | LFT | 4,205 | $0.61 | $0.50 | $0.70 | $0.50 | $1.00 |
| 0099 | Retro-reflectivity testing (808-09381) | LS | 1 | $3,000.00 | $4,158.00 | $3,000.00 | $3,950.00 | $3,950.00 |
| 0100 | Line, thermoplastic, dotted, white, 6 in. (808-11650) | LFT | 468 | $1.08 | $2.25 | $1.20 | $1.97 | $2.00 |
| 0101 | Transverse marking, thermoplastic, yield line, white, 27 in. (808-11698) | LFT | 468 | $18.57 | $20.00 | $21.00 | $19.03 | $20.00 |
| 0102 | Grooving for pavement markings (808-12032) | LFT | 12,698 | $0.72 | $0.75 | $0.80 | $0.60 | $1.00 |
| 0103 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 7,377 | $0.91 | $1.10 | $1.00 | $1.00 | $1.00 |
| 0104 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 4,005 | $0.91 | $1.10 | $1.00 | $1.00 | $1.00 |
| 0105 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 34 | $6.91 | $4.00 | $7.50 | $3.85 | $4.00 |
| 0106 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 37 | $12.87 | $8.50 | $14.00 | $7.79 | $8.00 |
| 0107 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 14 | $214.00 | $264.00 | $235.00 | $251.00 | $251.00 |
| 0108 | Pavement message marking, thermoplastic, 'only' (808-75325) | EACH | 2 | $249.00 | $235.00 | $275.00 | $223.00 | $223.00 |
| 0109 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 27 | $17.54 | $50.50 | $7.50 | $10.90 | $35.00 |
| 0110 | Snowplowable raised pavement marker (808-75998) | EACH | 41 | $52.43 | $74.00 | $57.00 | $70.00 | $70.00 |
| 0111 | Line, thermoplastic, broken, white, 6 in. (808-96075) | LFT | 848 | $1.35 | $2.10 | $1.50 | $1.97 | $2.00 |
| 0112 | HMA for temporary pavement, type C (402-10086) | TON | 239 | $190.00 | $270.00 | $132.00 | $318.70 | $218.00 |
| 0113 | Cost adjustment for acceleration (105-09357) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0114 | Borrow (203-02070) | CYS | 1,260 | $100.00 | $37.00 | $64.00 | $0.01 | $80.00 |
| 0115 | Subgrade treatment, type IC (207-09935) | SYS | 65 | $90.00 | $164.00 | $32.00 | $63.62 | $150.00 |
| 0116 | Curb and gutter, concrete, type C (605-06150) | LFT | 172 | $52.66 | $68.00 | $51.00 | $84.26 | $80.00 |
| 0117 | Pipe, type 1, circular, diameter 12 in. (715-05118) | LFT | 100 | $125.00 | $121.00 | $99.00 | $141.82 | $200.00 |
| 0118 | Video inspection for pipe (715-09064) | LFT | 405 | $5.32 | $13.00 | $10.00 | $4.84 | $10.00 |
| 0119 | Service point, type II (807-86810) | EACH | 1 | $9,770.00 | $10,000 | $10,500 | $9,770.00 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.