INDOT contract R-43761-A bid tabulation
SLIDE CORRECTION. Let by Indiana DOT on July 8, 2026, Floyd, Seymour. 6 bids received; low bid $1,097,342 by Mac Construction & Excavating Inc.
- Owner
- Indiana DOT
- Letting
- 08 JUL 2026
- Pay items
- 61
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mac Construction & Excavating Inc | $1,097,342 | Low |
| 2 | Ragle, Inc. | $1,263,937 | +15% |
| 3 | Beaty Construction Inc | $1,275,315 | +16% |
| 4 | Milestone Contractors LP | $1,427,874 | +30% |
| 5 | E & B Paving LLC | $1,440,850 | +31% |
| 6 | Force Construction Co Inc | $1,673,146 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mac Construction & Excavating Inc | 2. Ragle, Inc. | 3. Beaty Construction Inc | 4. Milestone Contractors LP | 5. E & B Paving LLC | 6. Force Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $18,000 | $22,000 | $22,500 | $30,000 | $30,000 | $15,520 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $52,000 | $62,750 | $63,766 | $72,500 | $70,000 | $83,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $44,163 | $25,000 | $25,506 | $74,685 | $28,000 | $31,560 |
| 0011 | Pavement removal (202-02240) | SYS | 467 | $11.50 | $26.00 | $45.00 | $65.00 | $39.00 | $41.00 |
| 0012 | Curb and gutter, remove (202-02279) | LFT | 610 | $6.25 | $8.00 | $15.00 | $25.00 | $7.00 | $18.00 |
| 0013 | Sidewalk concrete, remove (202-52710) | SYS | 272 | $23.00 | $16.00 | $15.00 | $26.00 | $9.00 | $26.00 |
| 0014 | Barrier wall, concrete, remove (202-94954) | LFT | 325 | $59.00 | $50.00 | $75.00 | $200.00 | $190.00 | $77.00 |
| 0015 | Excavation, common (203-02000) | CYS | 330 | $32.00 | $75.00 | $55.00 | $86.00 | $150.00 | $182.00 |
| 0016 | Borrow (203-02070) | CYS | 162 | $88.00 | $50.00 | $22.00 | $55.00 | $250.00 | $75.00 |
| 0017 | Lagging, precast concrete (203-02588) | SYS | 405 | $326.00 | $500.00 | $308.25 | $410.00 | $320.00 | $504.00 |
| 0018 | Stormwater management budget (205-12108) | DOL | 6,162 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $1,500.00 | $5,000.00 | $8,500.00 | $8,600.00 | $15,000 | $7,121.00 |
| 0020 | Subgrade treatment, type IC (207-09935) | SYS | 970 | $52.00 | $55.00 | $45.50 | $73.00 | $72.00 | $42.00 |
| 0021 | Compacted aggregate, no. 8 (301-12233) | CYS | 64 | $170.00 | $140.00 | $110.00 | $270.00 | $175.00 | $150.00 |
| 0022 | Compacted aggregate, no. 53 (301-12234) | CYS | 16 | $370.00 | $350.00 | $500.00 | $210.00 | $300.00 | $173.00 |
| 0023 | HMA patching, full depth, type B (304-12623) | TON | 93 | $489.00 | $375.00 | $285.00 | $480.00 | $825.00 | $293.00 |
| 0024 | HMA patching, partial depth, type B (304-12624) | TON | 55 | $285.00 | $300.00 | $350.00 | $460.00 | $825.00 | $308.00 |
| 0025 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 2,169 | $3.00 | $4.00 | $7.00 | $11.00 | $10.00 | $8.40 |
| 0026 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 181 | $205.00 | $225.00 | $225.00 | $160.00 | $260.00 | $235.00 |
| 0027 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 65 | $225.00 | $225.00 | $225.00 | $340.00 | $190.00 | $235.00 |
| 0028 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 206 | $124.00 | $225.00 | $225.00 | $250.00 | $190.00 | $235.00 |
| 0029 | Joint adhesive (401-11526) | LFT | 1,030 | $0.50 | $1.00 | $1.00 | $1.10 | $0.10 | $1.00 |
| 0030 | Asphalt for tack coat (406-05520) | TON | 2 | $1.00 | $600.00 | $600.00 | $980.00 | $1.00 | $627.00 |
| 0031 | Sidewalk, concrete (604-06070) | SYS | 272 | $94.13 | $90.00 | $102.50 | $68.00 | $71.00 | $74.00 |
| 0032 | Curb and gutter, concrete, type C (605-06150) | LFT | 610 | $36.04 | $35.00 | $44.00 | $76.00 | $33.00 | $34.00 |
| 0033 | Monument, type B (615-06505) | EACH | 1 | $1,500.00 | $2,500.00 | $1,000.00 | $2,100.00 | $2,800.00 | $1,463.00 |
| 0034 | Geotextile for riprap, type 2A (616-12248) | SYS | 438 | $10.00 | $9.00 | $4.75 | $8.75 | $10.77 | $6.30 |
| 0035 | Water (621-06567) | KGAL | 2 | $2.00 | $2.00 | $0.10 | $0.10 | $0.10 | $0.10 |
| 0036 | Sodding (621-06574) | SYS | 289 | $18.90 | $32.00 | $21.00 | $22.00 | $27.00 | $22.00 |
| 0037 | Field office, type C (628-09403) | MOS | 12 | $2,802.50 | $2,500.00 | $5,175.00 | $4,400.00 | $3,151.71 | $4,159.00 |
| 0038 | Computer system equipment (628-11976) | EACH | 2 | $1,080.00 | $1,000.00 | $825.00 | $1,600.00 | $800.00 | $832.00 |
| 0039 | Pile, steel H, HP, 12 X 84 (701-95782) | LFT | 1,650 | $197.00 | $235.00 | $185.00 | $189.00 | $202.00 | $216.00 |
| 0040 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 432 | $25.00 | $15.00 | $6.25 | $35.00 | $35.00 | $23.00 |
| 0041 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 108 | $85.00 | $25.00 | $90.00 | $70.00 | $52.00 | $37.00 |
| 0042 | Geotextile for underdrains, type 1A (718-12305) | SYS | 432 | $6.00 | $6.00 | $6.00 | $3.50 | $5.00 | $7.00 |
| 0043 | Casting, catch basin, adjust to grade (720-12796) | EACH | 1 | $1,750.00 | $1,650.00 | $1,250.00 | $4,900.00 | $1,750.00 | $1,617.00 |
| 0044 | Casting, manhole, adjust to grade (720-12798) | EACH | 1 | $1,800.00 | $1,500.00 | $1,250.00 | $4,900.00 | $1,750.00 | $1,617.00 |
| 0045 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 1,820 | $2.00 | $1.68 | $3.15 | $1.75 | $1.68 | $3.90 |
| 0046 | Temporary transverse pavement marking, removable, 6 in. (801-06217) | LFT | 128 | $3.00 | $1.98 | $3.15 | $2.00 | $1.98 | $6.10 |
| 0047 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 32 | $10.00 | $10.53 | $12.95 | $11.00 | $10.53 | $19.00 |
| 0048 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 720 | $3.00 | $1.93 | $4.25 | $2.00 | $1.93 | $5.70 |
| 0049 | Construction sign, type A (801-06640) | EACH | 8 | $200.00 | $251.00 | $165.00 | $251.00 | $251.00 | $172.00 |
| 0050 | Construction sign, type B (801-06645) | EACH | 12 | $100.00 | $155.00 | $120.00 | $160.00 | $155.00 | $125.00 |
| 0051 | Maintaining traffic (801-06775) | LS | 1 | $30,000 | $20,000 | $152,719 | $31,000 | $49,402 | $343,000 |
| 0052 | Barricade, type III-A (801-07118) | LFT | 34 | $15.00 | $16.98 | $16.00 | $17.00 | $16.98 | $17.00 |
| 0053 | Temporary curb ramp (801-11990) | EACH | 4 | $2,500.00 | $2,000.00 | $3,725.00 | $7,900.00 | $6,844.18 | $5,735.00 |
| 0054 | Portable signal (801-12081) | LS | 1 | $45,000 | $65,000 | $38,000 | $30,000 | $39,700 | $22,670 |
| 0055 | Driveway assistance device (801-12482) | EACH | 2 | $6,000.00 | $15,000 | $15,000 | $3,000.00 | $9,000.00 | $25,440 |
| 0056 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 10 | $45.00 | $25.00 | $35.00 | $45.00 | $90.00 | $104.00 |
| 0057 | Sign, sheet, relocate (802-07060) | EACH | 2 | $800.00 | $200.00 | $85.00 | $800.00 | $400.00 | $1,045.00 |
| 0058 | Grooving for pavement markings (808-12032) | LFT | 1,220 | $2.00 | $0.88 | $0.98 | $0.90 | $0.88 | $1.00 |
| 0059 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 1,220 | $3.00 | $1.23 | $1.25 | $1.25 | $1.23 | $1.30 |
| 0060 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 10 | $700.00 | $425.00 | $1,100.00 | $1,700.00 | $3,200.00 | $1,567.00 |
| 0061 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 10 | $350.00 | $200.00 | $650.00 | $1,500.00 | $2,300.00 | $1,045.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.